jessebs commented on Improvement JENKINS-43826
 
Re: Exclude skipped stages from estimated duration calculation

When only works if the stage was skipped because of a foreseen reason.  If the stage is skipped because a previous stage failed, then the skipped stages are on the order of a few milliseconds and are considered during the average stage time calculation.