Massachusetts legislative reform requires more than lip service

360 views
Skip to first unread message

Anthony D'Isidoro

unread,
Jan 5, 2025, 5:29:45 PMJan 5
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Massachusetts legislative reform requires more than lip service (The Editorial Board, Boston Globe: January 5, 2025)
Closed door meetings, few roll calls, and top=down rule won't cut it in 2025.


On Beacon Hill the Legislature ended the year in much the same way it operated throughout the 2023-24 session. Only a handful of lawmakers were in their seats to witness the final passage of two major health care bills and nearly 100 pieces of legislation, enacted during a marathon 14-hour session.

There were no roll-call votes. And odds are that few lawmakers other than those in leadership and the half-dozen members of the conference committees that drafted the health care bills behind closed doors knew what was actually in them before the pro forma voice votes were taken.

Welcome to the Massachusetts Legislature — a body with a propensity to work in secret and to draft rules that guarantee each and every member is beholden primarily not to the voters who sent them there but to the House speaker and Senate president from whom all power and most perks are derived.

It is a body that remains exempt from public records and open meeting laws — thus allowing most of its real work, including drafting a state budget, to be done in secret. Legislative leaders have been so adamant about maintaining that way of life, including shielding its inner workings from the scrutiny of the state auditor, that Auditor Diana DiZoglio opted to go to the voters last fall to win the right to audit the Legislature’s books.

And voters spoke loudly — with 72 percent voting their approval of the measure. But that overwhelming vote is no guarantee of success.

“We’ll be solely focused on following that law,” DiZoglio told the editorial board, “even as legislative leaders remain focused on stymieing transparency, not supporting it.”

When lawmakers convened on New Year’s Day for their swearing-in ceremonies for the new session, House Speaker Ron Mariano and Senate President Karen Spilka certainly paid a good deal of lip service to the idea of rules reform. But calling something a “reform” doesn’t make it so.

“It’s great to say that you are interested in rules reform after 72 percent of the voters say they want more transparency in the General Court,” DiZoglio said. “But the reality is there has to be a cultural shift for any new rules to work. And right now the real power lies in the hands of just a few.”

Spilka and Mariano both indicated in their opening day speeches that revisiting the July 31 deadline to end formal sessions in election years — a practice abandoned this year and in 2022 — would be among those “reforms.” Spending more time in formal session would at least provide more opportunities for roll-call votes, which require more members to actually be in the chamber and publicly indicate whether they support the legislation being voted on. Spilka also suggested moving up committee reporting deadlines for bills — which would help address the leisurely pace of legislative activity that causes some of those end-of-session logjams.

“I would hope in the new session we will redouble our efforts to make sure that substantive, complex matters are taken up in formal sessions with the predictability, the accountability, and the full consideration that they deserve,” said Senate Minority Leader Bruce Tarr, during a speech on the Senate floor Monday.

DiZoglio, a former legislator, agrees, suggesting that at minimum rules reform should include more recorded roll-call votes and a requirement giving lawmakers at least 72 hours to read a bill before having to vote on it.

“The real problem is they’re constantly suspending their own rules,” she added.

But structural reform, the kind that might provide transparency throughout the legislative process and the all-important budgeting process, is still far off.

The process of co-opting the 22 new lawmakers joining the Legislature this year — and keeping the old ones in line — begins almost immediately as the speaker and Senate president announce their leadership teams and new committee chairs and vice chairs. Each of those jobs brings extra pay — and as a Globe analysis last year showed, some of those committees have little or no reason to exist other than to provide financial rewards for soldiers who stay loyal to leadership.

Globe reporters Emma Platoff and Laura Crimaldi found that at least a dozen committees had not held a single hearing during the period of the analysis nor considered a piece of legislation. With this year’s 11 percent hike in base pay (to $82,044) and travel stipend (an additional $22,431 and $29,908) no one will make under $104,000. Committee chairs will now get at minimum $22,000 to $44,000 extra tacked on to their salary. In the Senate with 40 members and 42 standing committees, eight leadership posts for Democrats and another three for Republicans, everyone gets something extra — and then some.

It doesn’t have to be this way. Congress, for all its own flaws, provides extra pay only to the House speaker, the president pro tempore of the Senate, and the House and Senate majority and minority leaders. And yet somehow members of Congress are still eager to vie for committee chairmanships.

The California Legislature follows the congressional model.

Modest reform in Massachusetts could certainly start by jettisoning those committees that no longer seem to be needed — as demonstrated by their workload. DiZoglio suggests adding a modicum of democracy, encouraging members to campaign for chairmanships among their colleagues and allowing the “full body” to participate in the process.

But extra pay isn’t the only way leaders buy loyalty. There’s also the tried and true method of allowing lawmakers to “bring home the bacon,” by spreading around taxpayers’ dollars for local earmarks in the state budget — a dog park here, a game room at the local senior center there. Last year the Massachusetts Taxpayers Association put the number of House earmarks alone at 748, adding more than $80 million in new spending to the then $58 billion budget.

But the not so well-kept secret of closed-door budgeting is that those with the power — Mariano, Spilka, House Ways and Means Chair Aaron Michlewitz — are those whose districts benefit the most. Shocker, right. And then there are the so-called “stealth earmarks” — the ones adopted at the last minute in the legislative process as “consolidated amendments” — whose contents are pretty much a mystery to the rank and file until they’re passed.

Again, Congress provides a model for at least a modest reform — a requirement that every such amendment must carry the name of its congressional sponsor.

And let’s not forget this is allegedly a full-time Legislature, with nearly all lawmakers making well into six-figure salaries — and yet at least half reporting outside jobs or business interests. How much those outside interests actually represent isn’t known in many cases because the state’s financial disclosure law is so outdated — its top bracket indicating only if the job brought in $100,000 or more.

The Massachusetts Legislature, among the least transparent in the nation, is ripe for reform. The protestations of its leaders notwithstanding, it’s only the vigilance and pressure from voters that can make that happen. Now there’s a New Year’s resolution worth taking on.

Anthony D'Isidoro

unread,
Jan 6, 2025, 5:06:20 PMJan 6
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Quincy Democrat breaks from Mass. Senate colleagues in rare move (Chris Van Buskirk, Boston Herald: January 5, 2025)

Beacon Hill witnessed something rare this past week.

A Democratic state senator from Quincy publicly rebuked Senate President Karen Spilka’s reelection to the chamber’s top leadership post. Sen. John Keenan opted to vote “present” during Spilka’s reascension to the Senate President’s Office because of what he said were the branch’s poor marks on transparency.

He said his vote was “indicative that I don’t support her reelection.”

“We have to be more open, participatory, more inclusive going forward, and I think we have to respect the right of our constituents to know where we are on issues,” he told reporters.

Transparency and efficiency are quickly becoming major issues of the 2025-2026 legislative session, which kicked off Wednesday after lawmakers closed out the previous two-year term by passing almost 100 bills during a 14-hour meeting that lasted past midnight.

In twin speeches this past week, both Spilka and House Speaker Ron Mariano said they are planning to propose internal rules changes in the coming month that will aim to bolster public confidence in the legislative process.

The pledges came after legislators blew past multiple major deadlines in the 2023-2024 legislative session but eventually completed work on all major priorities that were left hanging at the conclusion of formal business over the summer.

In her speech, Spilka said she wants to move up the deadline for reporting bills out of legislative committees from the second year to the first year of a legislative session and introduce more transparency into the secretive negotiating process for compromise bills.

Keenan said Spilka’s ideas did not change his mind.

“I appreciate her comments. I appreciate her leadership. I appreciate what she does as Senate president. I just have a disagreement as to how as an institution, business should be conducted,” he said.

Spilka, who wields a large influence in the Senate over things like lucrative committee assignments, said Keenan “certainly has the right to do” what he wants.

“But I again go back to all of what the Senate has accomplished and how we have been leaders in transparency, and we’ll continue to be and evolve and make some changes, and some I laid out, and I’m sure there will be others,” she told reporters.

Keenan’s dissatisfaction with transparency in the Senate comes as State Auditor Diana DiZoglio is attempting to investigate the Legislature following the successful passage of a legislative audit law in November.

DiZoglio has faced resistance from Spilka and Mariano, who have argued a legislative audit is not necessary and violates separation of power principles outlined in the state constitution. The issue is likely going to end up in court.

Keenan said he supports a legislative audit but believes there should be “limits on what the auditor should do.”

“I’m respectful of the separation of powers, and I think that will ultimately be addressed. But in terms of being more open and transparent, clearly, the voters have sent a message to us that they believe that we should be,” he said. “Hopefully we will be open and transparent as we go through the next session.”

Anthony D'Isidoro

unread,
Jan 6, 2025, 9:13:45 PMJan 6
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
What to watch for on Beacon Hill in 2025 (Michael P. Norton, State House News Service: January 6, 2025)

BOSTON (SHNS) – A new year and new legislative session have arrived, and there are already loads of pressing issues that appear ripe for attention from Gov. Maura Healey, Senate President Karen Spilka, House Speaker Ronald Mariano and the rest of Beacon Hill’s extended cast of lawmakers, regulators and bureaucrats.

Mindful that there is almost certain to be a handful of major issues that unexpectedly pop up and demand attention from the governor’s administration and Legislature this year, here’s a look at some of the already simmering issues that could rise to a rolling boil in 2025:

MBTA BUDGET CRISIS: To many on Beacon Hill, MBTA officials warning that the agency doesn’t have enough money feels like the boy who cried wolf — but even in that fable, the wolf did eventually show up. It looks like that could be the case in 2025: the T has already spent down its pandemic aid and savings, and now its leaders have few immediate options to navigate a budget gap forecast to be around $700 million. Slashing the T’s spending probably will not get much traction after a concentrated — and, arguably, successful — effort in the last 18 months to staff up and invest in service improvements. Beacon Hill power players might be gearing up for yet another debate about how to fund the MBTA in the long term, informed by a task force that got an extension on the report that was due to Gov. Healey by the end of 2024 and buoyed by surging surtax revenues that must be earmarked for transportation or education. “There’s going to be more work around transportation, for sure,” Healey told the News Service in her year-end interview last month. – Chris Lisinski

SURTAX “SURPLUS”: The voter-approved surtax on high earners has been a bright spot for state budget managers, who otherwise are dealing with uneven tax collections. After the Legislature and Gov. Healey built the fiscal 2024 budget using a conservative estimate for surtax collections, the actual haul far outpaced that figure, leaving more than $1.2 billion in additional money set aside for future investments in transportation and education. Top Democrats already have their eyes on spending down that pot, and House budget chief Aaron Michlewitz signaled in October “we’ll probably have to use all of it” on transportation in particular. Healey and the Senate will have their own ideas. The timing overlaps with a pivotal debate at the MBTA, which is facing a massive budget gap starting July 1 that raises the specter of service cuts without additional state aid. Of course, when there’s money to be distributed, everyone wants a piece, so lawmakers are likely to face sustained lobbying efforts and internal debate on the best way to carve up the funding. Having a dedicated pool of money to spend on a handful of pressing issues early in the session could make some springtime budget decisions less painful as Beacon Hill braces for another tight budget year in fiscal 2026. – Chris Lisinski

WATCHING THE WALLET: Even with relatively low unemployment and state reserves at a historic high, most of Beacon Hill expects fiscal 2026 will be a challenging budget year. Softening non-surtax revenue collections, spending demands inflated by pandemic-era initiatives and a mountain of uncertainty about the direction of key federal policies all suggest policymakers may need to take a more active role in budget management. “We’re really worried about FY ’26,” Senate Ways and Means Chair Michael Rodrigues told reporters in December. But even before fiscal 2026 can begin on July 1, the state has to navigate through the second, riskier half of what has been a year of mixed results so far. The budget watchdogs at Mass. Taxpayers Foundation said in December that they do not think Healey will have to make the same kind of midyear budget cuts she did last January, but DOR projects that collections will end the year short of the current target so something may have to give. January collections, which DOR is due to report by Feb. 5, will be especially telling. That month is the start of a crucial six-month period for the state’s coffers. Collections are not split evenly across the 12 months and the second half of the fiscal year (January through June) typically produces about 60 percent of the state’s annual tax revenue, officials have said. The second half of the budget year also tends to be more volatile for tax collections. – Colin A. Young

LEGISLATIVE RULE CHANGES: Top Democrats once again failed to complete a long list of top priorities before the July 31 end of formal sessions in 2024. But unlike past terms when anything left in limbo died, lawmakers crafted workarounds to keep big action during — and after — election season a possibility. With that experience under their belts, legislative leaders are now eyeing more formal changes to their internal rules that would permanently amend the even-year July 31 target that has governed their operations for decades. To secure any alterations, though, Democrats will need to find agreement in an area where they have not had success for years: for two straight sessions, the House and Senate did compromise on joint rules, leaving previous iterations in place on an ostensibly temporary basis. The year ahead will also bring renewed fighting over legislative transparency as Auditor Diana DiZoglio presses ahead with her voter-empowered bid to audit the Legislature, and top Democrats weigh whether to comply or to maintain their resistance. – Chris Lisinski

FAMILY SHELTERS: The humanitarian and financial crises associated with the state’s family shelter system continue to drag into 2025. Funding for the emergency shelters is set to run out in January, and this looming shortfall will likely make appropriations and policy reform one of the first major bills for the new Legislature. While the concept of rapidly rehousing homeless families makes for a good catchphrase, it has proven difficult to implement. The state is now spending $1 billion annually on family shelter costs — more than double what it used to cost — and Gov. Healey has promised to move families out of expensive hotels and motels. Healey and lawmakers will likely agree on policies that move the state farther away from the traditional “right to shelter” model, with reforms to the system that guarantee less time in emergency housing for families. This issue remains a significant political challenge for Democrats, and conservatives are likely gearing up to make the issue central to their opposition campaigns to high-profile figures seeking reelection, like Boston Mayor Michelle Wu this year and Healey in 2026, if she chooses to run for governor again. – Sam Drysdale

MILTON ZONING CASE: Milton’s long-running zoning spat with the state over the MBTA Communities Act could reach a resolution in mid-February, or potentially sooner, whenever the Supreme Judicial Court makes its expected decision in the case brought by Attorney General Andrea Campbell in an attempt to force the Boston suburb to comply with a 2021 zoning law. The town argues that the only consequence the Legislature prescribed for non-compliance is loss of certain state grant eligibility. The AG sued the town almost a year ago, Feb. 27, 2024, for violating the law — which requires 177 communities with or adjacent to MBTA service to allow multi-family zoning by right in some areas — after Milton residents voted to spike a zoning plan that Milton Town Meeting had approved. The SJC’s decision could influence whether other municipalities in eastern Massachusetts choose to embrace or reject denser zoning as required by the law. But the majority of municipalities that have already faced their deadlines to comply with the law have done so. Campbell and top state officials view the law as a key tool for tackling Massachusetts’s housing crisis. – Alison Kuznitz

TRUMP TERM TWO: Gov. Healey, who as attorney general sued Donald Trump roughly 100 times, seems poised to take a less adversarial approach when the president-elect returns to the White House this month. A day after the election, Healey was no longer on the offensive castigating Trump and seemed markedly somber when telling reporters that she and Lt. Gov. Kim Driscoll “will work with anyone to make life better for residents in our state.” Healey has momentarily regained some of her partisan fierceness in television interviews, saying days later that she would “absolutely not” fulfill a hypothetical request from the Trump administration for Massachusetts State Police to assist with mass deportations. From her perch now in the corner office, Healey needs to strategically weigh how battling Trump could risk Massachusetts losing out on federal funding, a key resource that her administration regularly competes for against other states. Health and Human Services Secretary Kate Walsh said state officials are focused on working with their federal counterparts, particularly in protecting Medicaid dollars. But Attorney General Andrea Campbell, who may be taking the baton from Healey and going on the offensive, has said she’s worried about how the Trump presidency could impact access to reproductive and gender-affirming care — even with the commonwealth’s abortion shield law passed in the aftermath of the Dobbs ruling. Campbell has said she plans to review that law and others to ensure they are strong enough to withstand future challenges. – Alison Kuznitz

LEGAL INJECTION SITES: Lawmakers dropped the controversial idea to pursue supervised injection sites in a substance abuse law last year, but supporters are likely to continue to push the policy. With opioid-related deaths declining but still at crisis levels, the Senate embraced the sites, also known as overdose prevention centers, where people can use illegal drugs under the supervision of trained health care workers. Supporters say they are a life-saving tool to tamp down on the devastating effects of the opioid crisis, which has been exacerbated by the pervasive presence of fentanyl in the drug supply. Opponents note the sites are illegal under federal law and say they would encourage illegal drug use. The Senate-backed policy died in private opioid bill talks with the House. Injection sites have the support of Gov. Healey’s Public Health Commissioner, Robbie Goldstein. Healey hasn’t publicly said much about whether she supports the idea, and it remains to be seen whether she or Goldstein will put up more of a fight for them in the new session. – Sam Drysdale

UNEMPLOYMENT INSURANCE UNCERTAINTY: In state government, $2.5 billion can still go a long way, and so the possibility that Massachusetts could wind up owing that much back to the federal government for a Gov. Charlie Baker-era error has the chance to cause quite a few headaches. It’s been more than 18 months since the Healey administration revealed that Massachusetts mistakenly paid $2.5 billion in pandemic-era jobless benefits using federal dollars, not state dollars, and the U.S. Department of Labor still has not said whether the state will need to repay some or all of that total. Some onlookers think the incoming Trump team will be less inclined to give deep-blue Massachusetts a break. If the state does wind up on the hook, it’s possible Beacon Hill moves to pass along the costs to employers, who are already facing higher UI costs as a result of upheaval during the COVID-19 crisis. That move will raise competitiveness questions. – Chris Lisinski

MCAS & GRADUATION: After voters approved Question 2 to eliminate the MCAS exam graduation requirement, Massachusetts is suddenly searching about for a new statewide standard. Gov. Healey has made clear that she wants a uniform graduation model that ensures equity across districts, and plans to bring together stakeholders this year to come up with a solution that abides by the vote law. Education Committee Co-Chair Sen. Jason Lewis said he plans to file a bill requiring MassCore completion for all students, which would mandate a certain curriculum, as an alternative to the exam requirement that voters scrapped. Critics argue that such a move will have to be coupled with strong oversight to ensure equity across districts, and it would require additional funding from the state, as some schools lack the resources to fully implement MassCore. Some business groups that opposed the ballot question say they’ll try to convince leaders that the current MCAS system should stay in place until an alternative can be set up, though the Massachusetts Teachers Association — which financially backed Question 2 — says that’s out of the question. As the state works on a replacement, there is pressure on districts to certify that students are meeting the statewide competency requirements to earn diplomas. – Sam Drysdale

TEACHER STRIKES: If the past is prologue, teachers strikes are likely to continue and even accelerate in the new year. Educator unions have been pushing the boundaries of the Bay State’s law against public workers’ strikes in recent years, and seem to be upping the ante with an eye towards making a political statement against the labor policy. As teacher contracts expire next year and educators stare down the cost of living crisis across the state, more local unions may choose the path that has now won a number of pay increase victories already, despite court fines and opposition from Gov. Healey and powerful lawmakers. Plus, the Massachusetts Teachers Association and Massachusetts branch of the American Federation of Teachers might try to build on their success at the 2024 ballot box by circumventing a reluctant Legislature and petitioning directly to voters to make teacher strikes legal in 2026 or future years. – Sam Drysdale

BLOWIN’ IN THE WIND: Will 2025 finally be the year that Massachusetts gets meaningful power from offshore wind? The only project to have even begun turbine construction since the 2016 law that launched the Bay State’s pursuit of wind power got a few megawatts of power in 2024 before a blade disintegrated and brought everything to a grinding halt. Last year’s procurement of more wind power didn’t live up to its full billing, the process was repeatedly delayed, and one of the three projects chosen has backed out before contracts could be negotiated. And now, new contracts for the projects that remain aren’t due to be finalized until offshore wind opponent Donald Trump will be back in the White House later this month and there could be even greater uncertainty around the economic conditions that wiped out the state’s project pipeline in 2022 and 2023. “It’s important that we bring this back online. It is a very, very important industry to Massachusetts,” Gov. Healey said in August about the Vineyard Wind 1 project and sector generally. “It’s very important for the clean energy future, and I’m confident we get there.” Political and economic concerns aside, wind boosters now too have to consider the threat that public favor could turn against the clean energy movement as costs soar and ratepayers resist the shift. – Colin A. Young

STEWARD RIPPLE EFFECTS: The remnants of the Steward Health Care crisis will continue to reshape the state’s fragile health care system, as six hospitals adjust to new owners backed by a state aid package totaling at least $417 million over three years. Two work groups focused on the voids left by the closures of Carney Hospital in Dorchester and Nashoba Valley Medical Center in Ayer are expected to provide recommendations in early 2025 about community health care needs and ways to improve access to care. UMass Memorial has considered alternative uses for Nashoba, like transforming the hospital’s emergency room into an urgent care facility. Under-construction Norwood Hospital, which Steward abandoned, remains closed, and the Healey administration says it’s looking for a new operator to finish the project and resume health care services. The Health Policy Commission will be keeping close tabs on Revere Medical, the former Steward physician group acquired by an affiliate of a private equity company. – Alison Kuznitz

SOUTH COAST RAIL: Passenger rail service is expected to return to Taunton, Fall River and New Bedford for the first time since 1958 when the long-awaited MBTA commuter rail expansion to the South Coast begins service in May. Once service starts, all major cities within 50 miles of Boston will have commuter rail access to the state’s capital. Versions of the project have been under debate and development for years and the go-live date has repeatedly been postponed. “I’m optimistic,” Fall River Rep. Alan Silvia said in 2017. He added, “We all want to ride this train before I go to heaven – especially me.” The $1.1 billion project’s first phase will activate about 36 miles of existing tracks for commuter rail service with stations in Middleborough, East Taunton, Freetown, Fall River and New Bedford. The eventual full build is expected to extend the existing Stoughton Line south with stations in Easton, Raynham and Taunton before connecting with the Fall River and New Bedford lines. – Colin A. Young

MONEY FOR THE ENVIRONMENT: The big bond bills of 2024 were related to housing and economic development, but lawmakers have already begun lobbying for their pet projects and priorities in the environmental bond bill forthcoming from the Executive Office of Energy and Environmental Affairs. As they ran out of options for advancing some provisions when lawmaking came to a head for the session last summer, some lawmakers mentioned that they would withdraw their ideas with the intention of trying to get the language into the under-development enviro bond bill. Bond bills authorize a maximum amount of capital spending, but not every dollar authorized becomes reality since the state is constrained to a much lower limit on annual borrowing. The most recent capital plan lists a fiscal 2025 bond cap of $303 million for EEA, with a cap of $1.555 billion over the five-year plan. – Colin A. Young

MAYORAL ELECTIONS: If history is any guide, at least some lawmakers from the 33 cities that will vote for mayor in 2025 will think about throwing their hats into the ring (especially knowing they would not have to give up their legislative seat unless they win). Mayor Michelle Wu’s reelection effort in Boston headlines the pack, but four-year terms are also on the ballot in Easthampton, Everett, Framingham, Holyoke, Lawrence, Lynn, Newburyport, Newton, Northampton, Salem, and West Springfield. The Office of Campaign and Political Finance said voters will elect mayors for two-year terms in Agawam, Attleboro, Beverly, Brockton, Chicopee, Fall River, Fitchburg, Gardner, Gloucester, Haverhill, Leominster, Marlborough, Medford, Methuen, North Adams, Peabody, Somerville, Taunton, Westfield, Woburn, and Worcester. – Colin A. Young

2026 STATEWIDE ELECTIONS: It takes name recognition, time and money to build a statewide following and any candidate hoping to win one of the six constitutional offices up for grabs in 2026 will need to start early. Gov. Healey hasn’t said if she will run for a second term and said in December that she would start thinking about that possibility at some point this year. Be on the lookout for a potential primary opponent for Auditor Diana DiZoglio, whose push for more accountability from the Legislature has rankled insiders in the General Court. Congressman Joseph Kennedy III didn’t shy away from a challenge in 2020 when he tried, unsuccessfully, to unseat U.S. Sen. Ed Markey. Other officeholders must decide whether they will take a run at Markey in 2026, and some of the more veteran members of the state’s Congressional delegation will also need to decide whether to keep going, or call it quits. 

Anthony D'Isidoro

unread,
Jan 7, 2025, 10:12:58 AMJan 7
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
[cid:48c7083c-4494-4aba-a98f-65f002e30a9f]

[cid:569aa730-4bde-404a-9e91-db513ff5d6ff]

[cid:2c012aa1-c77b-408d-b8da-27c8ed439530]

[cid:7c353a7f-a84d-4d8c-ae8f-2814b54084ae]

[cid:b301be26-5c28-4b72-9c77-3053bf0edb31]

[cid:aa41228b-5b68-4ba9-a42c-eb5ebb386049]

Anthony D'Isidoro

unread,
Jan 7, 2025, 11:45:14 AMJan 7
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

APPLICATION DEADLINE: FRIDAY, JANUARY 10TH AT 5:00 PM.

The Harvard Allston Partnership Fund was created by Harvard University and the City of Boston, in collaboration with the Allston-Brighton community, to support neighborhood improvement projects, cultural enrichment, and educational programming in North Allston-Brighton. Learn more about the Partnership Fund:
https://edportal.harvard.edu/harvard-allston-partnership-fund

Online applications are requested for the 17th round of grant awards for the Harvard Allston Partnership Fund (HAPF). A total of $200,000 is available in one-year grants to community-based organizations that provide programs and services to residents of Allston-Brighton. Please see the detailed instructions in the Request for Proposals (RFP) for more information. The RFP contains specific priorities and conditions for funding.

Purpose: A total of $200,000 is available in one-year grants to community-based organizations that provide programs and services to residents of Allston-Brighton. The HAPF is looking forward to seeing the myriad ways partners generate thoughtful responses that will best serve our neighbors.

APPLY (UP TO $10,000):
https://harvarded.submittable.com/submit/f795e773-73dd-4419-803a-b26e6cdca85e/the-harvard-allston-partnership-fund-2024-up-to-10-000

APPLY (UP TO $25,000):
https://harvarded.submittable.com/submit/2a767009-5b8b-4c13-9177-26e9e6315b0a/harvard-allston-partnership-fund-2024-up-through-25-000

Please email edpo...@harvard.edu with questions.


Anthony D'Isidoro

unread,
Jan 7, 2025, 1:42:01 PMJan 7
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

Anthony D'Isidoro

unread,
Jan 7, 2025, 9:06:58 PMJan 7
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Cities with the worst traffic delays per driver worldwide (in hours)
Boston was the fifth most congested city in the United States and the 12th globally.

                                                                                                                         Hours

Source: INRIX Global Traffic Scorecard                                                                                                                                Flourish logoA Flourish chart

SHANNON LARSON, GLOBE STAFF                           



Anthony D'Isidoro

unread,
Jan 8, 2025, 9:40:58 PMJan 8
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com


On Tuesday, January 7, 2025, the Boston Public Schools recommended the closing of the Mary Lyon Pilot High School and the reconfiguration of the Mary Lyon K-8 to a PreK-6 school. The changes will take effect after the 2025-26 school year.

Excerpt from Boston Globe article:

Mary Lyon Pilot High School

Allston/Brighton’s Mary Lyon Pilot High School offers school-wide inclusion for all students — those with special needs, particularly emotional and behavioral disabilities, and those without — along with its sister school, the Lyon K-8. The lower school was founded as a K-5 in 1992. The high school was approved in 2008 and sits in the former home of Garfield Elementary, built in 1925.

In the last five years, its utilization rate has been just 40 percent; it scores a zero out of four on building experience and lacks the spaces to offer a full continuum of services, according to district data.

The majority of Lyon students are Black or Latino and about one-third have disabilities. The Lyon K-8 is also slated to change, to a PreK-6 school, and the existing Lyon High building, which already houses Grades 7 and 8 of the lower school, could remain in use by that school.

Anthony D'Isidoro

unread,
Jan 9, 2025, 7:05:48 PMJan 9
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
ACA keeping an eye on Beacon Park Yards (Jeff Sullivan, The Bulletin: January 9, 2025)

 

The Allston Civic Association (ACA) met recently and discussed the neighborhood reaction to a recent proposal for the Beacon Park Yards. 

