WPS QUALIFICATION

53 views
Skip to first unread message

shanky gupta

unread,
Apr 26, 2017, 6:19:14 AM4/26/17
to Materials & Welding
Dear experts,

Good morning

Myself shanky gupta working with L&T Modular fabrication yard, Sohar Oman.
I'm in a bit confusion about applicable edition in WPS. In our case project cut off date is 31st march 2015 so that all international codes also applicable earlier to cutoff.

Now our WPS are approved as per AWS D1.1 edition 2015 but as per cut off date it should be in edition 2010.

Please suggest me for this.