Check the design pressure first based on which the hydro test pressure has been set from your end . Hydrotest need not be designed as per code.
--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to
materials-weld...@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
----------------------------------------------------------------------------------------------------------
Information transmitted by this E-MAIL is intended only for the use of the addressee(s) and contains information that is privileged, confidential or exempt from disclosure under applicable law. If you are not the intended recipient or it appears that this mail has been forwarded to you without proper authority, you are notified that any use or dissemination and or copying of this email in any manner is strictly prohibited and you are requested to delete this e-mail immediately.
Communicating through e-mail is not secure and capable of interception and delays. Any one communicating with TATA Consulting Engineers Ltd., and / or its subsidiaries or associates or group companies by e-mail accepts the risks involved and their consequences.
While this e-mail has been checked for all known viruses, the addressee should also scan for viruses and notify the originator of e-mail.
---------------------------------------------------------------------------------------------------------
Check the design pressure first based on which the hydro test pressure has been set from your end . Hydrotest need not be designed as per code.
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of JIJILAL K M
Sent: Wednesday, May 9, 2018 12:26 PM
To: material...@googlegroups.com
Subject: [SOCIAL NETWORK] [MW:27814] Pipeline Hydro test pressure calculation
Dear Experts,
For the pipeline hydro test calculations,what is the pressure in bar required to produce hoop stress equal to 4341.45 kg/cm2?
--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to material...@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/BMXPR01MB2341FACB2356FFE57A7EB16AEBA10%40BMXPR01MB2341.INDPRD01.PROD.OUTLOOK.COM.
Ing. José Juan Jiménez Alejandro
Independent Consultant in Parts
and Pressure Equipment
SSI-TPI
Móvil +52 1 812 352 4606
Skype: jjjimeneza