The Beacon Park Yards, which currently has a huge number of rail cars sitting in it, is slated to be cleared and redeveloped for the neighborhood, fully stocked with a new commuter rail stop by Lower Allston (adjacent to the Boston University Football Fields) and a bus hub. This just a part of the Allston Multimodal Project, which will also move the trajectory of Route 90/the Mass Pike opening up more room for homeownership housing and development which community members have historically pushed for. Allston has some of the worst homeownership rates in the city hovering around 12 percent (neighboring Brighton is not much better at around 20 per cent). 

ACA President Tony D’Isidoro said the state is now looking to use at least part of Beacon Park Yards as a layup facility - a place to store trains when not in use. He said the community vehemently opposed that, and it looks like the state and the MBTA heard residents’ concerns. 

“We’ve been at this now for 11 years, trying to take advantage of a once-in-a-lifetime opportunity to restore and reconnect our community and provide for a regional multi-modal network that would be impactful for years and years to come,” he said. “Earlier this year, the Massachusetts Secretary of Transportation ruled out any chance of having a layup yard in Beacon Park Yards and we were very happy about that, but just recently in a letter regarding Amtrak it seems to have come back on the negotiations.” 

D’Isidoro said it was a bit confusing, as Amtrak doesn’t really have any rights to Beacon Park. “The T does have some contractual understandings with Harvard University – not with the City of Boston – as to some possible layup capabilities,” he said. “We are very supportive of east/west rail and building an outstanding world class rail system, and we know because of that there has to be some layup capabilities somewhere along the line. We just simply don’t think that Beacon Park Yards is the place to do that.” 

D’Isidoro pointed out that last year, the MBTA paid $255 million for the 24-acre Widett Circle next to I-93 and said he felt that was a better location. “And given that the City of Boston owns some property around that, most experts believe that is the perfect location to locate this layup facility,” he said.

D’Isidoro said he met with Governor Healey, heads of the Massachusetts Department of Transportation and the MBTA and others recently, and said it was made clear that the layup yard would be strongly opposed. 

“We will know their decision in two or three months,” he said. “They are currently conducting a rail study, which I will show you as soon as we get a copy of it and we are hoping the preferred alternative does not use Beacon Park Yard.” 

In other news, the ACA and community members are looking into how they can influence the Boston City Council and the Capital Budgeting process to make sure the Jackson Mann Boston Centers for Youth and Families (BCYF) Community Center replacement project gets funding to move forward as soon as possible. 

The Jackson Mann was deemed too old and decrepit to operate as a community center about two or three years ago, but since there has been no other suitable facility, the city is still using it as the only BCYF community center in Allston and Brighton. 

“We want to make sure our community is accounted for in that capital budget,” D’Isidoro said. 

Charlesview Director Jo Ann Barbour said they are starting up a grassroots campaign to show the city what kind of support there is. “We are in the process of putting together a post card writing campaign, and so stay tuned in terms of when that will happen, probably shortly after the first of the year,” she said. “We want to flood the Mayor’s Office with post cards. I think there will be other people doing petitions and letter-writing campaigns and things like that. We’re going to keep the heat on in terms of the need for a community center in Allston Brighton.” 

Barbour added that the community is going to likely start its own fundraising efforts to get the community center pushed through. “So more on that later, but right now we want to keep the heat on with the mayor and BCYF around the need for a new Jackson Mann in Allston Brighton,” she said. “But those post cards will be out there soon.” 

D’Isidoro said the turnout at the October City Council hearing on the subject was monumental. “I know for a fact that people at City Hall got the message,” he said. “They were very impressed with the turnout. At times we just got to get off the couch and show we’re not dead, we’re still here and we just give so much to the city and sacrifice an awful lot. We try to accommodate the initiatives the city is pushing, we show up at the meetings and we support as much as we can, and all we’re asking for is some reciprocal considerations for that effort. There is no reason why Allston Brighton should not have a first-class community center.” 

For more information on the ACA and to see recorded meetings, go to allstoncivicassociation.org

Boston Bulletin (January 9, 2025):

Anthony D'Isidoro

unread,
Jan 10, 2025, 8:56:04 AMJan 10
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

Mayor Wu’s 2025 Property Tax Relief Calculator will show you how much you would have saved on property taxes under Mayor Wu’s proposed tax relief plan.
Mayor Wu fought to protect Boston residents from seeing a sharp increase in property taxes this year. This tax relief plan was approved by the City Council and State House of Representatives, but was not approved by the State Senate.
enter your address or estimated property value, and compare the current property tax rate with the rate under the tax relief plan.


Anthony D'Isidoro

unread,
Jan 10, 2025, 10:00:14 AMJan 10
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
[cid:bacd3f88-5bfc-4725-84de-47b46ffa79c8]

[cid:636be618-143f-4cf8-88ae-2f1525741859]

[cid:973e12a1-982d-446a-9fb6-65d5107e6c2c]

[cid:4e68c81e-9801-4d40-b17f-b0f68be84cec]

[cid:8a4a91fa-2776-47af-b911-b4a359820e71]

[cid:b9c3a09d-057d-4b0c-ab36-792dcd59f6d7]

[cid:f6a50ab5-14a7-4dd5-b5e2-a56bde415dae]

[cid:693eafb9-e1db-4b17-bd96-5de6d7bb69fb]

sarah correia

unread,
Jan 10, 2025, 11:03:23 AMJan 10
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
I wish Mayor Wu had done this before the tax bills went out as the speculation about the new rate and amount of tax led me at least to look up various sources trying to figure out what the increase would be when in the end the amount I owned was 10% more than last year so no problem at all.

Sarah B Guest Perry (Correia)

On Friday, January 10, 2025 at 10:20:02 AM EST, <lesch...@gmail.com> wrote:


How does that help with the tax bill 😡!!!!!

Sent from my iPhone

On Jan 10, 2025, at 6:56 AM, Anthony D'Isidoro <anthony...@msn.com> wrote:


Outlook-fnbd4r4j.jpg
--
You received this message because you are subscribed to the Google Groups "Cleveland Circle Community" group.
To unsubscribe from this group and stop receiving emails from it, send an email to cleveland-circle-co...@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/cleveland-circle-community/LV3P222MB088610130F87812C9F63DD4EAF1C2%40LV3P222MB0886.NAMP222.PROD.OUTLOOK.COM.

--
You received this message because you are subscribed to the Google Groups "Cleveland Circle Community" group.
To unsubscribe from this group and stop receiving emails from it, send an email to cleveland-circle-co...@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/cleveland-circle-community/66E14583-03BE-4B63-B93D-097CD9432FA8%40gmail.com.

Anthony D'Isidoro

unread,
Jan 10, 2025, 3:11:18 PMJan 10
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
The Boston Public Health Commission (BPHC) Wastewater Monitoring program monitors COVID-19, Flu, and RSV by measuring viruses in wastewater across the City of Boston.


Please note: The laboratory that tests Boston's wastewater changed on August 1, 2024. Data may not be comparable due to the different methods used by the old and new lab. Boston Public Health Commission closely monitors the data and the methods used to communicate these results. We will continue to provide updates when methods change.








Anthony D'Isidoro

unread,
Jan 10, 2025, 6:48:23 PMJan 10
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Harvard Construction Mitigation (Week of January 13, 2025)   

January 10, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
  • Thermal striping in the Harvard Business School lot will take place in the spring.
Enterprise Research Campus

Residential/Hotel
  • On Saturday, January 11, green exterior panels will be installed on the midrise and high rise using boom lifts. Hotel insulation and roofing membrane will be installed. Miscellaneous interior work with hoists operational is planned.
  • Windows and panels are also being installed during the week on the residential buildings.
  • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
  • Storefront installation is underway on the ground floors.
  • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
  • Elevators are being installed.
  • Other smaller concrete operations continue including a topping slab at the podium deck between the hotel and residential buildings.
  • Roofing activities are underway.
  • MEP work is ongoing.
  • Framing is taking place inside the buildings.
  • Temporary heaters are operating.
Laboratory and Office Buildings.
  • On Saturday, January 11, curtain-wall panels will be installed using the tower crane. Roofing activity, mechanical penthouse work and miscellaneous general cleanup will be underway.  A drywall delivery will take place.
  • Exterior curtain-wall panels are being installed during the week. Boom lifts are active around the perimeter of the buildings.
  • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
  • Smaller concrete operations continue.
  • Roof activities are underway.
  • Elevators are being installed.
  • MEP work is ongoing.
  • Mechanical penthouse activities continue.
  • Masonry work continues.
  • Framing is underway.
  • Temporary heaters are operational.
Greenway
  • Backfilling continues with the site leveling off.
  • Lower level activities are finishing up with shallow utilities to start.
Treehouse Conference Center
  • Mass timber activities will take place on Saturday, January 11. A crane will be in operation.
  • Mass timber deliveries, activities and installation of the roof continue on the south side with a crane operating during the week.
  • Façade frame installation continues and glass installation begins using boom lifts.
  • MEP activities are ongoing. 
Building Mock-Ups
  • Building mockups are on the corner of Hague and Rotterdam Streets.
Eversource Conduit Project
  • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. This public utility work is not under the supervision of ERC.
General
  • Snow and ice removal and cleanup will take place as needed.
  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
  • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
  • Drones will be in use bi-weekly to monitor construction progress on site.
    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
    • Weekly flights are weather dependent and are scheduled one weekday morning.
    • A drone is scheduled to fly Thursday, January 16 from 7 a.m. to 9 a.m.
Signage Project at SEC and Stadium Way
  • A signage installation project in front of the SEC building will be finishing up.
  • Barriers surround the work area.
North Allston Storm Drain Extension Project (NASDEP)
The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
  • South of Science work between Rena Path and Rotterdam Street will continue this week.
  • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
  • Three weeks of excavation work for preclearing began on Thursday, January 9. Workers in protective clothing will be meeting all regulatory requirements during this activity.
92 Seattle Street
  • Renovation for reuse of this Harvard building is complete, and some final punch list items will be completed during winter break.
  • Harvard Capital Projects will make adjustments to tenant spaces starting on January 8.  
175 North Harvard Street, 100 South Campus Drive 
The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
  • The structural steel phase of the housing project is finishing on upper levels, and the final steel delivery took place last week. Steel decking installation and detailing continues and expected to be complete by Friday, January 24. Concrete deck placements will continue on upper levels to the roof and should be complete in early February. Mechanical, electrical, and plumbing trades are working throughout the site. Work continues working on small utilities, including storm, duct bank, and data and is backfilling around the foundation. Crews are fireproofing on several levels. This work will continue progressing up the building.
  • The crane is scheduled to be removed by early February. The height of the temporary construction hoist will need to be increased in the next couple of weeks before the crane is removed. More details will be provided as that work gets closer.
  • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be heard off-hours. Some tarping is removed at the lower floors after the fireproofing is complete.
  • For the next several weeks through Friday, January 24, a combination of activities at both the new affiliate housing building and American Repertory Theatre (ART) projects will require the closure of South Campus Drive to all vehicles Monday through Friday from 7 a.m. to 5 p.m. All traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5 p.m. and on weekends. Signage and details will be provided to divert traffic as needed and police details will be on site to provide assistance.
  • Concrete deck placements continue on the upper levels to the roof level during regular work hours throughout this month – some finishing work will extend beyond 9 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
  • The tower crane will be in use for the next few weeks during normal working hours. The crane is scheduled to be disassembled and removed from the site during the first week of February. Because this is a sizeable undertaking, the crane removal will require some after-hours work. More detail will be provided as the date gets closer.
  • Wheel washing and street sweeping continues to ensure soil is not being tracked through the neighborhood streets.
  • On the new American Repertory Theater (ART) work site, interior concrete walls and piers will continue after this through the first week of January. Concrete placements and detailing will continue through January. Exterior wall waterproofing is ongoing. Backfilling for exterior walls and excavating for utilities continues. Utility work continues around the building perimeter. Steel installation is complete, and the crane has been demobilized. Steel detailing for the theatre’s stage and fly tower structure and concrete placements will run through January.
  • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow in late February. A crane to support this work will mobilize mid-February.
  • Work continues on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently.
  • Crews at the affiliate housing building site will be working on Saturdays, January 11 and 18, weather permitting, to perform some welding and continue installing the structural steel. They will also be using the tower crane to install stairs. Heaters will be maintained by workers on Sundays through the winter.
  • Off hours snow and ice removal are expected as needed.
  • Both job sites will be closed on Monday, January 20, in observance of the Martin Luther King, Jr. Day holiday.
  • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
210 North Harvard Street
  • Eversource or Verizon will remove an old pole and power line.
  • The bakery Sofra is open. 
168 Western Ave
  • Crews will begin excavation for preclearing soil inside the site.
  • Interior work continues.
  • Minor prep work will take place at 9 Travis Street to relocate the Swiss Bakers bakery operation at the end of the month while their space gets renovated.

CONTACT US 


6:00 am – 6:00 pm

Construction Mitigation 

Hotline: (617) 496-0857
Email:
 mitig...@csl-consulting.com 

For After-Hours Emergencies

Harvard Operations 

Phone: (617) 495-5560


Anthony D'Isidoro

unread,
Jan 13, 2025, 8:12:10 PMJan 13
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Hello Everyone,

Thank you, Senator Keenan, and Senator Tarr for having the political courage to state the obvious.

Given, the Senate President is in the process of appointing her leadership team, committee chairs and committee members, don't expect a rush to the finish line for other members to show similar political courage. 

Tony

Mass. Senate isn’t transparent. Here’s how to fix that. (John F. Keenan and Bruce Tarr, Globe Opinion: January 13, 2025)
Our ‘business as usual’ risks public faith.


We are concerned: The public is losing faith in how the Legislature goes about its work, and something needs to be done about it.

For the second time in a row, the last formal session of our two-year legislative session ended in July with a 24-hour mad dash to finish as much work as possible. Throughout the night and into the morning, the Legislature scrambled, trying to pass bills that it had 18 months to research, discuss, negotiate, and send to the governor. While this work did result in some bills passing, critically impactful bills related to economic development, climate, hospital closures, and substance use disorder did not get done by the deadline of the formal session despite their potential to help millions of Massachusetts residents.

The Legislature has settled into the disturbing practice of leaving bills to the last minute, often with long lists of differences between Senate and House versions and producing little but disappointment for those we are supposed to serve. Lawmakers had the time, energy, and resources to consider and vote on all of these bills, yet we failed.

As a result of the Senate’s failure to finish bills during formal session, important legislative business had to be done through informal sessions. We had to use a less transparent and inclusive format designed for simpler, less impactful legislation in order to pass complicated bills.

For example, on Oct. 3, the Senate Committee on Ways and Means polled its members on a bill to modernize child custody jurisdiction laws. Committee members had only an hour to decide whether to advance this 28-page bill, which replaces an entire chapter of the state’s general laws. The bill then quickly advanced to the full Senate, where senators were put in the unfortunate position of being expected to pass the bill without reviewing it and decide whether to object to it or offer amendments, and without a recorded vote.

The two of us worked to delay this vote to ensure that we, our colleagues, and the public had time to consider its merits carefully. Little did we know at the time that this was just the first of many comprehensive bills that would be moved swiftly to the Senate floor.

By the end of informal sessions in December, a 320-page economic development bill, a 139-page clean energy bill, two health care bills totaling 110 pages, a 45-page bill relating to money transmission by the Division of Banks, a 27-page insurers solvency fund bill, and a 52-page substance-use disorder and recovery coach bill all moved quickly from committees to the Senate floor where they were passed, most gaveled through without roll-call votes, and one without even cursory discussion on the Senate floor or a roll-call vote.

We want to make clear that our objections are not necessarily with the substance of the bills but rather with the process. The standards of review and transparency that should apply to all major statewide policy bills were not applied to the passage of these bills. For the public, such nonparticipatory, nontransparent practices deny opportunities for them to contact their legislators to express support or concerns. These practices erode the public trust in the legislative process and the Legislature itself.

We come from different political parties. We have respectful differences on a variety of issues, but most importantly we share a respect for the Senate as an institution and for the abilities of its members. We share a growing sense of concern that the Senate requires major changes to function more effectively and transparently. In the next few weeks, the Senate will consider rules for the 2025-26 session. Many changes will be proposed, but we believe that at least the following two will move the Senate toward being more participatory, open, accountable, and transparent.

First, we will work to change the practice of remote participation with rules that encourage more in-person participation during formal sessions, and remote participation only when circumstances demand it. Remote participation hinders the relationship-building that is critical to legislating and hampers the ability of members to offer, review, and react to amendments, resulting in less inclusive and less robust debates. Procedurally, hybrid sessions hinder the legislative process as senators, the Senate clerk, court officers, and staff struggle to stay in contact and efficiently record votes.

Second, we propose that conference committees, which receive bills that have passed the Senate and House but have differences that require reconciling, release their reports long before the waning hours of the last formal session.

This change will give members sufficient time to thoroughly read and understand bills. At the same time, it will give the public access to these reports and an opportunity to comment.

To accept how we concluded formal sessions in July and the two-year legislative session in December would normalize a process that runs contrary to participation, accountability, transparency, and effectiveness. The Legislature must end what has become “business as usual.”

Change is necessary. If the public cannot trust how we make our laws, how can they trust the laws we make?

John F. Keenan is a Democratic state senator representing the Norfolk and Plymouth district. Bruce Tarr is the Republican Senate minority leader representing the First Essex and Middlesex district.

Anthony D'Isidoro

unread,
Jan 14, 2025, 2:15:07 PMJan 14
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Boston College Football

Dates are set. Sign up now.
Link is in our bio.


Anthony D'Isidoro

unread,
Jan 14, 2025, 5:02:51 PMJan 14
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

Age Strong

Age Strong & the Veronica B Smith Multi Services Senior Center sincerely thank the VBS Board of Directors for their many years of dedication & service to making the senior center a welcoming & warm place for Allston/Brighton residents. We also thank them for the generous donation, which will help expand programming & provide upgrades to the center.

Anthony D'Isidoro

Having accomplished its original mission, as we wind down the functions of the VBS Board of Directors, I want to thank everyone who served as members and officers on the Board.

Under the leadership of Lauren Basler and Jackie McLaughlin, the Veronica B. Smith Multi-Services Senior Center is well positioned to meet the ever-changing needs of older adults in our community.

Everything from trips and special events to fine arts and crafts, music and dance, lifelong learning, and fitness and health programs, as well as volunteering opportunities, have generated energy and excitement at the center.

As more older adults age in place in the city, the center becomes an even more integral part of our community. Thank you for all you do.

Photo: Front Row (L-R) Jenn Christie, Age Strong Commissioner Emily Shea, Karen Smith, Mayor Michelle Wu, Marisa Angilletta
Back Row (L-R) Anthony D'Isidoro, Curt Bletzer

Anthony D'Isidoro

unread,
Jan 14, 2025, 9:24:32 PMJan 14
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Lawmakers say they want transparency, but they don’t want to talk about it (Adrian Walker, Boston Globe: January 14, 2025)


Our lawmakers have been holding meetings about increasing transparency at the State House.

But, true to form, no one wants to talk about what was discussed in the transparency meetings. Several legislative leaders refused to discuss their talks with the State House News Service, which reported on the conversations. The ones I called also weren’t talking.

That irony sums up the state of affairs on Beacon Hill as the Legislature begins another session.

Maybe it isn’t fair to suggest that nothing has changed. After a year of getting pounded for their back-room dealings — most notably in the Globe’s “State Secrets” series — powerbrokers have made halting efforts to claim they are ready to change their ways.

Senate President Karen Spilka and House Speaker Ron Mariano have both suggested that they want to make it easier for the public to know what the Legislature is doing.

But it’s the details that matter, and there doesn’t seem to be much agreement on exactly how this more open government is going to work.

Just to review, much of the work of the Legislature is done by the committees that consider bills before they go to the full House (or Senate) for consideration.

But the committee process has steadily gotten more opaque over time. There is no requirement that written testimony be publicly available. When committees decide whether or not a bill will advance to the full chamber, the committee votes themselves are not publicly revealed.

Want to know whether your legislator voted to advance a bill you care about, or to squash it? Under current rules governing House and joint committees, you have no right to know.

Transparent, it is not.

The secrecy doesn’t end there, of course. Another cherished form of legislative privacy is the caucus.

Lawmakers of each party huddle together every week or so to plan strategy, decide what legislation to advance, and so on. These powwows have been secret for as long as anyone can remember. Caucuses are exempt from the state’s public meeting laws designed to let the public behind the curtain.

A House speaker once burst into laughter when I asked if I could sit in on a caucus for a story I was writing about him.

“Even if I let you in — which I won’t — it wouldn’t be a real caucus with you in the room,” Tom Finneran assured me. “Because no one would say anything.”

Years later, there is still little discernible sentiment for opening up these meetings, where so much is decided. The rule of omerta is alive and well when it comes to caucuses.

Transparency on Beacon Hill is an odd thing. Everyone claims to support it in theory. The problem is, there’s no longstanding form of secrecy they are prepared to give up. Even the easiest and most obvious reforms — like making committee votes and testimony public and transparent — never seem to make it across the finish line, no matter how often leaders pledge support for change.

It’s not hard to understand why. These are matters of arcane rules and processes. Lawmakers believe that most voters, busy leading their lives, glaze over at these process debates. They think that as long as they say the right things, few will notice or care that they didn’t really mean it.

A lot of history says they’re right about that. But maybe that is starting to change.

As frustration mounted over the last, lazy session that ended formal sessions last July, lawmakers seemed to be taking the negative public sentiment more seriously than usual. As major legislation piled up without action, the cries to know why so little was getting done grew in volume.

Perhaps that was part of the reason that Governor Maura Healey, in a December interview with the Globe, said she would support expanding the state’s public records laws to include the executive branch and the judiciary — with the caveat that “the right exemptions” need to be in place.

Add to that the constant demands for transparency by State Auditor Diana DiZoglio — and the challenge to reform the old ways of doing business have gotten harder to brush aside.

Perhaps that will lead to meaningful change. It’s hard to say.

If they are really serious about letting the public in, the transparency debate would be a great place to start.

Anthony D'Isidoro

unread,
Jan 15, 2025, 2:01:28 PMJan 15
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

Anthony D'Isidoro

unread,
Jan 15, 2025, 2:36:58 PMJan 15
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Mayor Michelle Wu and the City of Boston’s Office of Youth Engagement (OYEA) announced free tickets are now available for the 2025 Mayor’s Youth Summit (MYS), an annual, citywide celebration of the contributions of young people to Boston’s culture. With support from many local, youth-serving partner organizations and City departments, the 2025 Summit will be held 5:00 - 8:00 p.m. on Saturday, February 22 at the Artists For Humanity EpiCenter, a vibrant arts center for youth, located in South Boston. The Mayor’s Youth Summit, which resumed last year under Mayor Wu’s leadership, builds on her commitment to making Boston a home for everyone and ensuring our city’s youth have the tools to reach their fullest potential.

To learn more about and reserve free tickets for the 2025 Mayor’s Youth Summit, please visit boston.gov/youth-summit





Anthony D'Isidoro

unread,
Jan 17, 2025, 7:52:21 PMJan 17
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Safety concerns top battery meeting in Brighton (Jeff Sullivan, The Bulletin: January 16, 2025)

The proponent for the battery energy storage system (BESS) facility at 35 Electric Ave. in Brighton, Flatiron Energy, held a site walk with about 30 residents on Saturday, despite the snowy conditions. The site now houses the Welch Corporation, which deals with construction and site work across the city, but Flatiron partner Bret Cullen said the current owner is looking to retire, and Flatiron will be taking over the site for the installation of the battery network.

The proposed building is 64,000 square feet going up to a height of about 50 feet within 2.84 acres. Cullen said the battery clusters themselves will encompass about 5,000 square feet within the buildings, and he said the company will be installing the latest and greatest safety procedures. 

The discussion in Welch’s garage focused on safety issues The biggest issue for abutting residents – several meeting participants identified themselves as direct abutters – concerned fire and smoke. Cullen said according to the studies the consultant Flatiron hired, the gases emitted are not that much more dangerous than a normal house fire. 

“There is no data to support that it is any more dangerous than if a house on Parsons Street caught fire,” Cullen said. 

BESS fires have been known to emit hydrogen fluoride, which, when combined with water, forms hydrofluoric acid (https://tinyurl.com/ 2fmypfxa), which is highly dangerous and corrosive. A recent study of the Vista Morro Bay BESS project near LA did find hydrogen fluoride – as well as several other toxic chemicals – in extensive battery fire testing it conducted, but the study found the levels of toxic chemicals to be within acceptable levels (https://tinyurl.com/ 4x733v86). However, the study did stipulate in several pages that those levels were based on very specific conditions, including the weather, and could change given the right parameters (of which they did not study for the project). 

A big problem with these fires is thermal runaway. That’s when one battery cell gets too hot, ignites and starts the process for the next cell, creating a large fire within the system. The buildup of flammable gases can also, sometimes, result in an explosion. Cullen said for this system, they are using a fire suppression method called direct injection, wherein water or another agent is injected into a single battery cell when the cell heats up too much or smoke or gas is detected. According to several companies pitching the suppression method, it is the best way to stop thermal runaway, basically stopping it before it can spread (https://tinyurl.com/mw8tuvsh

Residents were also concerned that the increased hazard to the neighborhood would make home insurance either unaffordable or unattainable. Cullen said if that happened, the company would pay the insurance. He did not answer the follow up question as to what would happen if the homeowners could not sell their homes because of the perceived danger of the site. 

Several residents said they also felt that there were no other examples of BESS systems being installed in such close proximity to residential housing. Cullen said there are examples of similar sites, and Eversource is currently proposing a BESS and possibly a substation (https://tinyurl.com/4tbp66c6) near Cummins Highway and Pleasantview Street on the Roslindale, Mattapan and Hyde Park lines. 

“The Wellesley Fire Department just approved a similar situation and the New York Fire Department regularly approves these facilities,” Cullen said. 

“Would you put it on your street?” one resident said. 

“I would, yes,” said Cullen. 

Much of the site walk outside the garage, when it took place, dealt with landscaping and flood mitigation through the use of green infiltration methods and water retention. The 35 Electric Ave. project is being handled by the City of Boston Planning Department’s Article 80 Large Project Review process, specifically for its zoning and land-use implications. Cullen said there will be multiple other agencies and processes to approve the project from other avenues, like safety, fire prevention and the like. 

But that means that there will be a community benefits package that residents have to provide feedback for, and Cullen said that will be coming in the next few weeks and will be completely informed by residents. However, the company did look at areas it could improve to make the facility more palatable. They said since there won’t be a lot of parking on the site compared to what’s there now landscape consultant Dan Adams said he believes planting new evergreens all around the facility would help with noise mitigation as well as beautification. 

For the community benefits, which would be separate from the landscaping plan, Cullen said there is a small lot across the street, about 5,000 square feet, that could be a pocket park, snow parking, or something else the community would like to see. He said they just need to go through the process and figure out what would work best there for residents. 

