the above specifications states EFW welding whereas the supplier offers SAW pipes could you please advise this is acceptable or not.
Quote:
5.2 Welding:
5.2.1 The joints shall be double-welded, full-penetration
welds made in accordance with procedures and by welders or
welding operators qualified in accordance with the ASME
Boiler and Pressure Vessel Code, Section IX.
5.2.2 The welds shall be made either manually or automatically
by an electric process involving the deposition of filler
metal.