I would like to know how to better to use the "matrix reloaded" feature in combination with the "copy artefacts".
I have a matrix build that has 3 dimensions: component, platform
server, win => OK , build=1
client, win, => OK , build=1
client, mac => OK , build=1
at the end, the artefacts are archived.
server, win => OK , build=2
client, win => FAIL
client, mac => OK , build=2
when one of those 6 fails, I would like to be able to do a new build, to rebuild the failed component
client, win => OK, build=3
now, I have another build that does a "copy artefacts" from this matrix build.
I have the impression it takes the artefacts from build 1 and build 3, and not those of build 2...
2 questions:
1) how do I get to "copy artefacts" from the "last successful sub-build" rather than the "last successful build"?
2) how do I get the "build=3" to be incremental using the "matrix reloaded" plugin? there is a parameter to pass the "incremental" flag,
but either I can specify that parameter, and build all components, or I use the "matrix reloaded" plugin, but then I cannot override the parameter....
thanks for providing some thoughts about how to handle this.
-- lode