For more information on the project and to see upcoming meetings, go to https:// tinyurl.com/4z29bzvt

Boston Bulletin (January 16, 2025):

Anthony D'Isidoro

unread,
Jan 18, 2025, 6:01:26 PMJan 18
to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
Harvard Construction Mitigation (Week of January 20, 2025)   

January 17, 2025

Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
  • Thermal striping in the Harvard Business School lot will take place in the spring.
Enterprise Research Campus
Residential/Hotel
  • On Saturday, January 18, crews may be conducting a sprinkler main flush, which will result in water being discharged onto Trotting Avenue and into drainage system near the site on Hague Street. Other Saturday work includes installation of panels and some windows on the residential buildings. Hotel insulation and roofing membrane will be installed. Miscellaneous interior work with hoists operational is planned.
  • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
  • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
  • Storefront installation is underway on the ground floors.
  • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
  • Elevators are being installed.
  • Other smaller concrete operations continue including a topping slab at the podium deck between the hotel and residential buildings.
  • Roofing activities are underway.
  • MEP work is ongoing.
  • Framing is taking place inside the buildings.
  • Temporary heaters are operating.
    Laboratory and Office Buildings.
    • On Saturday, January 18, curtain-wall panels will be installed using the tower crane and boom lifts. Roofing activity and miscellaneous general cleanup will be underway.  A drywall delivery will take place.
    • Exterior curtain-wall panels are being installed during the week. Boom lifts are active around the perimeter of the buildings.
    • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
    • Smaller concrete operations continue.
    • Roofing activities are underway.
    • Elevators are being installed.
    • MEP work is ongoing.
    • Mechanical penthouse activities continue.
    • Masonry work continues.
    • Framing is underway
    • Temporary heaters are operational.
    Greenway
      • Backfilling continues with the site leveling off
      • Some drainage work is underway.
      Treehouse Conference Center
      • Mass timber and façade activities will take place on Saturday, January 18. A crane will be in operation.
      • Mass timber deliveries, activities and installation of the roof continue on the south side with a crane operating during the week.
      • Façade frame installation continues using boom lifts.
      • MEP activities are ongoing. 
      Building Mock-Ups
      • Building mockups are on the corner of Hague and Rotterdam Streets.
      Eversource Conduit Project
      • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. Crews are near Travis Street.  This public utility work is not under the supervision of ERC.
      General
      • Minimal construction work will be taking place on the Martin Luther King holiday on Monday, January 20.
      • Snow and ice removal and cleanup will take place as needed.
      • The project’s work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
      • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
      • Drones will be in use bi-weekly to monitor construction progress on site.
        • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
        • Weekly flights are weather dependent and are scheduled one weekday morning.
        • Drone flights are scheduled to fly Tuesday/Wednesday from 9 a.m. to 2 p.m. Thursday, January 23 from 9 a.m. to 2 p.m.
      Signage Project at SEC and Stadium Way
      • A signage installation project in front of the SEC building will be finishing up.
      • Barriers surround the work area.
      North Allston Storm Drain Extension Project (NASDEP)
      The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
      • The jobsite will be open on Martin Luther King Day (Monday, January 20).
      • South of Science work between Rena Path and Rotterdam Street will continue this week.
      • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
      • Three weeks of excavation work for preclearing continues this week. Workers in protective clothing will be meeting all regulatory requirements during this activity.
      92 Seattle Street
      • Renovation for reuse of this Harvard building is complete, and some final punch list items are being completed during winter break.
      • Harvard Capital Projects are making adjustments to tenant spaces.  
      175 North Harvard Street, 100 South Campus Drive 
      The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
      • The structural steel phase of the housing project is finishing on upper levels. Steel decking installation and detailing continues and is expected to be complete this month. Concrete deck placements will continue on upper levels to the roof and should be complete in early February. Mechanical, electrical, and plumbing trades are working throughout the site. Work continues working on small utilities, including storm, duct bank, and data and is backfilling around the foundation. Crews are fireproofing on several levels. This work will continue progressing up the building. Crews are backfilling foundations and performing site work.
      • The tower crane will be in use for the next few weeks during normal working hours. The crane is scheduled to be disassembled and removed from the site during the first week of February. Because this is a sizeable undertaking, the crane removal will require some after-hours work. More detail will be provided as the date gets closer.
      • The height of the temporary construction hoist will need to be increased to the roof in the next couple of weeks before the crane is removed. More details will be provided as that work gets closer.
      • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be heard off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
      • For the next several weeks, a combination of activities at both the new affiliate housing building and American Repertory Theatre (ART) projects will require periodic closures of South Campus Drive to all vehicles during working hours Monday through Friday from 7 a.m. to 5 p.m. All traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5 p.m. and on weekends. Signage and details will be provided to divert traffic as needed, and police details will be on site to provide assistance.
      • Occasional concrete deck placements continue on the upper levels to the roof level during regular work hours throughout this month – some finishing work will extend beyond 9 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
      • Wheel washing and street sweeping continues to ensure soil is not being tracked through the neighborhood streets.
      • On the new American Repertory Theater (ART) work site, interior wall placements were complete last week. Concrete placements and detailing will continue through January. Exterior wall waterproofing is ongoing. Backfilling for exterior walls and excavating for utilities continues. Utility work continues around the building perimeter. Steel detailing for the theatre’s stage and fly tower structure and concrete placements will run through January. An additional crane is needed to dismantle boom lifts from the slabs at the end of January.
      • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow beginning on Monday, February 24. A crane to support this work will mobilize mid-February.
      • Work continues on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently.
      • Crews at the affiliate housing building site will be working on Saturdays, January 18 and 25, weather permitting, to perform some welding and to install some steel sections. Heaters will be maintained by workers on Sundays through the winter.
      • Off hours snow and ice removal are expected as needed.
      • Both job sites will be closed on Monday, January 20, in observance of the Martin Luther King, Jr. Day holiday.
      • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
      210 North Harvard Street
      • Eversource or Verizon will remove an old pole and power line.
      • The bakery Sofra is open. 
      168 Western Ave
      • Crews will continue excavation for preclearing soil inside the site fence.
      • Interior work continues.
      • Minor prep work will take place at 9 Travis Street to relocate the Swiss Bakers bakery operation at the end of the month while their space gets renovated.

      Anthony D'Isidoro

      unread,
      Jan 27, 2025, 9:18:32 AMJan 27
      to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
      Harvard Construction Mitigation (Week of January 27, 2025)   

      January 24, 2025

      Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

      • Thermal striping in the Harvard Business School lot will take place in the spring.
      Enterprise Research Campus

      Residential/Hotel
      • On Saturday, January 25, activities include installation of panels on the residential buildings. Storefront ground floor work may take place at the midrise. Hotel soffits and glass will be installed on level 13. Elevator and other miscellaneous interior work with hoists operational are planned.
      • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
      • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
      • Storefront installation is underway on the ground floors.
      • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
      • Elevators are being installed.
      • Other smaller concrete operations continue including a topping slab at the podium deck between the hotel and residential buildings.
      • Roofing activities are underway.
      • MEP work is ongoing.
      • Framing is taking place inside the buildings.
      • Temporary heaters are operating.
        Laboratory and Office Buildings.
        • On Saturday, January 25, pipes will be delivered and unloaded using the tower crane. Exterior soffits will be installed using boom lifts. Glass installation will take place on level 1. Interior framing and mechanical work in the lower level will be underway. 
        • Exterior curtain-wall panels are being installed during the week.
        • Boom lifts are active around the perimeter of the buildings.
        • Level 1 exterior work is underway.
        • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
        • Smaller concrete operations continue.
        • Roofing activities are underway.
        • Elevators are being installed.
        • MEP work is ongoing.
        • Mechanical penthouse activities continue.
        • Masonry work continues.
        • Framing is underway
        • Temporary heaters are operational.
        Greenway
        • Backfilling continues with the site leveling off
        • Some drainage work is underway.
        Treehouse Conference Center
        • Mass timber and façade activities will take place on Saturday, January 25. A crane will be in operation
        • Mass timber deliveries, activities and installation of the roof continue on the south side with a crane operating during the week.
        • Façade frame installation continues using boom lifts.
        • Possible concrete core placements if weather permits.
        • MEP activities are ongoing. 
        Building Mock-Ups
        Building mockups are on the corner of Hague and Rotterdam Streets.

        Eversource Conduit Project

        Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. Crews are near Travis Street.  This public utility work is not under the supervision of ERC.

        General
        • Snow and ice removal and cleanup will take place as needed.
        • The project’s work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
        • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
        • Drones will be in use bi-weekly to monitor construction progress on site.
          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
          • Weekly flights are weather dependent and are scheduled one weekday morning.
          • A drone is scheduled to fly Thursday, January 30 from 7 a.m. to 9 a.m.
        Signage Project at SEC and Stadium Way
        • A signage installation project in front of the SEC building will be finishing up.
        • Barriers surround the work area.
        North Allston Storm Drain Extension Project (NASDEP)
        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
        • South of Science work between Rena Path and Rotterdam Street will continue this week.
        • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
        • Excavation and installation of the support system to install structures will take place.
        • Science Drive sidewalk will close, and pedestrians will be shifted to the SEC walkway when manhole work takes place in mid-February.
        92 Seattle Street
        • Renovation for reuse of this Harvard building is complete, and some final punch list items remain.
        • Delivery for handrails on the east entrance expected to arrive on January 28 with installation to follow.
        175 North Harvard Street, 100 South Campus Drive 
        The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
        • The structural steel phase of the housing project is finishing on upper levels. Steel decking installation and detailing is expected to be complete by the end of this month. Concrete deck placements will continue on upper levels to the roof and should be complete in early February, weather permitting. Mechanical, electrical, and plumbing trades are working throughout the site. Crews continue fireproofing on several levels. This work is progressing up the building. Crews are backfilling foundations and performing site work.
        • The tower crane will be in use for the next few weeks during normal working hours as crews continue to work through winter weather conditions. The crane is currently scheduled to be disassembled and removed from the site in mid-February. Because this is a sizeable undertaking, the crane removal will require after-hours work. More detail will be provided as the date gets closer.
        • The height of the temporary construction hoist continues to be increased to the roof and will be complete in the next few weeks before the crane is removed. More details will be provided as that work gets closer.
        • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be heard off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
        • For the next several weeks, work at the new affiliate housing building will require closures of South Campus Drive to all vehicles during working hours Monday through Friday from 7 a.m. to 5 p.m. All traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5 p.m. and on weekends. Signage and details will be provided to divert traffic as needed, and police details will be on site to provide assistance.
        • Occasional concrete deck placements continue on the upper levels to the roof level during regular work hours throughout this month – some finishing work will extend beyond 9 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
        • Wheel washing and street sweeping continues to ensure soil is not being tracked through the neighborhood streets.
        • On the new American Repertory Theater (ART) work site, concrete placements and detailing continues through January. Backfilling for exterior walls and excavating for utilities continues. Utility work continues around the building perimeter. Steel detailing for the theatre’s stage and fly tower structure and concrete placements will run through January. An additional crane will be on site to support the removal of boom lifts from lower levels on Thursday, January 31.
        • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow beginning on Monday, February 24. A crane to support this work will mobilize mid-February.
        • Adjustments continue on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for f lashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently.
        • Crews at the affiliate housing building site will be working on Saturdays, January 25 and February 1, weather permitting, adding the upper levels of the material hoist, performing some welding and installing some steel sections. Heaters will be maintained by workers on Sundays through the winter.
        • Off hours snow and ice removal are expected as needed.
        • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
        210 North Harvard Street
        • Eversource or Verizon will remove an old pole and power line.
        • The bakery Sofra is open. 
        168 Western Ave
        • Crews will continue excavation trenches for utilities and will place concrete pads for dumpsters and refrigeration units.
        • Interior work continues.
        • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated.

        Anthony D'Isidoro

        unread,
        Jan 27, 2025, 9:37:10 AMJan 27
        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com








        Anthony D'Isidoro

        unread,
        Jan 31, 2025, 9:52:16 AMJan 31
        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
        Planning approves 23-25 N. Beacon (Jeff Sullivan, The Bulletin: January 30, 2025)


        The Boston Planning and Development Agency Board (BPDA) of the City of Boston Planning Department (CBPD) voted unanimously on Thursday to approve the proposed 25-unit rental development at 23-25 N. Beacon St. in Allston. 

        The approval, however, did not occur before some questions were asked and answered. The proposed 25-unit rental building, which is set to replace the only three-family still standing on that particular corner of Union Square, is owned by Alpha Management. 

        As previously reported in The Bulletin, Alpha racked up more than 200 property code violations in recent times according to the Boston Inspectional Services Department (ISD) Code Enforcement website, as well as a few building code violations more than five years ago. Attorney Johanna Schneider said at the BPDA meeting that Alpha has been working with the city to resolve these issues, 95 percent of which she said involved improper trash storage.

        BPDA Board Member Kate Bennett asked about the property code violations and what Alpha’s been doing to ameliorate that at its 29 properties. 

        Schneider said Alpha has contracted a consultant to audit trash practices at its 29 properties (the citations for lack of snow shoveling were not discussed at the meeting). She said Alpha, ISD and the consultant have been going back and forth over November and December of 2024. 

        “It’s 29 properties so there is a lot going on,” she said. “There were, as of December, 151 (open) violations, and as I said 95 percent of them were trash related.” 

        Schneider said she wanted to “acknowledge the important role that (District 9 City) Councilor Liz Breadon and her staff played in this project.” 

        Schneider said that Alpha, at Breadon’s request, installed indoor trash facilities to reduce such trash violations and reduce illegal dumping, which was one of the other reasons given for the trash violations on Alpha’s properties (that and resident behavior). Schneider said it was also designed to address rodent issues. 

        “The consultant is also working with Alpha to develop a series of best practices to be developed at all of its proper ties,” she said. “Some of those practices include moving trash indoors wherever possible, installing a closed lid on dumpsters, and decrease non resident dumping through surveillance and other measures, as the audit has revealed many of the violations involved trash from properties not owned by Alpha.” 

        Schneider said the consultant will stay on to make sure Alpha implements these practices in the coming months. She also pointed out that many of Alpha’s properties are old, and the approval of a new building will help ease the maintenance schedule that is apparently burdening the company and creating these kinds of trash problems. 

        “We think, on this site in particular, going forward and having a new building will eliminate many of the maintenance challenges in operating older buildings that are approaching obsolescence, like the one we’re looking to replace here,” she said. 

        Despite this apparent zeal for cleaning up, Schneider did say Alpha is challenging about two-thirds of the total violations. “Seventeen of them have been cleared, 29 were dis missed for lack of evidence, and the remainder have been challenged in Housing Court be cause we don’t believe there is sufficient evidence to tie us to the violations,” she said.

        IAG reviews 83 Leo Birmingham plans (Katie Krom, The Bulletin: January 30, 2025)

        On Thursday, Jan 23 at 6 p.m., Impact Advisory Group (IAG) members, the development team from Nordblom Co., and public members interested in this project met to discuss a new 333-unit apartment building planned for 83 Leo Birmingham Pkwy. 

        This project started back in January of 2022 and recently, in January of 2025, received approval from the Boston Civic Design Commission and support from the Brighton Allston Improvement Association (BAIA). 

        The design team included Todd Fremont-Smith, Tamara Roy from Stantec, and Sabrina Miller. 

        The building site is 88,583 square feet on the corner between Soldiers Field Road and Leo Birmingham Parkway. The building will be six stories and have 333 units, 52 of which will be affordable units under the city’s Inclusionary Development Policy (IDP). The building will be 100 percent rentals, with the 52 income-restricted IDP units at 50 percent to 100 percent of the area median income. 

        There will be 175 parking spaces, with electric vehicle charging, and 51 percent of the land will be open space on the property. One of the most important aspects in this design, according to Miller, was to keep the greenspace on the site. 

        “We really want to preserve the greenery already existing in the grove,” Miller said. “We will even be increasing the biodiversity to make the grove even better.” 

        There will be a walking trail from Soldier Field Road up to Leo Birmingham, and many outdoor areas on the property. Along with that, the building will encompass an “Into the Woods Design” with wood fiber panels on the outside of the building, charcoal gray colors, and many plants within the property.

        The building overall is aiming to be very ecologically responsible. It will be an all-electric building with no emissions. The rooftop will have PV solar and the building massing will enhance views, airflow and day light to the building. 

        The parking garage will be underground and open up onto Leo Birmingham Parkway, with a drop-off location in front of the building so people do not hold up traffic. The location is near the Charles River with many bus routes, pedestrian paths and bike paths; so it is very connected. 

        In the spring, the Massachusetts Department of Conservation and Recreation (DCR) will be reducing the size of Leo Birmingham to two lanes rather than four, opening up even more pedestrian paths for the future residents. 

        Fremont-Smith explained that this is a huge move for the neighborhood overall. 

        The IAG members who spoke were very happy with the improvement that they have seen since the last meeting. 

        There were a few suggestions to make this property even better including looking into resident permit parking on Soldier Parkway, not having public restrooms in this new building, and adding lights to bike trails to make them even safer. 

        Two big comments were making this apartment building even taller with more affordable units, and decreasing the amount of parking spots in the garage since the area is so connected with transportation. 

        Resident Kevin Carragee said he felt there was too much parking and not enough density. 

        Fremont-Smith explained that according to the rules, there needs to be one car for every two apartments, and we don’t want cars to be all over the neighborhood because there aren’t enough spots. He explained that right now they have enough affordable units. 

        “We want to keep the building this height so that we can keep the prices low for residents and actually afford to build it,” Fremont-Smith said. “There are a ton of variables when it comes to this, but we will take all of these comments back and ask.” 

        Fremont-Smith added that construction costs are very high and the higher you go, the more costly the buildings become. 

        The developers also explained that they have not yet found a general contractor, but once they do they’ll be in contact with Boston Unions. 

        This project is still under review and still needs to be approved by the BPDA. Comments can be submitted through the City of Boston Planning Department website. There will be a meeting to discuss the lane reconstruction on the Leo Birmingham Parkway on Feb 22nd. 

        Those interested can stay up to date on this project through the City of Boston’s website. Nordblom Co. said they will make sure there will be communication to residents in the area as to when they should expect construction to start.

        Boston Bulletin (January 30, 2025):

        Anthony D'Isidoro

        unread,
        Feb 1, 2025, 9:15:09 AMFeb 1
        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
        Harvard Construction Mitigation (Week of February 3, 2025)   

        January 31, 2025

        Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank 

        • Thermal striping in the Harvard Business School lot will take place in the spring. 
        Enterprise Research Campus 
        Residential/Hotel
        • On Saturday, February 1, panel installation will take place on the residential buildings with several boom lifts operating. Roofing activities will be underway on the high rise and hotel. Elevator and other miscellaneous interior work with hoists operational are planned.
        • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
        • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
        • Storefront installation is underway on the ground floors.
        • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
        • Elevators are being installed.
        • Other smaller concrete operations continue.
        • Roofing activities are underway.
        • MEP work is ongoing.
        • Framing and bathroom install are taking place inside the buildings.
        • Temporary heaters are operating.
        Laboratory and Office Buildings
        • On Saturday, February 1, roofing materials will be delivered and unloaded using the tower crane. Curtain wall will be installed. Boom lifts will be used to install exterior Interior drywall framing and mechanical work will be underway. 
        • Installation of exterior curtain-wall panels will take place during the week.
        • Boom lifts are active around the perimeter of the buildings.
        • Level 1 exterior work is underway.
        • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
        • Smaller concrete operations continue.
        • Roof activities are underway.
        • Elevators are being installed.
        • MEP work is ongoing.
        • Mechanical penthouse activities continue.
        • Masonry work continues.
        • Framing and bathroom install are underway
        • Temporary heaters are operational.
        Greenway
        • Backfilling continues with the site leveling off
        • Some drainage work is underway.
        Treehouse Conference Center
        • Mass timber and façade activities will take place on Saturday, February 1. A crane will be in operation.
        • Mass timber activities and installation are finishing up.
        • Façade frame installation continues during the week using boom lifts.
        • Possible concrete core placements if weather permits.
        • MEP activities are ongoing. 
        Building Mock-Ups
        • Building mockups are on the corner of Hague and Rotterdam Streets.
        Eversource Conduit Project
        • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue after hours, typically from 8 p.m. to 5 a.m. Crews are near Travis Street.  This public utility work is not under the supervision of ERC.
        General
        • Snow and ice removal and cleanup will take place as needed.
        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
        • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
        • Drones will be in use bi-weekly to monitor construction progress on site.
          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
          • Weekly flights are weather dependent and are scheduled one weekday morning.
          • A drone is scheduled to fly Thursday, February 6 from 7 a.m. to 9 a.m.
        Signage Project at SEC and Stadium Way 
        • A signage installation project in front of the SEC building continues.  
        • Concrete removal will create some perceptible noise due to the use of a jackhammer. 
        • Barriers surround the work area. 
        North Allston Storm Drain Extension Project (NASDEP) 
        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site. 
        • South of Science work between Rena Path and Rotterdam Street will continue this week. 
        • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.  
        • Excavation and installation of the support system to install structures will continue. 
        • Rebar deliveries and slide rail installation will begin.  
        • A generator and motorized dewatering equipment operate on site. 
        • Science Drive sidewalk will close, and pedestrians will be shifted to the SEC walkway when manhole work takes place in mid-February. 
          92 Seattle Street  
            • Renovation for reuse of this Harvard building is complete, and some final punch list items remain.  
            • Stanchions were delivered on January 28 and will be installed while they wait for the handrails to be delivered next week to finish the handrail installation.
            175 North Harvard Street
            The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
            The structural steel phase of the housing project is complete. Steel decking installation and detailing is expected to be complete by the end of this month. Concrete deck placements will continue on upper levels to the roof and should be completed by mid-February, weather permitting. Mechanical, electrical, and plumbing trades continue to work throughout the site. Crews are fireproofing on the 8th level. This work is progressing up the building. Window deliveries continue and installation will start this week. Crews are backfilling foundations and performing site work.
            The tower crane will be in use for the next couple of weeks during normal working hours as crews continue to work through winter weather conditions. The crane is currently scheduled to be disassembled and removed from the site over the weekend beginning Friday evening, February 14. Because this is a sizeable undertaking, the crane disassembly will require early morning and later evening hours through the weekend with removal complete by Sunday, February 16. The project team appreciates the community’s understanding during this after-hours work.
            The height of the temporary construction hoist has been increased to the roof. Work continues on doors and ramps. Some work may be in the evening when the hoist is not operational.
            Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be heard off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
            During the week of February 3, work at the new affiliate housing building will require the closure of South Campus Drive to all vehicles during working hours Monday through Friday from 7:00 a.m. to 5:00 p.m. to support multiple concrete placements and critical deliveries that need to use South Campus Drive for access. All traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5:00 p.m. and on weekends. Signage and details will be provided to divert traffic as needed, and police details will be on site to provide assistance.
            Occasional concrete deck placements continue on the upper levels to the roof level during regular work hours throughout this month – some finishing work will extend beyond 9:00 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
            Wheel washing and street sweeping continues to ensure soil is not being tracked through the neighborhood streets.
            On the new American Repertory Theater (ART) work site, steel erection is complete. Backfilling for exterior walls and excavating for utilities, footings, and piers continues. Utility work continues around the building perimeter. Steel detailing for the theatre’s stage and fly tower structure and concrete placements for piers and footings are finishing up. The boom lifts from lower levels were removed from the site last week.
            Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow beginning on Monday, February 24. A crane to support this work will mobilize mid-February. This work is expected to take about seven months to complete.
            Adjustments continue on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently.
            Crews at the affiliate housing building site will be working on Saturdays, February 1 and February 8, weather permitting, performing some welding and installing some steel sections. Heaters will be maintained by workers on Sundays through the winter.
            Off hours snow and ice removal are expected as needed.
            The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
            210 North Harvard Street  
            • Eversource or Verizon will remove an old pole and power line.  
            • The bakery Sofra is open.   
            168 Western Ave  
            • One machine is operating for pre-clear excavation in the Swiss Bakers lot behind the fence.  
            • Crews will continue excavation trenches for utilities and will place concrete pads for dumpsters and refrigeration units. 
            • Interior work continues.  
            • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated.  

              Anthony D'Isidoro

              unread,
              Feb 7, 2025, 2:08:34 PMFeb 7
              to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

              Anthony D'Isidoro

              unread,
              Feb 8, 2025, 11:10:15 AMFeb 8
              to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
              Harvard Construction Mitigation (Week of February 10, 2025)   

              February 7, 2025

              Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
              • Thermal striping in the Harvard Business School lot will take place in the spring.
              Enterprise Research Campus

              Residential/Hotel
              • On Saturday, February 8, panel installation will take place on the residential buildings with several boom lifts operating. Roofing activities will be underway on the high rise and hotel. Miscellaneous interior work with hoists operational is planned.
              • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
              • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
              • Storefront installation is underway on the ground floors.
              • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
              • Elevators are being installed.
              • Other smaller concrete operations continue including loading dock slab and infill to the garage/basement.
              • Roofing activities are underway.
              • MEP work is ongoing.
              • Framing and bathroom installation are taking place inside the buildings.
              • Temporary heaters are operating.
              Laboratory and Office Buildings.
              • On Saturday, February 8, curtainwall will be placed using the tower crane. Interior drywall framing and mechanical work will be underway as well as general clean-up activities.
              • Installation of exterior curtain-wall panels will take place during the week.
              • Boom lifts are active around the perimeter of the buildings.
              • Level 1 exterior work is underway.
              • The site’s tower crane is operational. It is designed to move or “weathervane” in the wind.
              • Smaller concrete operations continue.
              • Roof activities are underway.
              • Elevators are being installed.
              • MEP work is ongoing.
              • Mechanical penthouse activities continue.
              • Masonry work continues.
              • Framing and bathroom install are underway
              • Temporary heaters are operational.
                Greenway
                • Backfilling continues with the site leveling off.
                • Tel/data duct work is being installed.
                Treehouse Conference Center
                • Mass timber finish and façade activities will take place on Saturday, February 8.
                • Façade frame and glass installation continues during the week using boom lifts.
                • Mass timber activities are finishing up.
                • Roofing activities are underway.
                • Concrete core extension will be placed.
                • MEP activities are ongoing. 
                Building Mock-Ups
                • Building mockups are on the corner of Hague and Rotterdam Streets.
                Eversource Conduit Project
                • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue. Crews are near Travis Street. This public utility work is not under the supervision of ERC.
                General
                • Snow and ice removal and cleanup will take place, including Sunday, February 9, as needed.
                • The project’s work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                • Drones will be in use bi-weekly to monitor construction progress on site.
                  • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                  • Weekly flights are weather dependent and are scheduled one weekday morning.
                  • A drone is scheduled to fly Thursday, February 13 from 7 a.m. to 9 a.m.
                Signage Project at SEC and Stadium Way
                • A signage installation project in front of the SEC building continues.
                • Concrete removal will create some perceptible noise due to the use of a jackhammer.
                • Barriers surround the work area.
                North Allston Storm Drain Extension Project (NASDEP)
                The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                • South of Science work between Rena Path and Rotterdam Street will continue this week.
                • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                • Excavation and installation of the support system to install structures will continue.
                • Expecting concrete deliveries.
                • Science Drive sidewalk will close, pedestrians will be shifted to the SEC walkway when manhole work takes place at the end of February.  
                • A generator and motorized dewatering equipment operate on site.
                  92 Seattle Street
                    • Renovation for reuse of this Harvard building is complete, and some final punch list items remain.
                    • Stanchions and handrails have been delivered. Handrail installation is now underway.
                    • Project completion is expected on February 17.
                    175 North Harvard Street, 100 South Campus Drive 
                    The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                    • Steel decking installation and detailing are expected to be complete by the end of this month. Concrete deck placements will continue on upper levels to the roof and should be completed by mid-February, weather permitting. Mechanical, electrical, and plumbing trades continue to work throughout the site. Crews are fireproofing on the 8th level for another month. This work is progressing up the building. Window deliveries continue and window installation has started. Crews are backfilling foundations and performing site work. Stairs are being installed on the north side of the building.
                    • The tower crane will be in use for the next week during normal working hours as crews continue to work through winter weather conditions. The crane is currently scheduled to be disassembled and removed from the site over the weekend beginning Friday evening, February 14. Because this is a sizeable undertaking, the crane disassembly will require early morning and later evening hours through the weekend with removal complete by Sunday, February 16. The project team appreciates the community’s understanding during this after-hours work.
                    • The height of the temporary construction hoist has been increased to the 12th floor and is operational. Hoist expansion work will continue to the roof. Some activity may extend into the evening when the hoist is not operational.
                    • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be heard off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
                    • During the week of February 10, work at the new affiliate housing building will require the closure of South Campus Drive to all vehicles during working hours Monday through Friday from 7 a.m. to 5 p.m. to support multiple concrete placements and critical deliveries that need to use South Campus Drive for access. All traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5 p.m. and on weekends. Signage and details will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift and on Sundays so vehicles can use South Campus Drive, with the exception of the February 14 to 16 weekend when the tower crane is scheduled to come down.
                    • Occasional concrete deck placements continue on the upper levels to the roof level during regular work hours throughout this month – some finishing work will extend beyond 9 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
                    • As winter weather allows, wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                    • On the new American Repertory Theater (ART) work site, backfilling for exterior walls and excavating for utilities continues around the building perimeter. Concrete work on footings and piers is underway. Steel detailing of fly tower structure continues
                    • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will follow beginning on Monday, February 24. Layout and setting of base plates for the mass timber structure is underway. A crane to support this work will mobilize mid-February. This work is expected to take about seven months to complete.
                    • Intermittent adjustments continue on the building mock-ups to review design and constructability across North Harvard Street.
                    • Crews at the affiliate housing building site will be working on Saturday, February 8, weather permitting, performing some welding and installing some steel sections. Heaters will be maintained by workers on Sundays through the winter.
                    • Off hours snow and ice removal are expected as needed including this Saturday and Sunday, February 8 and 9.
                    • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                    210 North Harvard Street
                    • Eversource or Verizon will remove an old pole and power line.
                    • The bakery Sofra is open. 
                    168 Western Ave
                    • One machine is operating for sanitary pipe installation trench work in the Swiss Bakers lot behind the fence.
                    • Small concrete placements will continue.
                    • Interior work continues.
                    • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated. 

                      CONTACT US 

                      Anthony D'Isidoro

                      unread,
                      Feb 15, 2025, 9:13:19 AMFeb 15
                      to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

                      Anthony D'Isidoro

                      unread,
                      Feb 15, 2025, 10:26:35 AMFeb 15
                      to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                      IAG, residents positive about Great Scott plan (Jeff Sullivan, The Bulletin: February 13, 2025)
                      Public meeting set for Feb. 24

                      The Impact Advisory Group (IAG) set up for the Great Scott building redevelopment at 1 Harvard Ave. in Allston had fairly positive comments on Monday night. 

                      The City of Boston Planning Department (CBPD) hosted the IAG with the intent of getting feedback. The plan is to leverage 139 rental residential units to allow Great Scott to reopen on the site, while also allowing O’Brien’s Pub – which is currently on the site – to remain. 

                      No parking and no multi-bedroom units are included. All units proposed are one-bed room or studios. Noannet Group’s Jordan Warshaw said this was because residents looking to live above a music venue with no room for a car are not likely to be family minded. He also said that such prospective renters, in his experience, prefer smaller apartment spaces with, hopefully, smaller rents. What was not said but could reasonably be assumed is that small apartments with relatively low rents are preferable to having multiple roommates, which is a common occurrence in Allston Brighton. 

                      Former Great Scott owner Carl Lavin spoke during the presentation and said he joined with Warshaw and Redefined firm representative Paul Armstrong because he wanted to see the legendary music venue make a return to Allston Rock City. He said he’s been with Great Scott for almost 25 years, but when the pandemic hit, it hit the venue hard and it was not able to reopen due to issues with the landlord. 

                      Lavin said Great Scott was originally founded in 1976 and started out as a neighborhood bar with some live music. 

                      “Then, college kids discovered Great Scott and descended and swarmed it and it was that type of place for a number of years,” he said. “My involvement started in 2003; I started booking shows weekly and it was at that time we sort of hatched the plan to turn Great Scott into a live music venue and cater to a different kind of music fan. We started having some success and the venue’s reputation grew in the area regionally and nationally.” 

                      Lavin pointed out that touring national acts started at Great Scott, including Passion Pit, Charlie XCX, Grouplove, Greta Van Fleet, Phoebe Bridgers, Nathaniael Ratelife and the Night Sweats, and comedians like Marc Maron and Nate Bargatze. 

                      “We worked with thousands of bands, hundreds of promoters, all different kinds of music and genres,” he said. 

                      This time around, Lavin, Warshaw and Armstrong will own the building so that the rent issues that were reported to have been the venue’s downfall will not happen again. It had previously been reported that Great Scott closed because an agreement on rent between the venue and the landlord could not be reached. 

                      IAG member Jake Dempsey asked if in the community benefits package there could be opportunities for young folks in the neighborhood to participate in the local music scene in some fashion. “There are my kids, and the West End House and whatever’s going to happen with the Jackson Mann,” he said. “I’d love to see if there were ways that this hub of the Boston music scene could be encouraging the next round of upcoming Boston musicians or giving young people of the neighborhood opportunities to be in this space and understand what it means.” 

                      Warshaw pointed out that venues are used for about four or five hours a day and he said he’d love to see it get more use. He said they used to work with music schools to hold their recitals at Great Scott in the past, and Lavin said they are in talks with the Allston Village Main Streets (AVMS) to help figure this out with O’Brien’s to create some use for the venue during the day now. 

                      “I think it would be natural for both O’Brien’s and Great Scott to be able work with organizations like Girls Rock Camp or School of Rock or things along those lines to give them the opportunity to have their showcases and performances,” Lavin said, adding that they could also do educational sessions to help aspiring youth learn to sound check and set up shows. 

                      Warshaw said they are also looking to host a contest to determine the outside decorations for the wall on the venue, and said it was not necessarily a permanent fixture and could be changed year to year. He said, however, the one resoundingly popular and memorable feature of the old Great Scott, the green awning, would be replicated to create a sense of connection to the lost concert hall. 

                      IAG member Lizzie Torres asked about having an artist preference to the affordable housing in the building. Warshaw said he had a bias as he is married to an artist and is in favor of the idea. 

                      “However when we first went into talks with folks in the city about artist housing or not, I personally was a little surprised to hear that artist housing is not universally loved and some people feel that too many buildings tried to steer towards artist housing at the expense of other people who need affordable housing,” he said. “We are very open. I originally thought it would be great to have the whole first floor of the building, which would be less attractive to some people living above a music venue, open it all up to artists, musicians, actors, just people who are happy to be there and don’t mind that they may have live music below them until 1 a.m.” 

                      Warshaw said they would love to do it, so long as the community would be behind it. 

                      For the recording of this meeting and more information on the project, go to https://tinyurl.com/3yyjm3sx 

                      The comment period ends on Feb. 27 and the public meeting is set for Feb. 24.

                      Boston Bulletin (February 13, 2025):

                      Anthony D'Isidoro

                      unread,
                      Feb 15, 2025, 11:13:25 AMFeb 15
                      to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                      Harvard Construction Mitigation (Week of February 18, 2025)   

                      February 14, 2025

                      Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                      • Thermal striping in the Harvard Business School lot will take place in the spring.
                      Enterprise Research Campus
                      Residential/Hotel
                      • On Saturday, February 15, panel installation will take place on the residential buildings with several boom lifts operating. Roofing activities will be underway on the high rise and hotel. Elevator and miscellaneous interior work with hoists operational are planned.
                      • On Sunday, February 16, a small crew of no more than six workers will be working on the interior midrise elevator.
                      • No work is planned for Monday, February 17, President’s Day.     
                      • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                      • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
                      • Storefront installation is underway on the ground floors.
                      • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
                      • Elevators are being installed.
                      • Other smaller concrete operations continue including loading dock slab and infill to the garage/basement.
                      • Roofing activities are underway
                      • MEP work is ongoing.
                      • Framing and bathroom installation are taking place inside the buildings.
                      • Temporary heaters are operating.
                        Laboratory and Office Buildings.
                        • On Saturday, February 15, curtainwall will be placed using the tower crane. Interior drywall framing, mechanical and elevator work will be underway as well as general clean-up activities.
                        • On Monday, Presidents Day, February 17, the tower crane will be used to place curtainwall.
                        • Installation of exterior curtain-wall panels will take place during the week.
                        • Boom lifts are active around the perimeter of the buildings.
                        • Level 1 exterior work is underway.
                        • The site’s tower crane is scheduled to be dismantled and removed the weekend of February 21, 22 and 23 from 6 a.m. to 7 p.m. Until then the crane will be operational. It is designed to move or “weathervane” in the wind.
                        • Smaller concrete operations continue.
                        • Roof activities are underway.
                        • Elevators are being installed.
                        • MEP work is ongoing.
                        • Mechanical penthouse activities continue.
                        • Masonry work continues.
                        • Farming and bathroom installation are underway.
                        • Temporary heaters are operational.
                        Greenway
                        • Drainage/irrigation piping installation continues.
                        • Backfilling continues to level the site.
                        Treehouse Conference Center
                        • Façade activities will take place on Saturday, February 15.
                        • Façade frame and glass installation continues during the week using boom lifts.
                        • Mass timber activities are complete, and the crane is removed.
                        • Roofing activities are underway.
                        • Concrete core extension continues.
                        • Framing is underway.
                        • MEP activities are ongoing.
                        Building Mock-Ups
                        • Building mockups are on the corner of Hague and Rotterdam Streets.
                        Eversource Conduit Project
                        • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue. Crews are near Travis Street. This public utility work is not under the supervision of ERC.
                        General
                        • Snow, water and ice removal and cleanup will take place as needed, including Sunday, February 16 and/or Monday, February 17.
                        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                        • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                        • Drones will be in use bi-weekly to monitor construction progress on site.
                          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                          • Weekly flights are weather dependent and are scheduled one weekday morning.
                          • A drone is scheduled to fly Thursday, February 20 from 7 a.m. to 9 a.m.
                        Signage Project at SEC and Stadium Way
                        • A signage installation project in front of the SEC building continues.
                        • Concrete removal will create some perceptible noise due to the use of a jackhammer.
                        • Barriers surround the work area.
                        North Allston Storm Drain Extension Project (NASDEP)
                        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                        • South of Science work between Rena Path and Rotterdam Street will continue this week.
                        • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                        • Excavation and installation of the support system to install structures will be complete.
                        • Expecting concrete deliveries.
                        • Cast and place structure operations have begun, and wall placement will start next week.
                        • Science Drive sidewalk will close, pedestrians will be shifted to the SEC walkway when manhole work takes place at the end of February.  
                        • A generator and motorized dewatering equipment operate on site.
                          92 Seattle Street
                          • The job site will be open on Saturday, February 15.
                          • Renovation for reuse of this Harvard building is complete, and some final punch list items remain.
                          • Stanchions and handrails have been delivered. Handrail installation and other work is now underway.
                          175 North Harvard Street, 100 South Campus Drive 
                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                          • The tower crane will be disassembled and removed from the site over the weekend beginning Friday evening, February 14. Because this is a sizeable undertaking, the crane disassembly and removal will require early morning and later evening hours through the weekend with removal complete by Sunday evening, February 16. An assist crane is expected to arrive on site and be assembled on Friday into the evening. Crews will begin dismantling the tower crane starting at 6 a.m. on Saturday, February 15 and will work until 9 p.m. Multiple trucks will be coming to the site to pick up and remove crane parts. On Sunday, February 16, work will continue, and the assist crane will be removed from site starting at 8 a.m. to 7 p.m. The project team appreciates the community’s understanding during this after-hours work. South Campus Drive will be closed to vehicles during this work. Vehicles leaving the Continuum and Trader Joe’s parking garage will be instructed via signage to make a right turn only out of the garage.
                          • The final concrete deck placement will take place on the housing building on Friday, February 14 during regular work hours. Finishing work will extend beyond 9 p.m. with the colder temperatures. Noise is generated by the power trowels used for finishing. The fresh concrete needs to be covered with blankets for warmth while curing. A pump truck will be present on South Campus Drive during concrete pours.
                          • concrete placement on the roof should be completed by mid-February, weather permitting. Mechanical, electrical, and plumbing trades continue to work throughout the site. Crews are fireproofing on the upper levels and progressing up the building. Window deliveries continue, and window installation has started. Stairs are being installed on the north side of the building. Sheathing continues on the south side of the low-rise building. A mobile crane may come on site to assist with these activities.
                          • During the week of February 17, work at the new affiliate housing building will require intermittent closure of South Campus Drive to all vehicles during working hours Monday through Friday from 7 a.m. to 5 p.m. to support a concrete placement on the roof and critical deliveries that need to use South Campus Drive for access. At these times, all traffic leaving the Continuum and Trader Joe’s parking will be instructed to make a right turn only out of the garage. The road will be open to traffic each day after 5 p.m. and on weekends. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift and on Sundays so vehicles can use South Campus Drive, with the exception of the weekend February 16 when the tower crane is scheduled to come down.
                          • The height of the temporary construction hoist has been increased to the 13th floor and will jump again next week to the roof. Work continues on doors and ramps. Some work may be in the evening when the hoist is not operational.
                          • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be noticed off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                          • On the new American Repertory Theater (ART) work site, crews are wrapping up concrete operations this week. Backfilling for exterior foundation walls, footings and piers, and excavating for utilities continues. Utility work continues around the building perimeter. Crews are grouting of columns at steel fly tower structure.
                          • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will mobilize on Monday, February 24. Layout and setting of base plates for the mass timber structure is underway. A crane to support this work will mobilize this week. This work is expected to take about seven months to complete.
                          • Adjustments continue on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently.
                          • Work will be taking place at the affiliate housing building site this weekend in addition to the tower crane removal. Crews will be doing some exterior framing and welding on site, weather permitting. At the ART site, some work is planned for Saturday, February 15. Carpenters will be on site setting base plates in preparation for the mobilization of mass timber. Heaters will be maintained by workers on Sundays through the winter.
                          • Off hours snow and ice removal can be expected on both job sites as needed, including Saturdays and Sundays, and potentially this Monday despite the holiday.
                          • The affiliate housing building and the ART sites will be closed on Monday, February 17, in observance of Presidents’ Day.
                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                          210 North Harvard Street
                          • Eversource or Verizon will remove an old pole and power line.
                          • The bakery Sofra is open. 
                          168 Western Ave
                          • Equipment is on site for sanitary pipe installation trench work in the Swiss Bakers lot behind the fence.
                          • In the next couple of weeks, an underground utility investigation will take place adjacent to the site fence on the sidewalk and possibly into Travis Street.  Pedestrians will be directed to the opposite side of the street during this activity.
                          • Small concrete placements will continue.
                          • Interior work continues.
                          • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated.
                            114 Western Ave
                            • A third-floor suite fit-out for minor interior work has started and will continue for six to seven weeks.
                            • Work hours for this project are 6 a.m. – 2 p.m.

                            Anthony D'Isidoro

                            unread,
                            Feb 22, 2025, 2:25:46 PMFeb 22
                            to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                            Harvard Construction Mitigation (Week of February 24, 2025)   

                            February 21, 2025

                            Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

                            • Thermal striping in the Harvard Business School lot will take place in the spring.
                            Enterprise Research Campus
                            Residential/Hotel
                            • On Saturday, February 22, panel installation will take place on the residential buildings with several boom lifts operating. Roofing activities will be underway on the high rise and hotel. Elevator and miscellaneous interior work with hoists operational are planned.
                            • On Sunday, February 23, a small crew of no more than six workers will be working on the interior midrise elevator shaft. Also 25 to 30 workers will be working on the roofs of the high rise and hotel to remove ice and install roofing. Hoists will be operational.
                            • During the week windows are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                            • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
                            • Storefront installation is underway on the ground floors.
                            • Mast climber scaffolding is set up and continues to be installed in sections on the high-rise building.
                            • Elevators are being installed.
                            • Other smaller concrete operations continue including loading dock slab and infill to the garage/basement.
                            • Roofing activities are underway.
                            • MEP work is ongoing.
                            • Framing and bathroom installation are taking place inside the buildings.
                            • Temporary heaters are operating.
                              Laboratory and Office Buildings.
                              • The site’s tower crane is scheduled to be dismantled and removed the weekend of February 21, 22 and 23.
                                • The arrival and assembly of a large crane with another assist crane will begin at 2 p.m. and will continue into the evening on Friday, February 21.
                                • On Saturday, February 22, starting at 6 a.m. to 7 p.m. crews will dismantle the crane with approximately 18 truckloads of crane parts leaving the site, entering and exiting at both the Hague Street and Milestone Street gates.
                                • On Sunday, February 23, starting at 6 a.m. to 7 p.m. the tower crane removal activities will finish including disassembly and removal of the large crane and its assist crane.
                              • Interior drywall framing, mechanical and elevator work will be underway as well as general clean-up activities.
                              • Installation of exterior curtain-wall panels will take place during the week.
                              • Boom lifts are active around the perimeter of the buildings.
                              • Level 1 exterior work is underway.
                              • The site’s tower crane is scheduled to be dismantled and removed the weekend of February 21, 22 and 23 from 6 a.m. to 7 p.m. Until then the crane will be operational. It is designed to move or “weathervane” in the wind.
                              • Smaller concrete operations continue.
                              • Roof activities are underway
                              • Elevators are being installed.
                              • MEP work is ongoing.
                              • Mechanical penthouse activities continue.
                              • Masonry work continues.
                              • Framing and bathroom install are underway
                              • Temporary heaters are operational.
                              Greenway
                                • Backfilling continues with the site leveling off
                                • Drainage/irrigation and duct piping installation continues.
                                Treehouse Conference Center
                                • Façade and roofing activities will take place on Saturday, February 22.
                                • Less than a dozen roofers will continue to work on Sunday, February 23.
                                • Façade frame and glass installation continues during the week using boom lifts.
                                • A crane will be on site on Tuesday, February 25.
                                • Roofing and terrace activities are underway.
                                • Concrete core extension continues.
                                • Framing is underway.
                                • Stair installation will take place.
                                • MEP activities are ongoing.
                                Building Mock-Ups
                                • Building mockups are on the corner of Hague and Rotterdam Streets.
                                Eversource Conduit Project
                                • Eversource duct bank installation by G. Greene Construction is underway along Western Avenue. Crews are near Travis Street. This public utility work is not under the supervision of ERC.
                                General
                                • Snow, water and ice removal and cleanup will take place as needed.
                                • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                • Drones will be in use bi-weekly to monitor construction progress on site.
                                  • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                  • Weekly flights are weather dependent and are scheduled one weekday morning.
                                  • A drone is scheduled to fly Thursday, February 27 from 7 a.m. to 9 a.m.
                                Signage Project at SEC and Stadium Way
                                • A signage installation project in front of the SEC building continues.
                                • Barriers surround the work area.
                                North Allston Storm Drain Extension Project (NASDEP)
                                The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                • Excavation and installation of the support system to install structures will be complete.
                                • Rebar and concrete will be placed this week.
                                • The dewatering system will mobilize on March 3 and be operational by March 10.
                                • Cast and place structure operations have begun, and wall placement will start next week.
                                • The Science Drive sidewalk will close at the end of next week, pedestrians will be shifted to the SEC walkway while manhole work takes place.  
                                • A generator and motorized dewatering equipment operate on site.
                                  92 Seattle Street
                                  • Work continues on the exterior ramp and rail. Crews will be working on Saturday, February 22.
                                  • Interior fit outs started on February 19 and will be completed by February 28.
                                  • A crane is mobilizing on Friday, February 28 at 6 a.m. – 7 a.m. to move equipment off the roof.
                                  175 North Harvard Street, 100 South Campus Drive 
                                  The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                  • The tower crane has been removed from the job site.
                                  • The final concrete pour on the roof will take place this week. A pump truck will be present on South Campus Drive during the concrete pour.
                                  • Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior framing is underway. Window deliveries continue, and window installation has started. Masonry work is underway. Stairs are being installed on the north side of the building. Sheathing continues on the south side of the low-rise building. A mobile crane may come on site to assist with these activities. Crews are prepping for the installation of roof equipment.
                                  • Work at the new affiliate housing building will require closure of South Campus Drive to all vehicles during working hours on Saturday, February 22.
                                  • During the week of February 24, South Campus Drive will need to be closed periodically between 7 a.m. to 5 p.m. to support concrete placements and critical deliveries that need to use the road for access. At these times, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift and on Sundays so vehicles can use South Campus Drive.
                                  • The height of the temporary construction hoist is increasing and will jump again over the next two weekends. Work continues on doors and ramps. Some work will occur in the evening when the hoist is not operational.
                                  • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. Some tarps blew off last weekend and are being reinstalled. Fireproofing operations are on hold during this work. A small amount of noise associated with the temporary heaters falls within normal limits and may be noticed off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
                                  • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                  • On the new American Repertory Theater (ART) work site, crews are backfilling for exterior foundation walls. Utility work continues around the building perimeter. Crews are grouting columns at the steel fly tower structure. Prepping the remaining footings and piers, which will be backfilled by the end of this week.
                                  • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) will mobilize on Monday, February 24. Layout and setting of base plates for the mass timber structure is complete. A crane to support this work was mobilized last week. This work is expected to take about seven months to complete. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries.
                                  • Adjustments continue on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently and concrete mockups will arrive on site this week.
                                  • This weekend, work will be taking place at the affiliate housing building site on Saturday, February 22. In addition to some roofing and sheathing work and increasing the height of the hoist, there will be a crane on South Campus Drive, requiring its closure during regular work hours. Heaters will be maintained by workers on Sundays through the winter.
                                  • Off hours snow and ice removal can be expected on both job sites as needed, including Saturdays and Sundays.
                                  • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                  210 North Harvard Street
                                  • Eversource or Verizon will remove an old pole and power line.
                                  • The bakery Sofra is open. 
                                  168 Western Ave
                                  • Equipment is on site for sanitary pipe installation trench work in the Swiss Bakers lot behind the fence.
                                  • Small concrete placements will continue.
                                  • Next week an underground utility investigation will take place in the landscaped area adjacent to the site near the sidewalk and on Travis Street.
                                  • Also soil samples will be taken in the landscaped area near the entrance at the corner of Travis Street and Western Avenue.
                                  • Interior work continues.
                                  • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated.

                                  Anthony D'Isidoro

                                  unread,
                                  Feb 28, 2025, 9:30:14 AMFeb 28
                                  to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                  Bluebikes, transmission lines in Allston (Jeff Sullivan, The Bulletin: February 27, 2025)

                                  The Allston Civic Association (ACA) met last week and heard from Boston Transportation Department (BTD) Active Transportation Planner Louisa Gag on bike issues, including incoming Bluebike stations in the neighborhoods of Allston and Brighton. 

                                  Gag said Allston will be seeing six-to-nine new Bluebike stations, and Brighton will be seeing six-to 12 which will be District 9’s share of the new 100 incoming stations to the city. She said Bluebikes is an organization run by the city specifically aimed at administering, installing and maintaining bike rentals. 

                                  Gag said there will be meetings coming up to gather information on where residents want to see new stations. Go to https:// tinyurl.com/56ffz44k for more information. 

                                  Gag also discussed the recently installed Bluebike station at Herter Park. “We recently inked a new deal with (the Massachusetts Department of Conservation and Recreation [DCR]) that allows us to more easily add stations to their property and so this was one of four sites one in Dorchester, a couple in Jamaica Plain – that were all part of that initial deal,” she said. “We also have one proposed for Eliot Bridge that could be coming, and we’re happy to hear ideas as well.” 

                                  ACA President Tony D’Isidoro asked about current bike infrastructure in the neighborhood, and said that some of the bike lanes appear to be fading and could use some sprucing up in the form of restriping. He asked what the maintenance plan is for that kind of infrastructure; for example, is it automatic and planned or is it done on-demand. 

                                  “I’ve noticed a lot of the bike lanes and the bus lane have faded,” he said. 

                                  “There is not necessarily a perfect process for this; the queue of any given thing that needs to get done every year is tremendous,” said Boston Streets Cabinet Capital Projects Design Director Lydia Hausle. “Tons of laborers are doing their best to get to everything, but striping requests make their way to us through a wide variety of methods, including 311, Office of Neighborhood Services (ONS) and programs for maintenance for wear-and tear on the streets.”

                                  Hausle said to reach out to 311 for restriping requests. 

                                  ONS Allston Liaison Kevin L’Herrou said to reach out to him if there are any issues around bike lanes not properly cleared from the snow. “Just reach out to 311 and tag me,” he said. 

                                  In other news, Eversource Project Manager David Cotter came by to update the ACA on a couple of underground transmission line replacements coming to the neighborhood and what kinds of disruptions residents can expect to see. 

                                  Cotter said the replacements are coming for two reasons. The first, and probably most understandable, is that much of the original cable was first installed in the 1960s. 

                                  The second is that replacing and repairing the existing line is difficult. He said the line will be completely replaced and upgraded to modern standards to make repairs and maintenance easier. It will also increase capacity for electrical usage in the neighborhood, as continued growth increases demand. 

                                  The transmission line runs under Lincoln Street and effectively parallels Route 90 until it ends at Electric Avenue. Cotter said the line was first installed in 1967. “The line is 58 years old; fifty-eight good years but I’m not sure I would want a 58-year-old extension cord in my house, so it’s time to replace some of these,” he said. 

                                  The other line replacements planned are set for Brighton Carver running under Linden Street, Brighton Avenue, Commonwealth Avenue and Charles Street, and Brighton-Belmont Avenue, which runs under Adamson Street, Everett Street, the Charles River and ends in Belmont. Cotter said those are in the early design stages. 

                                  The actual work will involve digging up the lines and replacing them. Cotter said the 1.3-mile route will start construction around the first quarter of 2027 and start service in the fourth quarter of 2029. He said typically one lane of the street they work on will be closed, as they have to excavate a trench, install the conduit, backfill the trench, temporarily restore the pavement, test and then repave. 

                                  “So you’ll see a brand new street when it’s all said and done on any of the streets we dig in,” he said. “If we go into the side walks when we’re working we’ll replace the sidewalks as well.” 

                                  For more information, go to https://tinyurl.com/3akna9tb

                                  Boston Bulletin (February 27, 2025):

                                  Anthony D'Isidoro

                                  unread,
                                  Mar 1, 2025, 8:42:45 AMMar 1
                                  to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

                                  Anthony D'Isidoro

                                  unread,
                                  Mar 1, 2025, 10:07:48 AMMar 1
                                  to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                  Harvard Construction Mitigation (Week of March 3, 2025)   

                                  February 28, 2025

                                  Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

                                  • Thermal striping in the Harvard Business School lot will take place in the spring.
                                  Enterprise Research Campus
                                  Residential/Hotel
                                  • On Saturday, March 1, the activities include:
                                    • Eversource will bring a crane onto Trotting Avenue to place three transformers on the level two podium between the hotel and the high rise residential building.
                                    • Soil will be trucked offsite.
                                    • The high rise temp loading dock will be reworked.
                                    • Glass installation will take place on the first floor of the mid rise.
                                    • Roofing activities will be underway on the high rise and hotel.
                                    • Elevator and miscellaneous interior work with hoists operational are planned.
                                    • On Sunday, March 2, a crew of a dozen workers will be working on the interior midrise and the high-rise elevator shafts. Also 25 to 30 workers will be working on the roofs of the high rise and hotel to close up openings and install roofing. Hoists will be operational.
                                    • During the week exterior wall sheathing is being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                                    • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
                                    • Storefront installation is underway on the ground floors.
                                    • Mast climber scaffolding and swing staging is set up and continues to be installed in sections on the high-rise building.
                                    • Elevators are being installed.
                                    • Other smaller concrete operations continue.
                                    • Roofing activities are underway.
                                    • MEP work is ongoing.
                                    • Framing and bathroom installation are taking place inside the buildings.
                                      Laboratory and Office Buildings.
                                      • On Saturday, March 1, a large crane will be assembled to start operating on Monday, March 3. Roofing activities will also be underway. Interior drywall framing, mechanical and elevator work will be underway as well as general clean-up activities.
                                      • On Sunday, March 2, a crew of four elevator workers will be working on the west building elevator service cars in the shaft.
                                      • Starting on Monday, March 3, the crane will be placing generators, chillers and curtainwall panels intermittently for the next two weeks.
                                      • Boom lifts are active around the perimeter of the buildings.
                                      • Level 1 exterior work is underway.
                                      • Smaller concrete operations continue.
                                      • Roof activities are underway.
                                      • Elevators are being installed.
                                      • MEP work is ongoing.
                                      • Mechanical penthouse activities continue.
                                      • Masonry work continues.
                                      • Framing and bathroom install are underway
                                      • Temporary heaters are operational.
                                        Greenway
                                          • Backfilling continues with the site leveling off
                                          • Duct piping installation continues.
                                          Treehouse Conference Center
                                          • Façade activities will take place on Saturday, March 1.
                                          • Façade frame and glass installation continues during the week using boom lifts.
                                          • Roofing and terrace activities are underway.
                                          • Concrete core extension continues.
                                          • Framing is underway.
                                          • Stair installation will take place.
                                          • MEP activities are ongoing.
                                          Building Mock-Ups
                                          • Building mockups are on the corner of Hague and Rotterdam Streets.
                                          Eversource Conduit Project
                                          • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                          General
                                            • Snow, water and ice removal and cleanup will take place as needed.
                                            • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                            • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                            • Drones will be in use bi-weekly to monitor construction progress on site.
                                              • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                              • Weekly flights are weather dependent and are scheduled one weekday morning.
                                              • A drone is scheduled to fly Thursday, March 4 from 7 a.m. to 9 a.m.
                                            Signage Project at SEC and Stadium Way
                                            • A signage installation project in front of the SEC building continues.
                                            • Barriers surround the work area.
                                            North Allston Storm Drain Extension Project (NASDEP)
                                            The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                            • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                            • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                            • Concrete placements as part of the installation of manhole structures will take place.
                                            • A dewatering system will be installed during the next couple of weeks.
                                            • A generator and motorized dewatering equipment operate on site.
                                              92 Seattle Street
                                              • Punchlist work continues on the exterior ramp and rail.
                                              • Interior fit out work is planned to take place in March.
                                              175 North Harvard Street, 100 South Campus Drive 
                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                              • The last concrete deck placement is scheduled for Tuesday, March 4 and finishing activities may continue after 6 p.m. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior framing is underway. Window deliveries and window installation continue. Masonry work is underway. Stairs are being installed on the north side of the building. Fireproofing is ongoing. Exterior wall sheathing continues on the south side of the low-rise building. A mobile crane may come on site to assist with these activities.
                                              • During the week of March 3, South Campus Drive will need to be closed periodically between 7 a.m. to 5 p.m. to support the March 4 concrete placement and critical deliveries that need to use the road for access. At these times, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                              • The height of the temporary construction hoist is increasing and will jump again on Saturday, March 1. Work continues on doors and ramps. Some work will occur in the evening when the hoist is not operational.
                                              • Crews continue to install building wrap to retain temporary heat on upper floors during concrete and fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be noticed off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
                                              • Exterior swing staging is being set up on the buildings to assist with exterior curtainwall installation.
                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                              • On the new American Repertory Theater (ART) work site, crews are backfilling for exterior foundation walls. Utility work continues. An additional crane will be on site this week for swing staging on the 10th and 12th floors of the midrise. Boom lifts can be seen on the low rise working on framing and sheathing with windows to follow.
                                              • Mass timber (engineered wood products known for their strength, durability, versatility and sustainability) began on Monday, February 24. Daily wood deliveries are anticipated. This work is expected to take about seven months to complete. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries.
                                              • Adjustments continue on the building mock-ups to review design and constructability across North Harvard Street. A surrounding structure will be built at the housing building mock-up to retain heat for flashing and masonry work. At the ART mockup, miscellaneous activities will take place intermittently and concrete mockups will arrive on site this week.
                                              • Work will be taking place at the affiliate housing building site on Saturdays, March 1 and March 8 to do some roofing and exterior wall sheathing work and increase the height of the hoist. Heaters will be maintained by workers on Sundays through the winter.
                                              • Off hours snow and ice removal can be expected on both job sites as needed, including Saturdays and Sundays.
                                              • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                              210 North Harvard Street
                                              • Eversource or Verizon will remove an old pole and power line.
                                              • The bakery Sofra is open. 
                                              168 Western Ave
                                              • Small concrete placements will continue.
                                              • An underground utility tie in is taking place in the landscaped area adjacent to the site near the sidewalk and on Travis Street.
                                              • Interior work continues.
                                              • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated.
                                                114 Western Ave
                                                • A third-floor suite fit-out for minor interior work has started and will continue through March.
                                                • Work hours for this project are 6 a.m. – 2 p.m.  

                                                Anthony D'Isidoro

                                                unread,
                                                Mar 7, 2025, 8:59:12 AMMar 7
                                                to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                Great Scott and O'Brien's Pub plans on the table (Jeff Sullivan, The Bulletin: March 6, 2025)

                                                Almost 100 residents came out last week in a virtual format to hear from the developers behind the new Great Scott Building proposal on Harvard Avenue.

                                                The proposal, sited for 1 Harvard Ave., will demolish the existing structure and construct a new, nine-story building with 139 rental units. The main topic of discussion during the meeting was that of the fate of Great Scott, which will be returning – along with O’Brien’s Pub – after the building is constructed.

                                                Great Scott closed due to the pandemic in 2020 and was replaced with a Taco Bell Cantina after operating for decades in the neighborhood. The owners of Great Scott, represented in the meeting by Carl Lavin, Redefined’s Paul Armstrong and Noannet Group’s Jordan Warshaw, want to preserve Great Scott and O’Brien’s with this new building. 

                                                The new building is to be designed with music in mind. 

                                                “One thing our team has tried to do is create unique buildings that don’t look like anything else in Boston,” said Warshaw. “There is a certain vocabulary of modern apartment buildings that tends to be replicated in a lot of locations around the city, state and country.” 

                                                Warshaw said they asked Architect Jan Brenner, of the Cambridge Seven Group, to design the exterior framework with syncopation in mind, which is a musical term for unexpected rhythms (again, extremely simplified explanation but for more detail go to https://tinyurl.com/3zrnk3zu). So the design itself is broken up the way you would count out a certain beat. 

                                                “We feel it’s a created rhythm, unexpected, layered and varied,” Brenner said. “That’s where we wanted to translate this idea of syncopation in our design and architecture.” 

                                                Most of the discussion was positive, as it was at the Impact Advisory Group (IAG) meeting the week previously, but one neighbor was opposed. Babak Veyssi, owner of the Peridot Building one lot away from the proposed site, said while he is pro development, he felt somewhat slighted by the height of the building. 

                                                “We have almost the same exact sized lot as this proposal, and they have 139 units, and we have 32 units and 50 parking spaces for retail and residents,” he said. “The massive size of this nine-story building where this whole street, I was always told, was going to remain in the four to-five story range, and that’s what we proposed and developed, and all the hardship that came with that.” 

                                                Veyssi said he wants to see those venues rebuilt and have residences there, but he said the size would impact his building. “It would chill and destroy one side of my building – all of the apartments facing there will be in total darkness, forever,” he said. 

                                                Many other residents said they were supportive of the redevelopment, provided Allston’s current residents are considered. 

                                                “I want this place to stay dirty and grungy,” said resident Olivia Doyon. “I want the shows at O’Brien’s to stay $10. That’s a huge reason why we love O’Brien’s is that it’s affordable. A lot of us punks and alternative people, we do not have the money to go to a show that’s $25. That’s not why we go out; we go out to go to a dirty grungy show.” 

                                                The fate of O’Brien’s itself was discussed. Warshaw said he was not confident they could reopen O’Brien’s in another location during the 18-month or so construction phase, but he said they would try. 

                                                “It’s something we are absolutely going to try to do, as we’d like to have it alive imperfectly than not being able to keep it alive at all during that period,” he said. “But you can imagine trying to get a one-year lease while playing amplified music. It’s not going to be the easiest thing to find.” 

                                                Resident Matt Zytka said he was completely for the redevelopment and the density. “We are in a housing crisis,” he said. “It’s not a concern, it’s a crisis. If we’re going to clutch pearls every time we see a tall building, it’s just not going to improve. I love how ambitious it is in terms of the unit number and not being concerned about parking or anything like that.” 

                                                Resident Eric Crowder said he’s been involved in the music scene for a long time, and part of what makes Allston special is the mid-level music venues for locals to express themselves. He said he felt much of the conversation was centering around Great Scott and O’Brien’s being launching pads for bands to go up the ladder and achieve mass marketability. 

                                                “There is a real problem at looking at a small venue as a launching pad for someone who is going to eventually play the House of Blues,” he said. “Small music venues have a very important place in the artistic culture of a city, especially for people who will never play to more than 70 people because they have a unique vision or sound that just doesn’t appeal to a large audience but increases the cultural IQ of a city. It’s not just a launching pad.” 

                                                Armstrong said Redefined is looking to keep O’Brien’s the way it is. Lavin said he’s ‘keenly aware’ of O’Brien’s importance. 

                                                For more information on the project, go to https://tinyurl.com/ 3yyjm3sx 

                                                The comment period is ending soon so if you have a concern or want to support the project, hit the site above. 

                                                Boston Bulletin (March 6, 2025):

                                                Paul Creighton

                                                unread,
                                                Mar 7, 2025, 5:12:41 PMMar 7
                                                to allstonbr...@googlegroups.com, cleveland-cir...@googlegroups.com, bacommunit...@googlegroups.com, Paul Creighton
                                                Anthony:

                                                This proposal reminds me of Homer's Trojan Horse; a disguised nine story 139 unit apartment building shoehorned onto a small lot with three parking spaces. This Harvard/Cambridge St. corner  has been a one story wrap around commercial block for at least 100 years.

                                                They are taking advantage of a sincere  group that is trying to recreate the defunct Great Scott's  (now Taco Bells) then at Harvard/Comm Ave.   Harvard Ave has changed dramatically in the last few years and trying to resurrect ALLSTON ROCK CITY is a bit of a pipe dream

                                                Sticking with the architect's musical syncopation metaphor  they might consider  opening with hip hop artist "Ludicrous".

                                                This development would be built right between a City  approved 165 unit housing project on the site of the recently closed  Allston Post Office and  the 39 unit building on the old Washington Allston site.  Both approved projects include parking and some open space and are build on bigger lots of land then these proposed 139 unit s going up on a "postage stamp  size" lot.

                                                This matter is not about saving the local music scene, it is an example of poor urban planning.

                                                By talking about artists and bike racks we are lowering our standards for livability,

                                                A five story structure would be more than enough and still provide a healthy return on investment.

                                                Stay tuned.

                                                Paul






                                                --
                                                To post to this group, send email to AllstonBr...@googlegroups.com
                                                For more options, visit this group at http://groups.google.com/group/AllstonBrighton2006?hl=en
                                                ---
                                                You received this message because you are subscribed to the Google Groups "AllstonBrighton2006" group.
                                                To unsubscribe from this group and stop receiving emails from it, send an email to allstonbrighton...@googlegroups.com.
                                                To view this discussion visit https://groups.google.com/d/msgid/allstonbrighton2006/LV3P222MB0886FE37A2A1FBB13DE5FF02AFD52%40LV3P222MB0886.NAMP222.PROD.OUTLOOK.COM.

                                                Anthony D'Isidoro

                                                unread,
                                                Mar 8, 2025, 8:17:59 AMMar 8
                                                to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                Harvard Construction Mitigation (Week of March 10, 2025)   

                                                March 7, 2025

                                                Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                • Thermal striping in the Harvard Business School lot will take place in the spring.
                                                HBS Utility Investigation
                                                •  Nineteen test pits in and near Harvard Business School’s Spangler Parking lot are planned during spring break to investigate utilities for potential future project work.
                                                • A vacuum truck will be operating intermittently starting on March 17, and backfilling operations are needed for this work
                                                • Restoration operations will begin on March 22.
                                                Enterprise Research Campus

                                                Residential/Hotel
                                                Weekend Activities
                                                • On Saturday, March 8, depending on the wind forecast, roofing, exterior panel installation and swing stage relocation may take place on the high rise with several boom lifts operating. Elevator and miscellaneous interior work with hoists operational are planned. Also, additional soil testing will be underway on Trotting Avenue.
                                                • On Sunday, March 9, nine workers in the interior midrise and high-rise elevator shafts will be onsite. Also, a dozen workers on the roof of the high rise will be closing up openings and installing roofing. Hoists will be operational.
                                                Weekday Activities
                                                • Exterior wall sheathing is being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                                                • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
                                                • Storefront installation is underway on the ground floors.
                                                • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                • Elevators are being installed.
                                                • Other smaller concrete operations continue.
                                                • Roofing activities are underway.
                                                • MEP work is ongoing.
                                                • Framing and bathroom installation are taking place inside the buildings.
                                                  Laboratory and Office Buildings.
                                                  Weekend Activities
                                                  • On Saturday, March 8, the crane will be loading piping. Interior drywall framing, mechanical and elevator work will be underway as well as general clean-up activities.
                                                  Weekday Activities
                                                  • The installation of exterior curtain wall panels will take place.
                                                  • The crane will be placing generators and chillers intermittently.
                                                  • Boom lifts are active around the perimeter of the buildings.
                                                  • Level 1 exterior work is underway.
                                                  • Smaller concrete operations continue.
                                                  • Roof activities are underway.
                                                  • Elevators are being installed.
                                                  • MEP work is ongoing.
                                                  • Mechanical penthouse activities continue.
                                                  • Masonry work continues.
                                                  • Framing and bathroom installation are underway
                                                  • Temporary heaters are operational.
                                                  Greenway
                                                    • Backfilling continues with the site leveling off
                                                    • Light pole work may begin.
                                                    • Duct piping installation will take place later in the week.
                                                    Treehouse Conference Center
                                                    Weekend Activities
                                                    • Façade work will take place on Saturday, March 8.
                                                    Weekday Activities
                                                      • Façade frame and glass installation continues during the week using boom lifts.
                                                      • Roofing and terrace activities are underway.
                                                      • Concrete core extension continues.
                                                      • On Tuesday, March 11, a crane will be on the south side of the building to load piping
                                                      • Framing is underway.
                                                      • MEP activities are ongoing.
                                                      Building Mock-Ups
                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                      Eversource Conduit Project
                                                      • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                      General
                                                      • Snow, water and ice removal and cleanup will take place as needed.
                                                      • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                      • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                      • Drones will be in use bi-weekly to monitor construction progress on site.
                                                        • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                        • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                        • A drone is scheduled to fly Thursday, March 13 at 2:30 p.m.
                                                      Signage Project at SEC and Stadium Way
                                                      • A signage installation project in front of the SEC building continues.
                                                      • Barriers surround the work area.
                                                      North Allston Storm Drain Extension Project (NASDEP)
                                                      The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                      • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                      • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                                      • Concrete placements as part of the installation of manhole structures will take place.
                                                      • A vacuum truck will arrive on Monday, March 10.
                                                      • A temporary drainage bypass system mobilized and will start on March 10.
                                                      • Science Drive sidewalk will close, and pedestrians will be shifted to the SEC walkway when sandbag / manhole work starts again on March 11.
                                                      • A dewatering system has been installed.  
                                                      • A generator and motorized dewatering equipment operate on site.
                                                        92 Seattle Street
                                                          • Punchlist work continues on the exterior ramp and rail.
                                                          • Welding operations will take place followed by rail installation.
                                                          • Interior fit out work is planned to take place in March.
                                                          175 North Harvard Street, 100 South Campus Drive 
                                                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                          • Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior framing is underway. Window deliveries and window installation using boom lifts continue. Masonry work is underway, and fireproofing is ongoing. Exterior wall sheathing continues on the south side of the low-rise building. An additional crane will be on site this week to set up swing staging on the 10th and 12th floors of the midrise. Work continues on doors and ramps. Some work will occur in the evening when the hoist is not operational. Exterior swing staging and a scaffolding lift system are being set up on the buildings to assist with curtainwall installation.
                                                          • During the week of March 10, South Campus Drive will need to be closed periodically between 7 a.m. to 5 p.m. to support critical deliveries that need to use the road for access. At these times, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                          • Crews continue to install building wrap to retain temporary heat on upper floors during fireproofing activities. A small amount of noise associated with the temporary heaters falls within normal limits and may be noticed off-hours. Tarping is removed at the lower floors after the fireproofing is complete.
                                                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                          • On the new American Repertory Theater (ART) work site, crews are installing a stormwater system.
                                                          • The ART has a crane operating to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation are beginning as mass timber gets installed.
                                                          • Adjustments continue on the building mock-ups to review design and constructability across North Harvard Street.
                                                          • Work will be taking place at the affiliate housing building site on Saturdays, March 8 and March 15, to do some exterior wall sheathing and masonry work. Heaters will be maintained by workers on Sundays through the winter. The crew at the ART project will be installing mass timber on Saturday, March 8, during regular work hours.
                                                          • Off hours snow and ice removal can be expected on both job sites as needed, including Saturdays and Sundays.
                                                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                          210 North Harvard Street
                                                          • Eversource or Verizon will remove an old pole and power line.
                                                          • The bakery Sofra is open. 
                                                          168 Western Ave
                                                          • An underground utility tie in an area adjacent to the site near the sidewalk and on Travis Street has been completed.
                                                          • Paving work will take place.
                                                          • Interior work continues.
                                                          • Roof penetrations and roof demolition will continue for three weeks.
                                                          • The Swiss Bakers bakery operation will be temporarily relocated to 9 Travis Street at the end of the month while their space gets renovated.
                                                          114 Western Ave
                                                          • A third-floor suite fit-out for minor interior work has started and will continue through March.
                                                          • Work hours for this project are 6 a.m. – 2 p.m.  

                                                          Anthony D'Isidoro

                                                          unread,
                                                          Mar 14, 2025, 7:13:17 AMMar 14
                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                          One more thing at Boston Landing (Jeff Sullivan, The Bulletin: March 13, 2025) 

                                                          The Boston Planning Department met with a couple of residents, a couple of Impact Advisory Group (IAG) members and the team from the Boston Landing development for a small project change at the Guest Street complex. 

                                                          There were technically two back-to-back meetings on the issue, one IAG and one public meeting. The Brighton site has seen major redevelopment since its Planned Development Area Master Plan was first approved in 2012, including the New Balance and WGBH buildings and the Boston Landing MBTA Commuter Rail Stop. 

                                                          NB Development Group Senior Director Keith Craig went through the most recent change, which is for the 115 Guest St. building, which he said currently does not have the same allowed uses for its ground-floor commercial as the rest of the complex. The Lantera, a 295-unit apartment building to the southeast of the site, currently only allows a handful of commercial uses– restaurant, retail, service, cultural, banking and postal, barber or beauty and take out. 

                                                          The new uses would basically allow for a higher variety of businesses, like sports, dance, yoga, private club, general sports and recreation and more (since the site includes the practice rink for the Bruins and the Track at New Balance, one might think sports uses would have been included at the get go). 

                                                          The building was completed in 2018 and offers about 16,000 square feet of retail. 

                                                          “The only retail locations currently occupied are Mainly Burgers and Crumbl Cookies,” Craig said. “The remainder of the building for ground-floor retail is unoccupied.” 

                                                          Craig did say the northwest of the building is reserved for popups. He said retail in the area has been tough. “We’ve had trouble getting viable retailers to invest and open up new locations, and so in the fall of 2020 we amended our other PDA development plans that incorporated a wider variety of uses; the exact same uses I’m proposing for this PDA plan,” he said. “The reason why we didn’t do this parcel back in 2020 was because our partner in this building just wasn’t going to be part of that effort at that time. But five years later we’re all on the same page.” 

                                                          Craig said if they had an interested retail business not on the old list, they would have to go through this PDA change process for every retail space individually, so they’re just getting it all done at once. 

                                                          Resident and Brighton Allston Improvement Association member Annabelle Gomes asked how the development of the Boston Landing Commuter Rail Station has influenced the success of the complex as a whole. Craig pointed out that the station ran above its 2030 ridership goals the same year as it opened in 2017 and has been instrumental for the businesses and buildings there. 

                                                          “That was the culmination of a five-year effort of us working with the local community, elected officials, MassDOT, the MBTA and Keolis to bring commuter rail back to the neighborhood,” he said. 

                                                          Gomes said she was very much in support. “I do think that all those added uses are important to activate Guest Street and get people to the street,” she said. 

                                                          Residents Bernadette Lally and Dan Daly said they were in support. 

                                                          “I think this project looks great; I know we’ve had a few bumps in the road, but everything seems to be coming out great,” Lally said. 

                                                          Allston Brighton Chamber of Commerce President Rosie Hanlon said, speaking for herself, said she wanted to see more interaction between Guest Street and the local Allston Brighton business community. “Both to help you recruit new businesses, integrating what you have and bringing people who live and work on Guest Street up into the Allston Brighton business districts,” she said. 

                                                          Craig said he would be happy to work with the Chamber to do so. 

                                                          The comment period for this new change ends on March 24. For more information, go to https://tinyurl.com/22z7scb7

                                                          Boston Bulletin (March 13, 2025):

                                                          Anthony D'Isidoro

                                                          unread,
                                                          Mar 15, 2025, 10:27:34 AMMar 15
                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                          Harvard Construction Mitigation (Week of March 17, 2025)   

                                                          March 14, 2025

                                                          Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                          • Thermal striping in the Harvard Business School lot will take place in the spring.
                                                          Utility Investigation at HBS
                                                          • Nineteen test pits in and near Harvard Business School’s Spangler parking lot are planned during spring break to investigate utilities for potential future project work.
                                                          • On Saturday, March 15 crews will sawcut, remove and patch the pavement to prepare for the weekday test pit work.
                                                          • A vacuum truck will be operating intermittently during excavation starting on March 17, and backfilling operations are needed for this work
                                                          • Restoration operations are scheduled for Saturday, March 22.
                                                          Enterprise Research Campus
                                                          Residential/Hotel
                                                          Weekend Activities
                                                          Weekend Activities
                                                          • On Saturday, March 15, exterior panel installation will take place on the midrise residential building with several boom lifts operating. The high rise will continue to be prepped for panel install and have roofing activity underway. Crews will be applying hot mix to the area beyond the connector nearer to the labs. The scaffolding will be reassembled at the hotel loading dock with repositioning work at the suspended deck.  Elevator and miscellaneous interior work with operational hoists is planned.
                                                          • On Sunday, March 16, six workers in the high-rise elevator shaft will be working onsite. If the weather permits, a dozen workers on the roof of the high rise will be closing up openings and installing roofing. Hoists will be operational.
                                                          Weekday Activities
                                                          • Exterior wall sheathing and panel clips are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                                                          • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
                                                          • Storefront installation is underway on the ground floors.
                                                          • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                          • Elevators are being installed.
                                                          • Other smaller concrete operations continue.
                                                          • Roofing activities are underway.
                                                          • MEP work is ongoing.
                                                          • Framing and bathroom installation are taking place inside the buildings.
                                                          • Eversource off-hours manhole cabling work inside the site may take place.
                                                          Laboratory and Office Buildings.
                                                          Weekend Activities
                                                          • On Saturday, March 15, boom lifts will be operating at level one. Roofing activities will be taking place on the east and west buildings. Interior drywall framing, mechanical and elevator work will be underway as well as general clean-up activities.
                                                          Weekday Activities
                                                            • Boom lifts are active around the perimeter of the buildings.
                                                            • Level 1 exterior work is underway.
                                                            • Smaller concrete operations continue.
                                                            • Roof activities are underway.
                                                            • Elevators are being installed.
                                                            • MEP work is ongoing.
                                                            • Mechanical penthouse activities continue.
                                                            • Masonry work continues.
                                                            • Framing and bathroom install are underway
                                                            • Temporary heaters are operational.
                                                            Greenway
                                                            Weekend Activities
                                                            • Crews will be removing soil used on a temporary access road.
                                                            Weekday Activities
                                                            • Area drains will be installed.
                                                            • Light pole base work will take place.
                                                            • Duct piping excavation, installation and backfilling will occur.
                                                            Treehouse Conference Center
                                                            Weekend Activities
                                                            • Façade work will take place on Saturday, March 15.
                                                            Weekday Activities
                                                              • Façade frame and glass installation continues during the week using boom lifts.
                                                              • Roofing and terrace activities are underway.
                                                              • Concrete core extension continues.
                                                              • Framing is underway.
                                                              • MEP activities are ongoing.
                                                              • Plans are underway for sewer tie-in work on Western Avenue.
                                                              Building Mock-Ups
                                                              • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                              Eversource Conduit Project
                                                              • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                              General
                                                              • Snow, water and ice removal and cleanup will take place as needed.
                                                              • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                              • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                              • Drones will be in use bi-weekly to monitor construction progress on site.
                                                              o   Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                              o   Weekly flights are weather dependent and are scheduled one weekday morning.
                                                              o   A drone is scheduled to fly Thursday, March 20 at 2:30 p.m.
                                                              Signage Project at SEC and Stadium Way
                                                              • A signage installation project in front of the SEC building continues.
                                                              • Barriers surround the work area.
                                                              North Allston Storm Drain Extension Project (NASDEP)
                                                              The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                              • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                              • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                                              • Some demolition work as part of the installation of manhole structures continues.
                                                              • A temporary drainage bypass system with an operator is running.
                                                              • A dewatering system has been installed.  
                                                              • A generator and motorized dewatering equipment operate on site.
                                                                92 Seattle Street  
                                                                • Inspections and minor punch list work are on the exterior ramp will take place.
                                                                • Interior fit out work is planned to take place in March.
                                                                175 North Harvard Street, 100 South Campus Drive 
                                                                The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                • Concrete deck pours are substantially complete. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior framing is underway. Window deliveries and window installation using boom lifts continue. Masonry work is underway, and fireproofing is ongoing. Exterior wall sheathing continues on the south side of the low-rise building. An additional crane will be on site this week to set up swing staging on the 10th and 12th floors of the midrise. Work continues on doors and ramps. Exterior swing staging and a scaffolding lift system are being set up on the buildings to assist with curtainwall installation. Brickwork has started. Spray on fireproofing was complete last week allowing for the temporary heat and building wrap to be removed.
                                                                • During the week of March 17, South Campus Drive will need to be closed periodically between 7 a.m. to 5 p.m. to support critical deliveries that need to use the road for access. At these times, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                • On the new American Repertory Theater (ART) work site, crews are installing a stormwater system. The project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation are beginning as mass timber gets installed. Columns, beams, and trusses are being installed.
                                                                • Adjustments continue on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                • Work will be taking place at the affiliate housing building site on Saturdays, March 15, and March 22, to do some exterior wall sheathing and masonry work. Heaters will be maintained by workers on Sundays through the winter. The crew at the ART project will be installing mass timber on Saturday, March 15, during regular work hours.
                                                                • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                210 North Harvard Street
                                                                • Eversource or Verizon will remove an old pole and power line.
                                                                • The bakery Sofra is open. 
                                                                168 Western Ave
                                                                • Roofing work will take place this Saturday, March 15.
                                                                • Interior work continues.
                                                                • Roofing activity will continue throughout the week.
                                                                • Paving work is anticipated at the end of the week.
                                                                • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.
                                                                114 Western Ave
                                                                • A third-floor suite fit-out for minor interior work has started and will continue through March.
                                                                • Work hours for this project are 6 a.m. – 2 p.m.

                                                                Anthony D'Isidoro

                                                                unread,
                                                                Mar 22, 2025, 12:45:50 PMMar 22
                                                                to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                Harvard Construction Mitigation (Week of March 24, 2025)   

                                                                March 21, 2025

                                                                Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

                                                                • Thermal striping in the Harvard Business School lot will take place in the spring.
                                                                Utility Investigation at HBS
                                                                • Restoration operations are scheduled for the test pit areas in and around Spangler Lot on Saturday, March 22.
                                                                Enterprise Research Campus

                                                                Residential/Hotel

                                                                Weekend Activities
                                                                • On Saturday, March 22, exterior panel installation will take place on the midrise residential building with several boom lifts operating. The high rise will continue to be prepped for panel install and have roofing activity underway. Elevator and miscellaneous interior work with operational hoists is planned.
                                                                • On Sunday, March 23, six workers in the high-rise elevator shaft will be working onsite. If the weather permits, a dozen workers on the roof of the high rise will be closing up openings and installing roofing. Hoists will be operational.
                                                                Weekday Activities
                                                                  • Exterior wall sheathing and panel clips are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                                                                  • A suspended scaffolding deck, like under a bridge is set up, on the underside of the cantilever section at the hotel.
                                                                  • Storefront installation is underway on the ground floors.
                                                                  • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                  • Elevators are being installed.
                                                                  • Other smaller concrete operations continue.
                                                                  • Roofing activities are underway.
                                                                  • MEP work is ongoing.
                                                                  • Framing and bathroom installation are taking place inside the buildings.
                                                                  • Eversource off-hours manhole cabling work inside the site may take place. A crane will be used to load large spools of wire a-top the two-level podium.
                                                                  Laboratory and Office Buildings.
                                                                  Weekend Activities
                                                                  • Saturday, March 22, boom lifts will be operating at level one storefront work. Roofing activities will be taking place on the east and west buildings. Interior drywall framing and mechanical work will be underway as well as general clean-up activities.
                                                                  Weekday Activities
                                                                  • Underground gas tie-in lines are being installed inside the site.
                                                                  • Boom lifts are active around the perimeter of the buildings.
                                                                  • Level 1 exterior work is underway.
                                                                  • Smaller concrete operations continue.
                                                                  • Roof activities are underway.
                                                                  • Elevators are being installed.
                                                                  • MEP work is ongoing.
                                                                  • Mechanical penthouse activities continue.
                                                                  • Masonry work continues.
                                                                  • Framing and bathroom install are underway
                                                                  • Temporary heaters are operational.
                                                                    Greenway
                                                                    • Sewer line work will be underway.
                                                                    • Light pole base work will take place.
                                                                    • Duct piping excavation, installation and backfilling will continue.
                                                                    Treehouse Conference Center
                                                                    Weekend Activities
                                                                    • Façade work, including glass installation, will take place on Saturday, March 22.
                                                                    Weekday Activities
                                                                      • Façade frame and glass installation continues during the week using boom lifts.
                                                                      • Roofing and terrace activities are underway.
                                                                      • Framing continues.
                                                                      • Elevator work has begun.
                                                                      • MEP activities are ongoing.
                                                                      • Mobile cranes will be on site every other day.
                                                                      Sewer Work on Western Ave.
                                                                      • The project team is working with the City to schedule nighttime sewer tie-in work in front of the Treehouse Conference Center site on Western Avenue which may begin Tuesday, March 25through Thursday, March 27 from 7 p.m. to 5 a.m. This work is planned to continue weeknights next week.
                                                                      • Between Hague and Milestone streets, pedestrians will shift at night to the Harvard Business School side of the road and cyclists will share the road during these activities.
                                                                      • A vehicular travel lane will be taken when crews are working in sewer manholes.
                                                                      • Signage will be in place and two police details will be scheduled.
                                                                      • Crews will also be patching the roadway at night.
                                                                      Building Mock-Ups
                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                      Eversource Conduit Project
                                                                      • Eversource electrical cabling will be taking place in the future along Western
                                                                      • Avenue. This public utility work is not under the supervision of ERC.
                                                                      General
                                                                      • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                      • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                                      • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                        • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                        • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                        • A drone is scheduled to fly Thursday, March 27 at 2:30 p.m.
                                                                      Signage Project at SEC and Stadium Way
                                                                      • A signage installation project in front of the SEC building continues.
                                                                      • Barriers surround the work area.
                                                                      North Allston Storm Drain Extension Project (NASDEP)
                                                                      The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                      • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                      • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                                                      • Backfilling operations for a temporary drainage bypass system will occur.
                                                                      • A vacuum truck may be necessary on site to clean out the dewatering tank.
                                                                      • A temporary drainage bypass system with an operator is running.
                                                                      • A dewatering system has been installed.  
                                                                      • A generator and motorized dewatering equipment operate on site.
                                                                        92 Seattle Street
                                                                        • Rail installation and inspections are complete.
                                                                        • Interior fit out work is planned to take place after rail installation and COO is in hand.
                                                                        175 North Harvard Street, 100 South Campus Drive 
                                                                        The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                        • Concrete deck pours are largely complete. Small miscellaneous pours will occur once or twice a week as needed on the upper portion of the building along with stair placements. Spray on fireproofing is complete and the temporary heat and building wrap has been removed. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out, framing, and sheathing operations are underway. Window deliveries and window installation using boom lifts continue. Exterior wall sheathing continues on the south side of the low-rise building. Work continues on doors and ramps. Exterior swing staging and a scaffolding lift system are being set up on the buildings to assist with curtainwall installation. Exterior brickwork continues.
                                                                        • During the week of March 24, South Campus Drive will need to be closed periodically between 7 a.m. to 5 p.m. to support critical deliveries that need to use the road for access. The contractor will also need to shut down S. Campus Drive for one day next week for crane access needed to set up the exterior hoists being used for masonry. The exact day has not yet been determined.
                                                                        • When South Campus Drive needs to be closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                        • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                        • On the new American Repertory Theater (ART) work site, crews are installing a stormwater system. The project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation are beginning as mass timber gets installed. Columns, beams, and trusses are being installed.
                                                                        • Adjustments continue on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                        • Work will be taking place at the affiliate housing building site on Saturdays, March 22, and March 29, to do some exterior wall sheathing, welding, and masonry work. The crew at the ART project will be installing mass timber on Saturday, March 22, during regular work hours.
                                                                        • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                        210 North Harvard Street
                                                                        • Eversource or Verizon will remove an old pole and power line.
                                                                        • The bakery Sofra is open. 
                                                                        168 Western Ave
                                                                        • Interior and roofing work continues.
                                                                        • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.

                                                                        Anthony D'Isidoro

                                                                        unread,
                                                                        Mar 27, 2025, 8:28:58 AMMar 27
                                                                        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com

                                                                        Twin Donuts’ last day – At least for now – (Jeff Sullivan, The Bulletin: March 27, 2025) 


                                                                        Twin Donuts, a landmark of the neighborhood of Allston, closed its doors on Sunday for the final time, at least under the current owners. The shop entered its 70th year this year, but the family announced that with the hit from the COVID-19 pandemic, increasing rents and decreasing patrons, they couldn’t make the restaurant work anymore. 

                                                                        On Sunday, March 23, the shop opened for its last day, and for most of that day patrons lined up outside of the building to get one last deep-fried piece of Boston history. 

                                                                        “We are wearing all black to commemorate the passing of Twin Donuts,” said resident Maria Kloiber regarding the garb of herself and her friend, Madison Gera. “Off and on I’ve been coming here since moving here five years ago.” 

                                                                        “I live across the street and this place is amazing,” said Gera. 

                                                                        Kloiber said she felt the food comes with a history. “I really feel like you can taste the difference when it’s been seasoned with the grease of 70 years,” she said. “It makes the eggs taste better, I think. I prefer the vibes of old diners too, as opposed to modern chains.” 

                                                                        Gera said she’d sometimes grab a deal of day-old donuts from Twin on the Too Good To Go app. “I picked up like a dozen donuts from them at the end of the day and I had those just all by myself, probably in the span of like 48 hours,” she said with a laugh. “They were good.” 

                                                                        Both said they would like to see the sign preserved if it could be. 

                                                                        “It’s a landmark people use to give you directions,” said Kloiber. “’Just go past the Twin Donuts sign and take a right.’” 

                                                                        “Oh 100 percent,” said Gera. “I love it, even when some of the lights are out and you get variations on Twin Donuts or something like that.” 

                                                                        Brookline resident Ted Jones said he’s been coming for 20 years. “My family grew up here and it’s always good stuff,” he said. “The closing is sad, I know they have other stores but it’s not the same. Not the same location or history. It’s sad, but a lot of things come and go over the course of time I guess.” 

                                                                        Jones said he would support saving the sign and the building if possible. “Yeah, I think it’s a good idea,” he said. 

                                                                        Resident Maggie Whittemore said she has come over from Lower Allston more than a few times. “It’s like a 10-minute walk, and I like the food and the diner aesthetics and I love the big old sign,” she said. “I hope they don’t get rid of it. It’s always nice to see on my morning commute, even if I’m not going in if I’m just passing it on the bus.” 

                                                                        Resident Tom Grannis said he’s been coming to the shop for 25 years now. “It’s the location; you get such a straight view right down Brighton Avenue, and it’s a short distance from the places across the way,” he said. “I come here just for the black tea mostly, but the food is good too. Egg and cheese, English muffins, but mainly tea. I’ll miss it for sure, it’s a landmark.” 

                                                                        Residents Ben Harvey, Thomas Dwyer and Veronica Wood said they came to say goodbye, as they all have good memories from the diner. 

                                                                        “Especially being hungover after a rough night at college,” said Dwyer. 

                                                                        “I used to live right across from that building and it became a part of my routine. I loved saying hi to people,” said Harvey. “Every time I come back to Boston I would drop in.” 

                                                                        “I just moved here recently so this is actually my first time,” said Wood. “I just wanted to show up in solidarity.” 

                                                                        All those interviewed by The Bulletin said they would like to see the landmark stay. The idea of a Twin Donuts apartment complex garnered mild enthusiasm from those in line.

                                                                        Boston Bulletin (March 27, 2025):

                                                                        Anthony D'Isidoro

                                                                        unread,
                                                                        Mar 29, 2025, 10:58:29 AMMar 29
                                                                        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                        Harvard Construction Mitigation (Week of March 31, 2025)   

                                                                        March 28, 2025

                                                                        Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                        • Thermal striping in the Harvard Business School lot will take place in the spring.
                                                                        Utility Investigation at HBS
                                                                        • Restoration operations for the test pit areas in and around Spangler Lot have been completed.
                                                                        Enterprise Research Campus

                                                                        Residential/Hotel
                                                                        Weekend Activities
                                                                        • On Saturday, March 29, exterior panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating.  Elevator and miscellaneous interior work with operational hoists are planned.
                                                                        • On Sunday, March 30, twenty workers will be working in the high-rise, mid-rise and hotel elevator shafts. Hoists will be operational.
                                                                        Weekday Activities
                                                                        • On Monday, March 31 a crane will be set up and operating near the Greenway to remove boom lifts.
                                                                        • Exterior wall sheathing and panel clips are being installed on the high-rise building, and green exterior panels are being installed on the midrise building.
                                                                        • A suspended scaffolding deck, like under a bridge is being dismantled in sections, on the underside of the cantilevered section at the hotel.
                                                                        • At the midrise the hoist has been removed, and infill work is underway.
                                                                        • Storefront installation is underway on the ground floors.
                                                                        • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                        • Elevators are being installed.
                                                                        • Other smaller concrete operations continue.
                                                                        • Roofing activities are underway.
                                                                        • MEP work is ongoing.
                                                                        • Framing and bathroom installation are taking place inside the buildings.
                                                                          Laboratory and Office Buildings
                                                                          Weekend Activities
                                                                          • On Saturday, March 29, exterior boom lifts work will take place. Roofing activities will be underway on the east and west buildings. Interior drywall framing, elevator shaft and penthouse mechanical work will occur as well as general clean-up activities.
                                                                          • On Sunday, March 30, a crew of four will be working in the east building elevator shaft.
                                                                          Weekday Activities
                                                                          • Underground gas tie-in lines are being installed inside the site.
                                                                          • Boom lifts are active around the perimeter of the buildings.
                                                                          • Level 1 exterior work is underway.
                                                                          • Smaller concrete operations continue.
                                                                          • Roof activities are underway.
                                                                          • Elevators are being installed.
                                                                          • MEP work is ongoing.
                                                                          • Mechanical penthouse activities continue.
                                                                          • Masonry work continues.
                                                                          • Framing and bathroom install are underway
                                                                          • Temporary heaters are operational.
                                                                          Greenway
                                                                          Weekend Activities
                                                                          • Sewer line work will be underway on Saturday, March 29.
                                                                          Weekday Activities
                                                                            • Light pole base work will take place.
                                                                            • Duct piping excavation, installation and backfilling will continue.
                                                                            • A shared used road will be constructed.
                                                                            • On Tuesday, April 1 landscaping crews will begin prepping for hardscape and tree planting.
                                                                            • Sewer pipe installation will be taking place on Milestone Street near the Greenway inside the site.
                                                                            Treehouse Conference Center
                                                                            Weekend Activities
                                                                            • Façade work including glass installation will take place on Saturday, March 29.
                                                                            Weekday Activities
                                                                              • Façade frame and glass installation continues during the week using boom lifts.
                                                                              • Roofing and terrace activities are underway.
                                                                              • Framing continues.
                                                                              • Elevator work has begun.
                                                                              • MEP activities are ongoing.
                                                                              • Sub-flooring work has begun.
                                                                              • Mobile cranes will be on site every other day.
                                                                              Sewer Work on Western Ave.
                                                                              • Nighttime sewer tie-in work is scheduled to take place in front of the Treehouse Conference Center site on Western Avenue beginning Monday, March 31 through Thursday, April 3 from 7 p.m. to 3 a.m. This work is also planned to continue at night, Monday through Friday next week.
                                                                              • Between Hague and Milestone streets, pedestrians will shift at night to the Harvard Business School side of the road and cyclists will share the road during these activities.
                                                                              • A vehicular travel lane will be taken when crews are working in sewer manholes.
                                                                              • Signage will be in place and two police details will be scheduled.
                                                                              • Crews will also be patching the roadway at night.
                                                                              Building Mock-Ups
                                                                              • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                              Eversource Conduit Project
                                                                              • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                              General
                                                                              • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                              • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                                              • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                • A drone is scheduled to fly Thursday, April 3 at 2:30 p.m.
                                                                              Signage Project at SEC and Stadium Way
                                                                              • A signage installation project in front of the SEC building continues.
                                                                              • Barriers surround the work area.
                                                                              North Allston Storm Drain Extension Project (NASDEP)
                                                                              The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                              • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                              • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                                                              • Backfilling operations for a temporary drainage bypass system will occur.
                                                                              • A vacuum truck may be necessary on site to clean out the dewatering tank.
                                                                              • A temporary drainage bypass system with an operator is running.
                                                                              • A dewatering system has been installed.  
                                                                              • A generator and motorized dewatering equipment operate on site.
                                                                              92 Seattle Street
                                                                              • Rail installation and inspections are complete.
                                                                              • Interior fit out work is planned to take place after rail installation and COO is in hand.
                                                                              175 North Harvard Street, 100 South Campus Drive 
                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                              • Small miscellaneous concrete pours will occur once or twice a week as needed on the upper portion of the building along with stair placements. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing operations continue. Window deliveries and window installation using boom lifts continue. Exterior wall sheathing continues. Work continues on doors and ramps. Stairs are being installed. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Exterior brickwork preparation continues.
                                                                              • During the week of March 31, the contractor will need to close South Campus Drive between 7 a.m. to 5 p.m. on Wednesday, April 2, and Thursday, April 3, to support crane access needed to set up the exterior hoists for masonry. South Campus Drive may be closed periodically on other days as well to support critical deliveries that need the road for access.
                                                                              • When South Campus Drive needs to be closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                              • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. Steel installation using a crane is also underway, A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation are beginning as mass timber gets installed. Columns, beams, trusses, stairs, walls and flooring are also being installed.
                                                                              • Adjustments continue on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                              • Work will be taking place at the affiliate housing building on Saturdays, March 29, and April 5, to do some exterior wall sheathing, welding, window installation, and masonry work. The crew at the ART project will be installing mass timber and steel using the crane on Saturday, March 29, during regular work hours.
                                                                              • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                              210 North Harvard Street
                                                                              • Eversource or Verizon will remove an old pole and power line.
                                                                              • The bakery Sofra is open. 
                                                                              168 Western Ave
                                                                              • Interior and roofing work continues.
                                                                              • A crane pick is scheduled for Monday, March 31. No traffic impacts are associated with this work.
                                                                              • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.
                                                                                114 Western Ave
                                                                                • Punch list for third-floor suite fit-out for minor interior work will continue.
                                                                                • Work hours for this project are 6 a.m. – 2 p.m.

                                                                                Anthony D'Isidoro

                                                                                unread,
                                                                                Apr 5, 2025, 12:32:07 PMApr 5
                                                                                to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                Harvard Construction Mitigation (Week of April 7, 2025)   

                                                                                April 4, 2025

                                                                                Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

                                                                                • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                Utility Investigation at HBS
                                                                                • Two additional test excavations to determine underground utility conditions will be conducted on Saturday, April 5 from 7 a.m. to 2 p.m. near the parking lot egress and attendant’s booth on Batten Way.
                                                                                Enterprise Research Campus
                                                                                Residential/Hotel
                                                                                Weekend Activities
                                                                                • On Saturday, April 5, exterior panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating. Prep work for concrete will be underway at the loading dock off Trotting Avenue. Eversource will be tying in between their manhole on Trotting and the building. Glass infill install will take place at the mid-rise former hoist area. Duct installation will take place. Elevator and miscellaneous interior work with operational hoists are planned.
                                                                                • On Sunday, April 6 a crew of 12 will be completing interior prep work for the concrete at the loading dock below the podium between the hotel and mid-rise. Additionally, 20 workers will be active in the high-rise, mid-rise and hotel elevator shafts. Hoists will be operational.
                                                                                 Weekday Activities
                                                                                • Eversource will be on site making connections between their Trotting Avenue manhole and the building.
                                                                                • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                • A suspended scaffolding deck, like under a bridge is being dismantled in sections, on the underside of the cantilevered section at the hotel.
                                                                                • At the midrise the hoist has been removed and infill work is underway.
                                                                                • Storefront installation is underway on the ground floors.
                                                                                • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                • Elevators are being installed.
                                                                                • Other concrete operations continue.
                                                                                • Roofing activities are underway.
                                                                                • MEP work is ongoing.
                                                                                • Framing and bathroom installation are taking place inside the buildings.
                                                                                • Temporary heaters are being removed.
                                                                                Laboratory and Office Buildings
                                                                                Weekend Activities 
                                                                                • On Saturday, April 5, exterior boom lifts work will take place to work on Level 1 soffits. Interior drywall framing, elevator shaft and penthouse mechanical work will occur as well as general clean-up activities.
                                                                                • On Sunday, April 6, a crew of four will be working in the east building elevator shaft.
                                                                                 Weekday Activities
                                                                                  • Boom lifts are active around the perimeter of the buildings.
                                                                                  • Level 1 soffit and exterior work is underway.
                                                                                  • Smaller concrete operations continue.
                                                                                  • Roof activities are underway.
                                                                                  • Elevators are being installed.
                                                                                  • MEP work is ongoing.
                                                                                  • Mechanical penthouse activities continue.
                                                                                  • Masonry work continues.
                                                                                  • Framing and bathroom install are underway.
                                                                                  • Temporary heaters are being disconnected.
                                                                                  Greenway
                                                                                  Weekend Activities
                                                                                  • Regrading may take place on Saturday, April 5.
                                                                                  Weekday Activities
                                                                                    • Light pole base work will take place.
                                                                                    • Duct piping excavation, installation and backfilling will continue.
                                                                                    • A shared used road will be constructed.
                                                                                    • Landscaping crews will continue prepping for hardscape and tree planting.
                                                                                    Treehouse Conference Center
                                                                                    Weekend Activities
                                                                                    • Façade work including glass, electrical, steel and sub-floor installation will take place on Saturday, April 5.
                                                                                     Weekday Activities
                                                                                      • Façade frame and glass installation continues during the week using boom lifts.
                                                                                      • Roofing and terrace activities are underway.
                                                                                      • Framing continues.
                                                                                      • Elevator work has begun.
                                                                                      • MEP activities are ongoing.
                                                                                      • Sub-flooring work continues.
                                                                                      • Mobile cranes will be on site every other day.
                                                                                       Sewer Work on Western Ave.
                                                                                      • Nighttime sewer tie-in work is scheduled to take place in front of the Treehouse Conference Center site on Western Avenue, Monday, April 7 through Thursday, April 10 from 7 p.m. to 5 a.m.
                                                                                      • Between Hague and Milestone streets, pedestrians will shift at night to the Harvard Business School side of the road and cyclists will share the road during these activities.
                                                                                      • A vehicular travel lane will be taken when crews are working in sewer manholes.
                                                                                      • Signage will be in place and two police details will be scheduled. Two-way traffic will be maintained.
                                                                                      • Crews will also be patching the roadway at night.
                                                                                      • The roadway will be plated during the day and on the weekend.
                                                                                      Building Mock-Ups
                                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                      Eversource Conduit Project
                                                                                      • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC. 
                                                                                      • Between Hague and Milestone streets, pedestrians will shift at night to the Harvard Business School side of the road and cyclists will share the road during these activities.
                                                                                      • A vehicular travel lane will be taken when crews are working in sewer manholes.
                                                                                      • Signage will be in place and two police details will be scheduled.
                                                                                      • Crews will also be patching the roadway at night.
                                                                                      • The roadway will be plated during the day and on the weekend. 
                                                                                       General
                                                                                        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                        • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                                                        • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                          • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                          • A drone is scheduled to fly Wednesday, April 9 at 2:30 p.m. 
                                                                                        Signage Project at SEC and Stadium Way
                                                                                        • A signage installation project in front of the SEC building continues.
                                                                                        • Barriers surround the work area.
                                                                                        North Allston Storm Drain Extension Project (NASDEP)
                                                                                        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                        • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                        • Science Drive is narrowed through fall 2025 with new line striping indicating the lanes.
                                                                                        • A pump truck will be needed for wall replacement operations.
                                                                                        • An onsite crane is needed for a box culvert installation.
                                                                                        • Backfilling operations for a temporary drainage bypass system will occur.
                                                                                        • A vacuum truck may be necessary on site to clean out the dewatering tank.
                                                                                        • A temporary drainage bypass system with an operator is running.
                                                                                        • A dewatering system has been installed.  
                                                                                        • A generator and motorized dewatering equipment operate on site.
                                                                                          92 Seattle Street  
                                                                                          • Project has received a COO.
                                                                                          • Interior fit out work has started and will continue for two weeks.
                                                                                          175 North Harvard Street, 100 South Campus Drive 
                                                                                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                          • Small miscellaneous concrete pours will occur once or twice a week as needed on the upper portion of the building along with stair placements. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing operations continue. Window and doorframe deliveries and window installation using boom lifts continue. Exterior wall sheathing continues. Work continues on doors and ramps. Stairs are being installed. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Exterior brickwork in the courtyard begins this month. Boom lifts and swing staging is on the low rise working on window installation.
                                                                                          • The contractor will need to close South Campus Drive during the week of April 7 between 7 a.m. to 5 p.m. to support lift access to the building’s west elevation, which cannot accommodate swing staging. The only available access for this work is via a large boom lift that will not fit within the fence line.
                                                                                          • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5:00 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive. 
                                                                                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                          • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. 
                                                                                          • Steel installation continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, and flooring are also being installed. The south tower stage wall is now up.
                                                                                          • Adjustments continue on the ART building mock-up to review design and constructability across North Harvard Street. 
                                                                                          • Work will be taking place at the affiliate housing building on the next two Saturdays, April 5 and April 12, to do some exterior wall sheathing, welding, and window installation.
                                                                                          • The crew at the ART project will not be working on Saturday, April 5. 
                                                                                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                           210 North Harvard Street
                                                                                          • Eversource or Verizon will remove an old pole and power line.
                                                                                          • The bakery Sofra is open. 
                                                                                          168 Western Ave
                                                                                          • Interior and roofing work continues.
                                                                                          • A crane pick is scheduled inside the Swiss Baker parking lot for Monday, April 7 from 7 a.m. to 3 p.m. Sixteen parking spaces will be blocked off for this activity.
                                                                                          • Plans are underway for gas work to start in mid-April or May. This work will close the Travis Street entrance and sidewalk and impact a few parking spaces.
                                                                                          • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.
                                                                                            114 Western Ave
                                                                                            Renovated Suite 3500 is occupied.

                                                                                            Anthony D'Isidoro

                                                                                            unread,
                                                                                            Apr 11, 2025, 8:12:17 AMApr 11
                                                                                            to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                            Residents, firefighters fire back (Jeff Sullivan, The Bulletin: April 10, 2025) 

                                                                                            The Boston City Council recently held a hearing with residents, industry experts, state officials and local officials to start crafting regulation around Battery Energy Storage Systems (BESS) in the city. 

                                                                                            The biggest concerns discussed were that of fire, fire safety and hazardous chemicals going into the air. 

                                                                                            The hearing comes after two somewhat controversial projects, one proposed at 35 Electric Ave. in Brighton and one proposed for 401 Cummins Hwy. on the Hyde Park, Roslindale and Mattapan lines. Both would be close to residential properties, with 35 Electric Ave.’s profile approaching 20 feet from a residential property line. 

                                                                                            Public regulation was the immediate focus. For large projects the state generally takes the lead – that’s anything over 100 megawatt hours of storage. All sorts of processes, regulations, and governmental mechanisms for control were discussed. 

                                                                                            In terms of safety procedure, Boston Fire Department (BFD) Captain Kelly said he was gratified that the department was being consulted at the beginning of the process. “We’re generally at the end, we see it once everything has been built and gone through,” he said. “With us being allowed to be here in the beginning, it allows us to address any life safety concerns that arise at the time, instead of at the end. That is going to save us a tremendous amount of time, money and headaches.” 

                                                                                            Kelly said that the BFD has not created any best practices for dealing with a fire at a BESS– as there aren’t currently any such facilities in the city – nor has it discussed any practices with cities that already have such facilities about what they plan to do in case of emergency. 

                                                                                            “I have had several conversations and meetings with third party consultants, private industry fire protection consultants regarding the best way to go about developing the procedures and standards we need here in Boston in terms of energy storage,” he said. 

                                                                                            District 9 City Councilor Liz Breadon asked the city representatives if they had conducted any kind of study to figure out where the best locations for large BESS systems should go. Green New Deal Director Oliver Sellers-Garcia said the short answer was “No.” 

                                                                                            “I think it’s because the nature of what a BESS is. It’s complex in a way that does not necessarily match a land-use based analysis,” he said. 

                                                                                            Garcia did say that the state’s siting suitability process, which was outlined in the recent 2024 BESS legislation https://tinyurl.com/4huxdt6t is something they will be keeping an eye on. 

                                                                                            The main problem with BESS, at least with the currently proposed lithium-ion models, is thermal runaway. That’s when one battery cell in the unit – of which there are hundreds – fails and overheats, which then causes a cascade effect, and all the cells start to overheat. This can cause explosive results – as what happened in Surprise, Arizona, in 2019 https://tinyurl.com/5376h3z7, or long-lasting fires that can take days to extinguish and can then reignite, as what recently happened in Moss Landing, California just this past January and February -https:// tinyurl.com/3znjhfcd 

                                                                                            Residents in Moss Landing reported after the 300 megawatt facility burst into flames, twice,- https://tinyurl.com/4mpjpn3m- negative respiratory health effects, and residents, especially those around Electric Avenue in Brighton, were concerned about those potential adverse health effects.

                                                                                            Massachusetts actually released a report about the toxicology of a BESS fire from MSN-RN EMTP Nantucket Fire Department Captain Timothy J. Vamosi ( https:// tinyurl.com/2fmypfxa ) that details how the chemicals in those fires change and can become dangerous, including hydrogen fluoride which can become hydrofluoric acid if it comes into contact with water. 

                                                                                            Tests from the Texas A&M Engineering Extension Service found that 24 heavy metals and 75 semi-volatile organic compounds were detected in burn bunker testing - https:// tinyurl.com/ya7a9vhy. The tests also found that heavy metals remained on firefighter protective gear, even after it was specifically cleaned to get rid of contaminants (as many firefighter laundry rooms are designed to work). 

                                                                                            Brighton resident Mary LaRosee said she was concerned about the fires and toxic gases. And Brighton resident and NFD firefighter Benny Upton said he had problems with the proximity to residential neighborhoods. 

                                                                                            “This facility is being proposed just 20 feet from residential neighborhood property lines,” he said. 

                                                                                            Upton said he was not buying any updates in safety infrastructure, as Flatiron Energy, the company behind the facility, cited improvements from the 2022 Moss Landing Fire during its Dec. 2024 presentation to the city to avoid similar accidents 

                                                                                            “Even after adopting California’s strict environmental standards – the toughest in the country – catastrophic failure still occurred, on Jan. 16 this year, a thermal runaway fire broke out at the Moss Landing facility, leading to the evacuation of 1,200 people, road closures, widespread reports of illness due to air degradation, heavy toxic metals, cobalt, nickel, magnesium and cooper were released into the air and state-of-the-art fire suppression systems failed to control the fire.” 

                                                                                            Upton said this same facility later reignited, as detailed above, in February. He said California is considering legislation to require 3,200 feet of setback for such BESS facilities. 

                                                                                            “Yet here in Brighton?” he said. “Flatiron is offering us 20 feet, putting hundreds of families at risk.” 

                                                                                            GreenRoots Director of Climate Justice John Walkey said after 10 years of fighting in East Boston over a power substation, he and the opposition learned a lot. He said despite the fact that the substation is under construction at the moment, it did result in increased public processes around electrical infrastructure. He also pointed out that it is ratepayers who ultimately pay for all this infrastructure. 

                                                                                            “They will be going to the Department of Public Utilities with a rate case and put the cost of this on ratepayers,” he said. “Don’t just think of this as a private company that’s building something with their money, it’s your money, because it’s coming out of ratepayers’ bills. So the benefits for the neighbors are the same as if it was a bunch of luxury condos. What does it do for the neighbors? Not much of anything except what you can get out of them in the community process.”

                                                                                            Boston Bulletin (April 10, 2025):

                                                                                            Anthony D'Isidoro

                                                                                            unread,
                                                                                            Apr 12, 2025, 9:49:42 AMApr 12
                                                                                            to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                            Harvard Construction Mitigation (Week of April 14, 2025)   

                                                                                            April 11, 2025

                                                                                            Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                            • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                            Enterprise Research Campus

                                                                                            Residential/Hotel
                                                                                            Weekend Activities
                                                                                            • On Saturday, April 12, the removal of concrete forms and materials will be underway at the loading dock off Trotting Avenue. Weather permitting, exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the infill hoist area. Elevator and miscellaneous interior work with operational hoists at all three buildings are planned.
                                                                                            • On Sunday, April 13 a crew of 12 will be completing removing forms and other concrete operation materials at the loading dock below the podium between the hotel and mid-rise. Additionally, 12 workers will be active in the high-rise and mid-rise elevator shafts. Hoists will be operational.
                                                                                            Weekday Activities
                                                                                            • Eversource may be on site making connections between their Trotting Avenue manhole and the building.
                                                                                            • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                            • A suspended scaffolding deck has been removed from the underside of the cantilevered section at the hotel.
                                                                                            • At the midrise the hoist has been removed, and infill work is underway.
                                                                                            • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                            • hotel.
                                                                                            • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                            • Elevators are being installed.
                                                                                            • Other concrete operations continue.
                                                                                            • Roofing activities are underway.
                                                                                            • MEP work is ongoing.
                                                                                            • Framing and bathroom installation are taking place inside the buildings.
                                                                                            • Temporary heaters are being removed.
                                                                                              Laboratory and Office Buildings.
                                                                                              Weekend Activities 
                                                                                              • On Saturday, April 12 exterior work will include miscellaneous roofing (weather permitting), interior drywall elevator install and MEP work in the penthouse as well as general clean-up activities.
                                                                                              • On Sunday, April 13 a crew of six will be working in the east building elevator shaft.
                                                                                              Weekday Activities
                                                                                                • Boom lifts are active around the perimeter of the buildings.
                                                                                                • Level 1 soffit and exterior work is underway.
                                                                                                • Smaller concrete operations continue.
                                                                                                • Roof activities are underway.
                                                                                                • Elevators are being installed.
                                                                                                • MEP work is ongoing.
                                                                                                • Mechanical penthouse activities continue.
                                                                                                • Masonry work continues.
                                                                                                • Framing and bathroom install are underway
                                                                                                • Temporary heaters are being disconnected.
                                                                                                Treehouse Conference Center
                                                                                                Weekend Activities
                                                                                                • Work includes façade (weather permitting), electrical, and dry-wall installation on Saturday, April 12.  A dry-wall delivery is expected.
                                                                                                Weekday Activities
                                                                                                  • Façade frame and glass installation continues during the week using boom lifts.
                                                                                                  • Roofing and terrace activities are underway.
                                                                                                  • Framing and drywall continues.
                                                                                                  • Elevator work has begun.
                                                                                                  • MEP activities are ongoing.
                                                                                                  • Sub-flooring work continues.
                                                                                                    Greenway
                                                                                                      • Light pole base work will take place.
                                                                                                      • Duct piping excavation, installation and backfilling will continue.
                                                                                                      • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                      Streetscape
                                                                                                      • Duct bank installation and road work has begun.
                                                                                                      Western Ave Roadway Work
                                                                                                      • On Saturday, April 12, crews will be patching Western Avenue.  Two-way traffic will be maintained. A police detail will be directing traffic, cyclists and pedestrians.
                                                                                                      Building Mock-Ups
                                                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                      Eversource Conduit Project
                                                                                                      • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                      General
                                                                                                        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                        • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                                                                        • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                          • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                          • A drone is scheduled to fly Thursday, April 17 at 2:30 p.m.
                                                                                                        Signage Project at SEC and Stadium Way
                                                                                                        • A signage installation project in front of the SEC building is finishing.
                                                                                                        North Allston Storm Drain Extension Project (NASDEP)
                                                                                                        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                        • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                        • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                        • A pump truck will be needed for wall replacement operations.
                                                                                                        • An onsite crane is needed for box culvert installation.
                                                                                                        • Backfilling operations intermittently occur.
                                                                                                        • A temporary drainage bypass system with an operator is running.
                                                                                                        • A generator and motorized dewatering equipment operate on site.
                                                                                                          92 Seattle Street
                                                                                                          • Project has received a COO. Minor punch list items are finishing.
                                                                                                          • Interior fit out work is complete.
                                                                                                          175 North Harvard Street, 100 South Campus Drive 
                                                                                                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                          • Small miscellaneous concrete pours will occur as needed on the upper portion of the building. Window and doorframe deliveries and window installation using boom lifts continue. Exterior wall sheathing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Exterior brickwork in the courtyard begins this month. Boom lifts and swing staging are on the low rise working on window installation. Roofing will progress if the weather is good. Once the roofing is down, the swing staging will be removed from the level 12 roof. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing continue. Work continues on doors and ramps. Stairs are being installed.
                                                                                                          • The contractor will need to close South Campus Drive on Wednesday, April 16, (weather dependent) to accommodate a crane needed to place mechanical equipment on the 10th and 14th floor roofs. Approximately once a week, a pumper truck will be on South Campus Drive to support concrete placements.
                                                                                                          • On other days during the week of April 14, the contractor will need to periodically close South Campus Drive between 7 a.m. to 5 p.m. to support lift access to the building’s west elevation, which cannot accommodate swing staging. The only available access for this work is via a large boom lift that will not fit within the fence line.
                                                                                                          • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                          • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. The rest of this month will focus on wall panels. An increase in trucking is expected for panel delivery.
                                                                                                          • Steel detailing work continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage. The south tower stage wall is now up.
                                                                                                          • Adjustments are paused on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                          • Work will be taking place at the affiliate housing building on the next two Saturdays, April 12 and April 19, to do some exterior wall sheathing, welding, and window installation. This work is dependent on the weather.
                                                                                                          • The crew at the ART project will be working on Saturdays, April 12 and 19, installing mass timber. This work is dependent on the weather.
                                                                                                          • Both job sites will be closed for the Patriot’s Day holiday on Monday, April 21.
                                                                                                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                          • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                          210 North Harvard Street
                                                                                                          • Eversource or Verizon will remove an old pole and power line.
                                                                                                          • The bakery Sofra is open. 
                                                                                                          168 Western Ave
                                                                                                          • Interior and roofing work continues.
                                                                                                          • A crane pick is scheduled for Monday, April 14 from 7 a.m. to 3 p.m. No traffic impacts are associated with this work.
                                                                                                          • Pre-clearing for gas line work is scheduled to begin on Tuesday, April 15 and continue
                                                                                                          • Into the following week. Sidewalk, the MBTA bus stop and Travis Street entrance to Swiss Bakers will be impacted during this work.
                                                                                                          • The sidewalk adjacent to Swiss Bakers on Travis Street will be closed with pedestrians shifted to the opposite side of the street. 
                                                                                                          • A  temporary walkway will be in place at the corner of Western Avenue and Travis Street while work is underway on that section of the Western Avenue sidewalk.  
                                                                                                          • The MBTA bus stop in front of Swiss Bakers on Western Avenue will move a few yards east away from the work zone.
                                                                                                          • The Travis Street entrance to Swiss Baker’s will be closed with customers directed to the parking lot entrance.
                                                                                                          • Workers in protective clothing will be meeting all regulatory requirements while removing soil. 
                                                                                                          • Construction equipment and trucks will be active in this area.
                                                                                                          • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.

                                                                                                          Anthony D'Isidoro

                                                                                                          unread,
                                                                                                          Apr 19, 2025, 12:21:47 PMApr 19
                                                                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                          Harvard Construction Mitigation (Week of April 21, 2025)   

                                                                                                          April 18, 2025

                                                                                                          Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                          • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                          Enterprise Research Campus
                                                                                                          Residential/Hotel
                                                                                                          Holiday Weekend Activities
                                                                                                          • On Saturday, April 19, exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the infill hoist area. Elevator and miscellaneous interior work with operational hoists at all three buildings are planned.
                                                                                                          • On Patriot’s Day, Monday, April 21, carpenters and plumbers will be working inside the mid-rise and high-rise buildings. Hoists will be operational.
                                                                                                          Weekday Activities
                                                                                                            • Eversource may be on site making connections between their Trotting Avenue manhole and the building.
                                                                                                            • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                            • At the midrise the hoist has been removed and infill work is underway.
                                                                                                            • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                                            • hotel.
                                                                                                            • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                            • Elevators are being installed.
                                                                                                            • Other concrete operations continue.
                                                                                                            • Roofing activities are underway.
                                                                                                            • MEP work is ongoing.
                                                                                                            • Framing and bathroom installation are taking place inside the buildings.
                                                                                                            • Temporary heaters are being removed.
                                                                                                              Laboratory and Office Buildings.
                                                                                                              No construction work will be taking place this holiday weekend.
                                                                                                              Weekday Activities
                                                                                                                • Boom lifts are active around the perimeter of the buildings.
                                                                                                                • Level 1 soffit and exterior work is underway.
                                                                                                                • Smaller concrete operations continue.
                                                                                                                • Roof activities are underway.
                                                                                                                • Elevators are being installed.
                                                                                                                • MEP work is ongoing.
                                                                                                                • Mechanical penthouse activities continue.
                                                                                                                • Masonry work continues.
                                                                                                                • Framing and bathroom install are underway
                                                                                                                • Spray-on insulation work will take place.
                                                                                                                • Temporary heaters are being disconnected.
                                                                                                                  Treehouse Conference Center
                                                                                                                  Holiday Weekend Activities
                                                                                                                  • Work includes façade, sub-floor, insulation and dry-wall installation as well as roofing activity on Saturday, April 19.  A duct bank delivery will take place.
                                                                                                                  • No construction work will be taking place on Patriot’s Day, Monday, April 21.
                                                                                                                  Weekday Activities
                                                                                                                    • Façade frame and glass installation continues during the week using boom lifts.
                                                                                                                    • Roofing and terrace activities are underway.
                                                                                                                    • Framing and drywall continues.
                                                                                                                    • Elevator work has begun.
                                                                                                                    • MEP activities are ongoing.
                                                                                                                    • Sub-flooring work continues
                                                                                                                    • Small concrete placements will take place.
                                                                                                                    Greenway
                                                                                                                      • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                      • Trees will begin to be planted.
                                                                                                                      Streetscape
                                                                                                                      • Duct bank and road work excavation has begun.
                                                                                                                      Western Ave Utility and Roadway Work
                                                                                                                      • Nighttime utility tie-in work is scheduled to take place in front of the Treehouse Conference Center site on Western Avenue, Tuesday, April 22 through Friday, April 25 from 7 p.m. to 5 a.m.
                                                                                                                      • Between Hague and Milestone streets, pedestrians will shift at night to the Harvard Business School side of the road and cyclists will share the road during these activities.
                                                                                                                      • A vehicular travel lane will be taken when crews are working in sewer manholes.
                                                                                                                      • Signage will be in place and two police details will be scheduled. Two-way traffic will be maintained.
                                                                                                                      • Crews will also be patching the roadway at night.
                                                                                                                      • The roadway will be plated during the day and on the weekend.
                                                                                                                      Building Mock-Ups
                                                                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                      Eversource Conduit Project
                                                                                                                      • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                      General
                                                                                                                      • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                      • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                                                                                      • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                        • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                        • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                        • A drone is scheduled to fly Thursday, April 24 at 2:30 p.m.
                                                                                                                      Signage Project at SEC and Stadium Way
                                                                                                                      • A signage installation project in front of the SEC building is finishing.
                                                                                                                      North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                      The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                      • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                      • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                      • Box culvert installations are ongoing.
                                                                                                                      • A pump truck will be needed for wall replacement operations.
                                                                                                                      • An onsite crane is needed for box culvert installation.
                                                                                                                      • Backfilling operations intermittently occur.
                                                                                                                      • A temporary drainage bypass system with an operator is running.
                                                                                                                      • A generator and motorized dewatering equipment operate on site.
                                                                                                                        92 Seattle Street
                                                                                                                          • Project has received a COO. Minor punch list items are finishing.
                                                                                                                          • Interior fit out work is complete.
                                                                                                                          • Knee wall work continues.
                                                                                                                          175 North Harvard Street, 100 South Campus Drive 
                                                                                                                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                          • Small miscellaneous concrete pours will occur as needed on the upper portion of the building. Window and doorframe deliveries and window installation using boom lifts continue. Exterior wall sheathing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Exterior brickwork in the courtyard begins this month. Boom lifts and swing staging are on the low rise working on window installation. Roofing is progressing. Once it is in place, the swing staging will be removed from the level 12 roof. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing continue. Work continues on doors and ramps. Stairs are being installed.
                                                                                                                          • The contractor will need to close South Campus Drive on Wednesday, April 23, (weather dependent) to accommodate a crane needed to lift insulation to the roof. Approximately once a week, a pumper truck will be on South Campus Drive to support concrete placements.
                                                                                                                          • On other days during the week of April 21, the contractor will need to periodically close South Campus Drive between 7 a.m. to 5 p.m. to support lift access to the building’s west elevation, which cannot accommodate swing staging. The only available access for this work is via a large boom lift that will not fit within the fence line.
                                                                                                                          • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                          • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. The rest of this month will focus on wall panels. An increase in trucking is expected for panel delivery.
                                                                                                                          • Steel detailing work continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage. The south tower stage wall is now up.
                                                                                                                          • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                          • Work will be taking place at the affiliate housing building on the next two Saturdays, April 19 and April 26, to do some exterior wall sheathing, masonry, and window installation. This work is dependent on the weather.
                                                                                                                          • The crew at the ART project will be working on Saturdays, April 19 and 26, installing mass timber. This work is dependent on the weather.
                                                                                                                          • Both job sites will be closed for the Patriot’s Day holiday on Monday, April 21.
                                                                                                                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                          • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                          210 North Harvard Street
                                                                                                                          • Eversource or Verizon will remove an old pole and power line.
                                                                                                                          • The bakery Sofra is open. 
                                                                                                                          168 Western Ave
                                                                                                                          • Interior and roofing work continues.
                                                                                                                          • A crane pick is scheduled for Thursday, April 24 from 2 to 6 p.m. Parking spaces will be occupied by the crane. No traffic impacts are associated with this work.
                                                                                                                          • Pre-clearing for gas line work is scheduled to begin on Tuesday, April 22 and continue into the following week.  Excavation will begin on Wednesday, April 23 and National Grid will be installing the pipe on Monday and Tuesday, April 28 and 29. Sidewalk, the MBTA bus stop and Travis Street entrance to Swiss Bakers will be impacted during this work.
                                                                                                                            • The sidewalk adjacent to Swiss Bakers on Travis Street will be closed with pedestrians shifted to the opposite side of the street. 
                                                                                                                            • A temporary walkway will be in place at the corner of Western Avenue and Travis Street while work is underway on that section of the Western Avenue sidewalk.
                                                                                                                            • The MBTA bus stop in front of Swiss Bakers on Western Avenue will move a few yards east away from the work zone.
                                                                                                                            • The Travis Street entrance to Swiss Baker’s will be closed with customers directed to the parking lot entrance.
                                                                                                                            • Workers in protective clothing will be meeting all regulatory requirements while removing soil. 
                                                                                                                            • Construction equipment and trucks will be active in this area.
                                                                                                                          • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.

                                                                                                                          Anthony D'Isidoro

                                                                                                                          unread,
                                                                                                                          Apr 25, 2025, 9:04:23 AMApr 25
                                                                                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                          ACA begins Boston Calling prep (Jeff Sullivan, The Bulletin: April 24, 2025) 

                                                                                                                          Last week at the Allston Civic Association (ACA), President Tony D’Isidoro introduced Boston Calling representative Kristen Franks to give the neighborhood an update on what’s happening with the three-day music festival this year at the Harvard Athletic Fields in Lower Allston. 

                                                                                                                          “In springtime, the flowers come up, the trees bud, the birds chirp and, most importantly, we have Kristen come by the ACA to talk a little bit about Boston Calling,” he said. 

                                                                                                                          Franks said this year’s festival has a 10:45 p.m. cut-off time for all music, with the aim being to get all audience out of the campus by 11 p.m. “We’re really trying to get everyone out. We have a great working relationship with (Boston Po lice Department [BPD] District) D-14 and all of the public safety agencies – Mass State Police, Cambridge Police and Harvard Police, MBTA Police and we’ve had several public safety meetings to date,” Franks said. 

                                                                                                                          Franks said there will be a big change this year because of Chappell Roan. At the time of her booking the festival for last year’s show, Hot to Go had just scratched the surface of the juggernaut that Good Luck Babe! would become. Franks said her 3 p.m. time slot saw about 30,000 people coming in to see her perform. She said that the two big stages to the north of the site, the Green and the Red stages will now be one stage in that area. She said this was because when they had two, there was a bottleneck that happened when Roan ended her set and so many people were either trying to get to the next performer or leave. 

                                                                                                                          “It’s going to be what is called a rotating stage, where when one band is performing, the next band is setting up,” she said. “It really just allows us – and I can’t wait to see this in person – to rotate the stage. People can get comfortable; our capacity’s not changing so this will allow people to spread out.” 

                                                                                                                          Franks said they will once again use the hockey arena for performances. This will provide an air-conditioned area for patrons to enter during what might be an extremely hot day. “We have partnered with the Berklee School of Music; there will be a lot of student bands in there,” she said. 

                                                                                                                          As in previous years, Franks said they will have the same sound team which will allow residents to call in if the sound is spilling over into the nearby neighborhoods. “We will also have people out on bikes and some on foot who will go out with a sound monitor and take recordings of the sound once we’ve adjusted the sound system too,” she said. “Last year, we didn’t really have to do too much of that because I think we’ve figured out that sweet spot and what levels to allow the artists to perform at. They all sign an agreement to not turn up the PA system. We have full autonomy over their sound production.” 

                                                                                                                          Franks said they will have a mailing going out to the neighborhood in the coming weeks and they will have a 24-hourhotline that will be staffed a week before the festival for neighborhood complaints. The mailing information will be posted on the ACA website at AllstonCivicAssociation.org 

                                                                                                                          Franks said much of the festival will run as before, with the ride-share lot being located at the Harvard Business School and buses and the Red Line will be running extra to accommodate the huge influx of people coming to the show. “We do a lot of work with some of our promoters and vendors to get people to visit the Allston and Brighton businesses ahead of time; we are an open gate type of thing so you can come in, leave and come back in,” she said. “We always try to promote the local businesses and chambers of commerce.” 

                                                                                                                          Franks said they will be at tending and donating Boston Calling Tickets to the Allston Brighton Chamber of Commerce dinner on Thursday, May 8 at 5 p.m. at the Heights Room at Corcoran Commons at Boston College. For more information, go to https://tinyurl.com/sexbjttc
                                                                                                                          ACA member Christine Varriale asked about ride-share enforcement, and Franks said to aide in discouraging drop offs where they’re not supposed to go, parts of Memorial Drive will be sectioned off from vehicles during the show.

                                                                                                                          Boston Bulletin (April 24, 2025):

                                                                                                                          Anthony D'Isidoro

                                                                                                                          unread,
                                                                                                                          Apr 26, 2025, 11:24:40 AMApr 26
                                                                                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                          Harvard Construction Mitigation (Week of April 28, 2025)   

                                                                                                                          April 25, 2025

                                                                                                                          Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

                                                                                                                          • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                          Enterprise Research Campus
                                                                                                                          Residential/Hotel
                                                                                                                          Weekend Activities
                                                                                                                          • On Saturday, April 26, exterior green panel installation and activity (weather dependent) may take place on the midrise and high-rise residential buildings with several boom lifts operating including the infill hoist area. Lintel work at the hotel may take place using boom lifts if weather permits. Elevator and miscellaneous interior work with operational hoists at all three buildings are planned.
                                                                                                                          • On Sunday, April 27, a crew of five will be installing louvers on boom lifts in the hoist area on the east side of the high-rise building. A dozen workers will be working inside the elevator shafts in the hotel and high-rise buildings. Hoists will be operational.
                                                                                                                          Weekday Activities 
                                                                                                                            • Eversource may be on site making connections between their Trotting Avenue manhole and the building.
                                                                                                                            • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                            • The hotel’s hoist will begin to be removed next week.  A crane will be operating onsite for this work.
                                                                                                                            • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                                                            • hotel.
                                                                                                                            • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                            • Elevators are being installed.
                                                                                                                            • Other concrete operations continue.
                                                                                                                            • Roofing activities are underway.
                                                                                                                            • MEP work is ongoing.
                                                                                                                            • Framing and bathroom/kitchen installations are taking place inside the buildings.
                                                                                                                            • Flooring and other finish fit-out activity is underway.
                                                                                                                            • Temporary heaters are being removed.
                                                                                                                              Laboratory and Office Buildings.
                                                                                                                              Weekend Activities
                                                                                                                              • On Saturday, April 26 exterior work will include first floor boom lift work (weather permitting), elevator and miscellaneous interior work as well as general clean-up activities.
                                                                                                                              Weekday Activities
                                                                                                                                • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                • Level 1 soffit and exterior work is underway.
                                                                                                                                • Smaller concrete operations continue.
                                                                                                                                • Roof activities are underway.
                                                                                                                                • Elevators are being installed.
                                                                                                                                • MEP work is ongoing.
                                                                                                                                • Mechanical penthouse activities continue.
                                                                                                                                • Masonry work continues.
                                                                                                                                • Framing and bathroom/kitchen install are underway
                                                                                                                                • Spray-on insulation work will take place.
                                                                                                                                • Flooring is being installed.
                                                                                                                                • Temporary heaters are being disconnected.
                                                                                                                                  Treehouse Conference Center
                                                                                                                                  Weekend Activities
                                                                                                                                  • Work includes façade (weather dependent) and dry-wall installation as well as roofing activity on Saturday, April 26.  A drywall delivery will take place.
                                                                                                                                  Weekday Activities
                                                                                                                                  • Façade frame and glass installation continues during the week using boom lifts.
                                                                                                                                  • Roofing and terrace activities are underway.
                                                                                                                                  • Framing and drywall continues.
                                                                                                                                  • Elevator work has begun.
                                                                                                                                  • MEP activities are ongoing.
                                                                                                                                  • Sub-flooring work continues
                                                                                                                                  • Small concrete placements will take place.
                                                                                                                                  Greenway
                                                                                                                                  • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                  • Trees are being delivered and planted.
                                                                                                                                  • Water feature piping will be installed.
                                                                                                                                  Streetscape
                                                                                                                                  • Sub-grade pre-clearing and excavation is underway surrounding the buildings on Trotting Avenue, Axle Way and Milestone Street.
                                                                                                                                  Western Avenue Roadway Restriping
                                                                                                                                  • At nighttime next week, crews will black out and restripe lines on Western Avenue in front of the ERC.
                                                                                                                                  Building Mock-Ups
                                                                                                                                  • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                  Fiber Optic Communications Installation
                                                                                                                                  • Fiber optic cable will be installed for Crown Castle at night on Monday, May 5 and Tuesday, May 6 into Wednesday, May 7 from 7 p.m. to 4 a.m. Crews will be accessing manholes throughout the ERC site and at Western Avenue.
                                                                                                                                  Eversource Conduit Project
                                                                                                                                  • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                  General
                                                                                                                                  • The project’s work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                  • Hoists (exterior construction elevators) are operating on hotel, lab and one residential building.
                                                                                                                                  • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                    • Weekly flights are weather dependent and are scheduled one weekday afternoon.
                                                                                                                                    • A drone is scheduled to fly Thursday, May 1 at 2:30 p.m.
                                                                                                                                  North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                  The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                  • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                  • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                  • Box culvert installations are finishing up.
                                                                                                                                  • A pump truck will be needed for wall replacement operations.
                                                                                                                                  • An onsite crane is needed for box culvert installation.
                                                                                                                                  • Backfilling operations intermittently occur.
                                                                                                                                  • Carpenters are installing form work and reinforcing steel.
                                                                                                                                  • A temporary drainage bypass system with an operator is running.
                                                                                                                                  • A generator and motorized dewatering equipment operate on site.
                                                                                                                                    92 Seattle Street
                                                                                                                                      • Project has received a COO.
                                                                                                                                      • Knee wall punch-list work is finishing up.
                                                                                                                                      175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                      The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                      • Window and doorframe deliveries and window installation using boom lifts continue. Exterior wall sheathing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and will be jumping to the tower next week. Roofing is progressing and a support crane will be on site next week to assist. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing continue. Work continues on doors and ramps. Stairs are being installed. Brick work started last week on the courtyard side of the building to be followed by the south side. Bricks are being delivered regularly.
                                                                                                                                      • During the week of April 28, the contractor will need to periodically close South Campus Drive between 7:00 a.m. to 5:00 p.m. to support lift access to the building’s west elevation, which cannot accommodate swing staging. The only available access for this work is via a large boom lift that will not fit within the fence line. In addition, to accommodate some trucks that are too large to make the turn into the job site, the contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                      • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5:00 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.  
                                                                                                                                      • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                      • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. The rest of this month will focus on wall panels. An increase in trucking is expected for panel delivery.  
                                                                                                                                      • Steel detailing work continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage.
                                                                                                                                      • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.  
                                                                                                                                      • Work will be taking place at the affiliate housing building on the next two Saturdays, April 26, and May 3, to do some exterior wall sheathing, masonry, window installation, and interior mechanical, electrical, and plumbing work. This work is dependent on the weather.
                                                                                                                                      • The crew at the ART project will be working on Saturdays, April 26, and May 3, installing mass timber. This work is dependent on the weather.
                                                                                                                                      • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                      • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                      210 North Harvard Street
                                                                                                                                      • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                      • The bakery Sofra is open. 
                                                                                                                                      168 Western Ave
                                                                                                                                      • Interior and roofing work continues.
                                                                                                                                      • National Grid will be installing the pipe on Monday and Tuesday, April 28 and 29. Sidewalk, the MBTA bus stop and Travis Street entrance to Swiss Bakers will be impacted during this work.
                                                                                                                                        • The sidewalk adjacent to Swiss Bakers on Travis Street will be closed with pedestrians shifted to the opposite side of the street. 
                                                                                                                                        • A temporary walkway will be in place at the corner of Western Avenue and Travis Street while work is underway on that section of the Western Avenue sidewalk.  
                                                                                                                                        • The MBTA bus stop in front of Swiss Bakers on Western Avenue will move a few yards east away from the work zone.
                                                                                                                                        • The Travis Street entrance to Swiss Baker’s will be closed with customers directed to the parking lot entrance.
                                                                                                                                        • Workers in protective clothing will be meeting all regulatory requirements while removing soil. 
                                                                                                                                        • Construction equipment and trucks will be active in this area.
                                                                                                                                      • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated.
                                                                                                                                        304 Western Ave
                                                                                                                                        • A catch basin installation project within the loading dock will begin on Wednesday, April 30, and the work is scheduled to be complete within two weeks.
                                                                                                                                        • Abutters will be notified.

                                                                                                                                        Anthony D'Isidoro

                                                                                                                                        unread,
                                                                                                                                        May 2, 2025, 5:17:55 PMMay 2
                                                                                                                                        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                        Jackson Mann perhaps on horizon, WRHS in limbo (Jeff Sullivan, The Bulletin: May 1, 2025)

                                                                                                                                        The Boston City Council Ways and Means Committee met recently and discussed the city’s capital projects budget and plan for the fiscal year 2026 (FY26). 

                                                                                                                                        The plan goes from FY26 to FY30 for about $4.5 billion budgeted for 390 projects. It should be noted that those projects are dependent on money, political willpower, necessity and staff all being available or present. Fiscal Year 26 is slated for about $560 million. 

                                                                                                                                        One subject that permeated the discussion was planning limbo, or, the fact that several projects get approved and initially funded, but never seem to go anywhere. 

                                                                                                                                        In Allston and West Roxbury, those projects include the Jackson Mann Boston Centers for Youth and Families (BCYF) Community Center and the West Roxbury Educational Complex, known colloquially as the West Roxbury High School (WRHS). 

                                                                                                                                        Controversy has been prevalent relative to both projects. Both buildings have had severe structural issues, with the WRHS being threatened with closing from 2017 onwards and eventually closing in 2019. The Jackson Mann K-8 School was being permanently closed in 2022 and the adjacent community center has since limped along, with announcements of the building to be shut down going out once a year since 2022 (the most recent was last year’s announcement that they would transfer programming to the Brighton High School basement, which was met with large opposition that presumably changed the course of administration to shore up the building for this year). 

                                                                                                                                        Both buildings have community support. Since the first announcements – and then retractions of said announcements in some cases for each building community support has been adamant. Rallies in Downtown at the Boston Public Schools (BPS) administration buildings kept the WRHS building open an extra two years longer than the then administration planned. More than 300 residents turned up for the Jackson Mann at a community meeting in the fall of 2024. 

                                                                                                                                        At the time, Chief of Operations for the City of Boston Dion Irish said the time to advocate was during the capital planning budget process. Which is now. 

                                                                                                                                        So District 9 City Councilor Liz Breadon and District 6 City Councilor Ben Weber each asked the administration what’s going on with these buildings and how they can best advocate for them. 

                                                                                                                                        Breadon said they’ve been discussing the Jackson Mann for years, but she’s at least a little heartened that the study planned for the more than $4.1 million expected project is moving forward this year. “It’s 280,000 square feet, and so what do we have to do to work with BPS to move that along,” she said. “Because we could sit here, contemplating our navals and considering our options, but we wouldn’t be further on. This is the only one we have. We don’t have a pool or a community center that can host a championship basketball competition and it could be a huge asset for our schools and neighborhood that’s lacking certain amenities. People want me to be able to show progress when I go back to the community.” 

                                                                                                                                        Irish said the study is moving forward and said the land the site sits on will allow for some interesting options. “We think the real estate is a great opportunity for us to find a way to leverage that and move this project forward,” he said. “So we will be assigning a project manager for this and engaging one of our consultants to work with the Planning Department and yourself as well to work on a plan on how we can advance this project. We can certainly have regular check-ins with you to make sure you know there is work in progress in the coming months.” 

                                                                                                                                        Next, the WRHS and Weber. 

                                                                                                                                        Relative to the WRHS, according to Weber, “Right now in District 6 we have WRHS; it’s like $18 million budgeted. We talked to BPS Superintendent (Mary) Skipper about this and there is no plan,” he said. “There won’t be a plan for years. So what can we do to get projects moving forward? If anyone has any advice for us to get projects moved up this ladder from ‘to be scheduled’ to design, what can we do as councilors?” 

                                                                                                                                        Chief Financial Officer for the City of Boston Ashley Groffenberger said the decision to advance a project “is based on a lot of factors.” “Money, staff capacity to deliver, what other projects are we working on at the time are all considered. Things are moving forward and we are making space in terms of money and staff capacity. It’s helpful to have a sense of priority as to what the council, the mayor, and the community wants to see filling in as things move through the pipeline,” she said. 

                                                                                                                                        Breadon also discussed the overall financial strategy of the capital planning process. She pointed out that the city has a debt limit of about $7 billion because of its Triple A rating for this time period, but is only accessing $4.5 billion. She said she felt this was inefficient, as putting projects on hold just makes them more costly in the long run. 

                                                                                                                                        “I’ve seen projects sitting there, and by the time we get around to doing them, the cost of doing them is now three times what it was when it was first proposed,” she said. 

                                                                                                                                        Groffenberger said city debt policy restricts borrowing in this regard. “That $7 billion figure is the statutory debt limit, but we hold ourselves to a much lower debt limit,” she said. “It’s a function of the general fund budget, and so the city could decide to increase that limit so it could issue more bonds (borrow more money) and, given our standing and our rating, we would have no problem issuing more bonds and issuing more debt. The only trade-off would be you have to spend more in the operating budget in debt service. It’s a choice, a trade-off and at this time we’re not anticipating making any changes to our debt policy but it’s a choice we could explore in the future.” 

                                                                                                                                        It could expand capital options in the future, if such borrowing increases were implemented.

                                                                                                                                        Boston Bulletin (May 1, 2025):

                                                                                                                                        Anthony D'Isidoro

                                                                                                                                        unread,
                                                                                                                                        May 3, 2025, 2:34:09 PMMay 3
                                                                                                                                        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                        Harvard Construction Mitigation (Week of May 5, 2025)   

                                                                                                                                        May 2, 2025

                                                                                                                                        Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                        • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                        Enterprise Research Campus
                                                                                                                                        Residential/Hotel

                                                                                                                                        Weekend Activities
                                                                                                                                        • On Saturday, May 3, the site will have several activities underway, weather permitting. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the infill hoist area. Elevator and miscellaneous interior work with an operational hoist in the high-rise building.
                                                                                                                                        • On Sunday, May 4, a dozen workers will be working inside the hotel and high-rise building elevator shafts. Another six workers will be installing drywall in the first-floor area where the midrise meets the highrise.
                                                                                                                                        Weekday Activities
                                                                                                                                        • Crews are scheduled to work at the midrise off Trotting Avenue, on the first and second floor exterior façade from 7 to 11 p.m. Boom and scissor lifts and light towers pointed at the building will be operational.
                                                                                                                                        • Eversource may be on site finishing permanent power connections.
                                                                                                                                        • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                        • At the midrise the hoist has been removed and infill work is underway.
                                                                                                                                        • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                                                                        • hotel.
                                                                                                                                        • The hotel hoist continues to be removed with a crane on site.
                                                                                                                                        • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                        • Elevators are being installed.
                                                                                                                                        • Other concrete operations continue.
                                                                                                                                        • Roofing activities are underway.
                                                                                                                                        • MEP work is ongoing.
                                                                                                                                        • Framing and bathroom installation are taking place inside the buildings.
                                                                                                                                        • Temporary heaters are being removed.
                                                                                                                                          Laboratory and Office Buildings.
                                                                                                                                          • On Saturday, May 3 exterior work will include interior drywall, elevator install and MEP work in the penthouse as well as general clean-up activities.
                                                                                                                                          • On Sunday, May 4 a crew of six will be working in the east building elevator shaft.
                                                                                                                                          Weekday Activities
                                                                                                                                            • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                            • Level 1 soffit and exterior work is underway.
                                                                                                                                            • Smaller concrete operations continue.
                                                                                                                                            • Roof activities are underway.
                                                                                                                                            • Elevators are being installed.
                                                                                                                                            • MEP work is ongoing.
                                                                                                                                            • Mechanical penthouse activities continue.
                                                                                                                                            • Masonry work continues.
                                                                                                                                            • Framing and bathroom install are underway
                                                                                                                                            • Spray-on insulation work will take place.
                                                                                                                                            • Temporary heaters are being disconnected.
                                                                                                                                            Treehouse Conference Center
                                                                                                                                            Weekend Activities
                                                                                                                                            • Work includes façade, sub-floor, insulation and dry-wall installation as well as roofing activity on Saturday, May 3.  A duct bank delivery will take place.
                                                                                                                                            Weekday Activities
                                                                                                                                            • Façade frame and glass installation continues using boom lifts.
                                                                                                                                            • Roofing and terrace activities are underway.
                                                                                                                                            • Framing and drywall continue.
                                                                                                                                            • Elevator work continues.
                                                                                                                                            • MEP activities are ongoing.
                                                                                                                                            • Flooring work continues
                                                                                                                                            • Small concrete placements will take place.
                                                                                                                                              Greenway
                                                                                                                                                • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                • Trees continue to be planted.
                                                                                                                                                • Prep work is underway for water features.
                                                                                                                                                • Small concrete placements will take place.
                                                                                                                                                • Work continues on the shared use path.
                                                                                                                                                Streetscape
                                                                                                                                                • Pre-clearing and excavation continues on Trotting near the buildings.
                                                                                                                                                Building Mock-Ups
                                                                                                                                                • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                Nighttime Fiberoptic Manhole Work
                                                                                                                                                • Fiber-optic cables will be pulled between manholes at Western Avenue onto Trotting Avenue and Milestone streets, and on Axle Way inside the ERC site at night on Monday and Tuesday, May 5 and 6 and into Wednesday, May 7 from 7 p.m. to 4 a.m.
                                                                                                                                                Eversource Conduit Project
                                                                                                                                                • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                General
                                                                                                                                                • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                • Hoists (exterior construction elevators) are operating on the residential, hotel and lab buildings.
                                                                                                                                                • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                  • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                  • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                  • A drone is scheduled to fly Friday, May 2 at 3 p.m. and on Thursday, May 8 at 3 p.m.
                                                                                                                                                North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                • Box culvert installations are finishing up.
                                                                                                                                                • An onsite crane is needed for box culvert installation.
                                                                                                                                                • Rebar installations are underway.  
                                                                                                                                                • A pump truck will be needed for wall replacement operations.
                                                                                                                                                • Backfilling operations intermittently occur.
                                                                                                                                                • Truck traffic will increase to load in material.
                                                                                                                                                • A temporary drainage bypass system with an operator is running.
                                                                                                                                                • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                  92 Seattle Street
                                                                                                                                                    • Project has received a COO.
                                                                                                                                                    • Knee wall punch-list work is finishing up once the mock-up is approved.
                                                                                                                                                    175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                    The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                    • Window installation using boom lifts continues. Exterior wall sheathing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and will be jumping to the tower next week. Brick work is underway on the courtyard side of the building to be followed by the south side. Bricks are being delivered regularly. Roofing is progressing and a support crane will be on site to assist. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing continue. Work continues on doors and ramps. Stairs are being installed. Miscellaneous deliveries to the hoist will continue.
                                                                                                                                                    • During the week of May 5, the contractor will need to periodically close South Campus Drive between 7 a.m. to 5 p.m. to support lift access to the building’s west elevation, which cannot accommodate swing staging. The only available access for this work is via a large boom lift that will not fit within the fence line. In addition, to accommodate some trucks that are too large to make the turn into the job site, the contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                    • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                    • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                    • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. Currently crews are finishing wrapping the skin of the section at the high point of the fly tower. Next week, Mass Timber work will begin on an adjacent section of the building closest to South Campus Drive through the month of May.
                                                                                                                                                    • Steel detailing work continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage. South stair tower installation continues.
                                                                                                                                                    • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                                                    • Work will be taking place at the affiliate housing building on the next two Saturdays, May 3 and May 10, to do some exterior wall sheathing, masonry, window installation, and interior framing and mechanical, electrical, and plumbing work. This work is dependent on the weather.
                                                                                                                                                    • A small crew at the ART project will be working on Saturday, May 3, installing mass timber. This work is dependent on the weather.
                                                                                                                                                    • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                    • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                    210 North Harvard Street
                                                                                                                                                    • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                    • The bakery Sofra is open. 
                                                                                                                                                    168 Western Ave
                                                                                                                                                    • Epoxy flooring work will take place inside the building on Saturday and Sunday, May 3 and 4, from 7 a.m. to 3 p.m.
                                                                                                                                                    • National Grid has completed the gas pipe connection and will restore and clean up.
                                                                                                                                                    • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 
                                                                                                                                                      304 Western Ave
                                                                                                                                                      • A catch basin installation project within the loading dock began on Wednesday, April 30, and the work is scheduled to be complete within two weeks.

                                                                                                                                                      Anthony D'Isidoro

                                                                                                                                                      unread,
                                                                                                                                                      May 11, 2025, 8:33:47 AMMay 11
                                                                                                                                                      to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                      Harvard Construction Mitigation (Week of May 12, 2025)   

                                                                                                                                                      May 9, 2025

                                                                                                                                                      Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                      • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                      Enterprise Research Campus

                                                                                                                                                      Residential/Hotel

                                                                                                                                                      Weekend Activities
                                                                                                                                                      • On Saturday, May 10, the site will have several activities underway, weather permitting. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the infill hoist. Windows delivery areas on set up near swing staging on the high rise. Elevator and miscellaneous interior work in all three buildings.
                                                                                                                                                      • On Sunday, May 11, a dozen workers will be working inside the hotel and high-rise building elevator shafts. Another dozen workers will be installing drywall in the first floor area at the where the midrise meets the high-rise.
                                                                                                                                                      Weekday Activities 
                                                                                                                                                        • Crews are scheduled to work at the midrise off Trotting Avenue, on the first and second floor exterior façade from 7 to 11 p.m. Boom and scissor lifts and light towers pointed at the building will be operational.
                                                                                                                                                        • Eversource may be on site finishing permanent power connections.
                                                                                                                                                        • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                        • At the midrise the hoist has been removed, and infill work is underway.
                                                                                                                                                        • The high rise hoist will begin to be removed using a crane.
                                                                                                                                                        • The hotel hoist continues to be removed with a crane on site.
                                                                                                                                                        • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the hotel.
                                                                                                                                                        • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                        • Elevators are being installed.
                                                                                                                                                        • Other concrete operations continue.
                                                                                                                                                        • Roofing activities are underway.
                                                                                                                                                        • MEP work is ongoing.
                                                                                                                                                        • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                        • Temporary heaters are being removed.
                                                                                                                                                          Laboratory and Office Buildings.
                                                                                                                                                          • On Saturday, May 10 exterior curtainwall work, weather permitting, will be underway.  Interior drywall, elevator installation and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                          • On Sunday, May 11 a crew of six will be working in the east building elevator shaft.
                                                                                                                                                          Weekday Activities
                                                                                                                                                            • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                            • Level 1 soffit and exterior work is underway.
                                                                                                                                                            • Smaller concrete operations continue. 
                                                                                                                                                            • Roof activities are underway.
                                                                                                                                                            • Elevators are being installed.
                                                                                                                                                            • MEP work is ongoing.
                                                                                                                                                            • Mechanical penthouse activities continue.
                                                                                                                                                            • Masonry work continues.
                                                                                                                                                            • Pre-clearing for hardscape/landscape will take place
                                                                                                                                                            • Framing, drywall, and bathroom install are underway
                                                                                                                                                            Treehouse Conference Center
                                                                                                                                                            Weekend Activities
                                                                                                                                                            • Work includes curtainwall installation (weather permitting), insulation and dry-wall installation as well as roofing activity on Saturday, May 10. 
                                                                                                                                                            • On Sunday, May 11, a crew of 25 may be installing curtainwall, weather permitting.
                                                                                                                                                            Weekday Activities
                                                                                                                                                              • Façade frame and glass installation continues using boom lifts.
                                                                                                                                                              • Roofing and terrace activities are underway.
                                                                                                                                                              • Excavation for drainage work and a pedestrian area are underway.
                                                                                                                                                              • Framing and drywall continue.
                                                                                                                                                              • Elevator work continues.
                                                                                                                                                              • MEP activities are ongoing.
                                                                                                                                                              • Flooring work continues
                                                                                                                                                              • Small concrete placements will take place.
                                                                                                                                                                Greenway
                                                                                                                                                                  • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                  • Trees continue to be delivered and planted.
                                                                                                                                                                  • Prep and utility work is underway for water features.
                                                                                                                                                                  Streetscape
                                                                                                                                                                  • Piping in the trench continues on Trotting near the buildings.
                                                                                                                                                                  Building Mock-Ups
                                                                                                                                                                  • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                  Eversource Conduit Project
                                                                                                                                                                  • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                  General
                                                                                                                                                                  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                  • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                    • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                    • A drone is scheduled to fly on Thursday, May 15 at 3 p.m.
                                                                                                                                                                  North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                  The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                  • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                  • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                  • Structure and box culvert activity continues.
                                                                                                                                                                  • Backfilling operations intermittently occur.
                                                                                                                                                                  • Truck traffic will increase to load in material.
                                                                                                                                                                  • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                  • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                    92 Seattle Street
                                                                                                                                                                      • Project has received a COO.
                                                                                                                                                                      • Replacing and repowering roof equipment is underway.
                                                                                                                                                                      • Knee wall mock-up for the west wall repair is complete. Waiting for review to proceed with the work.  
                                                                                                                                                                      • All work is targeting completion in four weeks.
                                                                                                                                                                      175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                      The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                      • Window installation using boom lifts continues. Exterior wall sheathing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and will be jumping to the tower next week. In the next week and half, a crane in the next week and half will load roofing material to the 8th and 10th story roof. Brick work is underway on the courtyard side of the building to be followed by the south side. Bricks are being delivered regularly. Roofing is progressing and a support crane is on site to assist. Mechanical, electrical, and plumbing trades continue to work throughout the site. Interior fit out and framing continues. Drywall operations will begin in June. Miscellaneous deliveries to the hoist will continue.
                                                                                                                                                                      • During the week of May 12, the contractor will need to periodically close South Campus Drive between 7 a.m. to 5 p.m. to accommodate some trucks that are too large to make the turn into the job site, the contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                      • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. South Campus Drive will be open to traffic each day after 5 p.m. and on Sunday. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                      • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                      • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber (engineered wood products known for their strength, durability, versatility and sustainability) for the next several months. Daily wood deliveries are underway. Currently crews are finishing wrapping the skin of the section at the high point of the fly tower. Mass Timber work has begun on an adjacent section of the building closest to South Campus Drive through the month of May. The project added a 100-ton crane in the access road to assist with chimneys, which is expected to be completed by May 23. Masonry work is mobilizing this month.
                                                                                                                                                                      • Steel detailing work continues ahead of waterproofing. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage.
                                                                                                                                                                      • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                      • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                                                                      • Work will be taking place at the affiliate housing building on the next two Saturdays, May 10 and May 17, to do some exterior wall sheathing, window installation, and interior framing and mechanical, electrical, and plumbing work. This work is dependent on the weather.
                                                                                                                                                                      • A small crew at the ART project will be working on Saturdays, May 10 and 17, installing mass timber. This work is dependent on the weather.
                                                                                                                                                                      • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                      • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                      210 North Harvard Street
                                                                                                                                                                      • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                      • The bakery Sofra is open. 
                                                                                                                                                                      168 Western Ave
                                                                                                                                                                      • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                      • Mechanical roof work continues.
                                                                                                                                                                      • On Wednesday, May 14, crews will be installing the storefront.  
                                                                                                                                                                      • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 
                                                                                                                                                                        304 Western Ave
                                                                                                                                                                        • A catch basin installation project within the loading dock has been completed.

                                                                                                                                                                        Anthony D'Isidoro

                                                                                                                                                                        unread,
                                                                                                                                                                        May 24, 2025, 9:07:14 AMMay 24
                                                                                                                                                                        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                        Harvard Construction Mitigation (Week of May 26, 2025)   

                                                                                                                                                                        May 23, 2025

                                                                                                                                                                        Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                        • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                        Enterprise Research Campus

                                                                                                                                                                        Residential/Hotel

                                                                                                                                                                        Weekend Activities
                                                                                                                                                                        • On Saturday, May 24, the site will have several activities underway, weather permitting. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including at the mid-rise hoist infill area. Window material delivery areas are set up near swing staging on the high rise. Roofing activity may take place. Elevator and miscellaneous interior work in all three buildings.
                                                                                                                                                                        • On Sunday, May 25, eight workers will be inside the hotel and high-rise building elevator shafts, and a dozen carpenters will be working in the area where the hoist was removed at the high-rise doing infill work.
                                                                                                                                                                        • Exterior work is weather permitting.
                                                                                                                                                                        • On Monday, May 26, Memorial Day, eight workers will be inside the hotel and high-rise building elevator shafts, and a dozen carpenters will be working in the area where the hoist was removed at the high-rise doing infill work. Exterior work is weather permitting.
                                                                                                                                                                        Weekday Activities
                                                                                                                                                                        • Crews are scheduled to work at the midrise off Trotting Avenue, on the first and second floor exterior façade from 3 to 11 p.m. Boom and scissors lifts and light towers pointed at the building will be operational. Some infill work and excavation near the foundation will take place at the hotel on Wednesday, May 28, weather permitting.
                                                                                                                                                                        • Eversource may be on site finishing permanent power connections.
                                                                                                                                                                        • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                                        • At the midrise the hoist has been removed, and infill work is underway.
                                                                                                                                                                        • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                                                                                                        • hotel.
                                                                                                                                                                        • A crane will be on site starting Wednesday, May 28 to work on infilling the curtainwall where the hoist was.
                                                                                                                                                                        • Mast climbers scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                        • Elevators are being installed.
                                                                                                                                                                        • Other concrete operations continue.
                                                                                                                                                                        • Roofing activities are underway.
                                                                                                                                                                        • MEP work is ongoing.
                                                                                                                                                                        • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                          Laboratory and Office Buildings.
                                                                                                                                                                          • On Saturday, May 24, exterior curtainwall work, weather permitting, will be underway.  Interior drywall, elevator installation and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                                          • No work is planned for Sunday, May 25 or Monday, May 26, Memorial Day.
                                                                                                                                                                          Weekday Activities
                                                                                                                                                                            • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                            • Level 1 soffit and exterior work is underway.
                                                                                                                                                                            • Smaller concrete operations continue.
                                                                                                                                                                            • Roof activities are underway.
                                                                                                                                                                            • Elevators are being installed and inspected.
                                                                                                                                                                            • MEP work is ongoing.
                                                                                                                                                                            • Mechanical penthouse activities continue.
                                                                                                                                                                            • Masonry work continues.
                                                                                                                                                                            • Irrigation work will take place on Axel Way.
                                                                                                                                                                            • Framing, drywall and bathroom install are underway.
                                                                                                                                                                            Treehouse Conference Center
                                                                                                                                                                            Weekend Activities
                                                                                                                                                                            • Work includes roofing delivery and south roof installation (weather permitting) with a crane operating, façade work, flooring and drywall installation on Saturday, May 24. 
                                                                                                                                                                            • A crew of twelve roofers may be working on Sunday, May 25.
                                                                                                                                                                            • No work is taking place on Monday, May 26, Memorial Day.
                                                                                                                                                                            Weekday Activities
                                                                                                                                                                            • A small crew is scheduled to work installing facade clips and caulking from 3 to 11 p.m. using lifts.
                                                                                                                                                                            • Cranes are assisting with roofing and terrace activities.
                                                                                                                                                                            • Duct bank work will begin. 
                                                                                                                                                                            • Framing and drywall continue.
                                                                                                                                                                            • Elevator work continues.
                                                                                                                                                                            • MEP activities are ongoing.
                                                                                                                                                                            • Flooring work continues including third level sub-base flooring install on Tuesday, May 27.
                                                                                                                                                                            • Small concrete placements will take place.
                                                                                                                                                                              Greenway
                                                                                                                                                                                • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                                • Trees continue to be planted.
                                                                                                                                                                                • Prep and utility work is underway for water features.
                                                                                                                                                                                • Outcropping (boulder) install to take place.
                                                                                                                                                                                Streetscape
                                                                                                                                                                                Weekend Activities
                                                                                                                                                                                • On Saturday, May 24, structural soils will be installed along Trotting Avenue will all work contained within the site.
                                                                                                                                                                                • No work is planned for Sunday, May 25 or Monday, May 26, Memorial Day.
                                                                                                                                                                                Weekday Activities
                                                                                                                                                                                • Work and backfilling in the trench will take place on Trotting Avenue near the buildings.
                                                                                                                                                                                Evening Fiberoptic Manhole Work
                                                                                                                                                                                • Fiber-optic work will take place at manholes Milestone Street, and Axle Way inside the ERC site on Tuesday, June 3 from 5 p.m. to midnight
                                                                                                                                                                                Building Mock-Ups
                                                                                                                                                                                • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                Eversource Conduit Project
                                                                                                                                                                                • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                General
                                                                                                                                                                                • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                • All projects will be working on Thursday, May 29 with limited deliveries during Harvard’s Commencement.
                                                                                                                                                                                • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                  • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                  • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                  • A drone flight is scheduled to fly on Friday May 31 at 3 p.m.
                                                                                                                                                                                North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                • Interior work only on commencement day, May 29.
                                                                                                                                                                                • Structure and box culvert activity continues.
                                                                                                                                                                                • Backfilling operations intermittently occur.
                                                                                                                                                                                • Truck traffic will increase to load in material.
                                                                                                                                                                                • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                92 Seattle Street
                                                                                                                                                                                • Project has received a COO.
                                                                                                                                                                                • Replacing and repowering roof equipment is underway.
                                                                                                                                                                                • Knee wall mock-up for the west wall repair is complete. Waiting for review to proceed with the work.  
                                                                                                                                                                                • All work is targeting completion in four weeks.
                                                                                                                                                                                175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                • Window installation using boom lifts continues. Exterior wall framing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and the tower. More swing staging will be coming in at the north tower. Brick work is ramping up and will be in full swing in the next couple of weeks. Brick deliveries will start to increase. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation in the south tower continues. Drywall work is scheduled to begin in June. A crane is arriving the first week of June to support work on the north tower.
                                                                                                                                                                                • During the weeks of May 26 and June 2, excluding Sundays and Monday, May 26, the contractor will need to close South Campus Drive between 7 a.m. to 5 p.m. to accommodate lift access. South Campus Drive will be open to traffic each day after 5 p.m.
                                                                                                                                                                                • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                • On the new American Repertory Theater (ART) work site, the project has a crane in place to install mass timber for the next several months. Daily wood deliveries continue. Crews are finishing walls at the fly tower section. Mass Timber work continues on an adjacent section of the building closest to South Campus Drive through the month of May. A 100-ton crane is positioned in the access road to assist with chimneys, which may extend into next week due to weather. Masonry work is underway. Additional trades will arrive on site next week for block work, roof level parapet work, and slab on deck pours. This work is in preparation for roofers to be on site beginning Monday, June 23. Work will be taking place on lower plenum level block walls and roof topping slabs.
                                                                                                                                                                                • Steel detailing work continues ahead of waterproofing. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage.
                                                                                                                                                                                • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                                                                                • Work will be taking place at the affiliate housing building on the next two Saturdays, May 24 and May 31, to do some exterior wall sheathing, window installation, and interior framing and mechanical, electrical, and plumbing work. This work is dependent on weather.
                                                                                                                                                                                • There will not be any work at the ART project on Saturday, May 24.
                                                                                                                                                                                • Please note that both projects will have onsite security during Boston Calling from 2 p.m. to 12 a.m. on Friday through Sunday, May 23-25.
                                                                                                                                                                                • The projects will be closed on Monday, May 26, for the Memorial Day holiday. Both projects are planning to work on Thursday, May 29, during Harvard’s Commencement.
                                                                                                                                                                                • As a component of Harvard’s public benefit commitments with the City of Boston, Harvard University Housing is working with Cambridge Landscaping to replace approximately 60 dead trees throughout Smith Field, adjacent to the new affiliate housing building. Several of those trees abut South Campus Drive adjacent to the Continuum. The work is scheduled to begin on Tuesday, May 27, and will take several weeks to complete. The project scope also includes installation of a new accessible ramp between South Campus Drive and the park, which is in the approvals process.
                                                                                                                                                                                • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                210 North Harvard Street
                                                                                                                                                                                • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                • The bakery Sofra is open. 
                                                                                                                                                                                168 Western Ave
                                                                                                                                                                                • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                • Mechanical roof work continues and is scheduled to be completed by the end of next week.
                                                                                                                                                                                • Paving is planned for Monday, June 2 within the site fence.
                                                                                                                                                                                • Storefront work is wrapping up. Crews will be back to place film on the glass.
                                                                                                                                                                                • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 

                                                                                                                                                                                Anthony D'Isidoro

                                                                                                                                                                                unread,
                                                                                                                                                                                May 31, 2025, 8:17:12 AMMay 31
                                                                                                                                                                                to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                Harvard Construction Mitigation (Week of June 2, 2025)   

                                                                                                                                                                                May 30, 2025

                                                                                                                                                                                Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank

                                                                                                                                                                                • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                Enterprise Research Campus

                                                                                                                                                                                Residential/Hotel

                                                                                                                                                                                Weekend Activities
                                                                                                                                                                                • On Saturday, May 31, the site will have several activities underway, weather permitting. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including at the mid-rise hoist infill area. Window material delivery areas are set up near swing staging on the high rise. Paver and stone work will be taking place on the east deck, weather permitting. Roofing activity may take place. Elevator and miscellaneous interior work in all three buildings.
                                                                                                                                                                                • On Sunday, June 1, 20 workers will be inside the garage cleaning up.  Eight workers will be inside the hotel and high-rise building elevator shafts. Paver and stone work will be taking place with 15 workers on the east deck.
                                                                                                                                                                                Weekday Activities
                                                                                                                                                                                • Crews are scheduled to work at the midrise off Trotting Avenue, on the first and second floor exterior façade from 3 to 11 p.m. Boom and scissor lifts and light towers pointed at the building will be operational.
                                                                                                                                                                                • Night crews will be pre-clearing at the loading dock using an excavator and truck from 9 p.m. to 5 a.m.
                                                                                                                                                                                • Eversource may be on site finishing permanent power connections.
                                                                                                                                                                                • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                                                • At the midrise and high rise, the hoists have been removed and infill work is underway.
                                                                                                                                                                                • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                • A crane will be set up on Trotting Avenue on Monday, June 2, to work on infilling the hotel curtainwall former hoist area.
                                                                                                                                                                                • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                • Elevators are being installed.
                                                                                                                                                                                • Other concrete operations continue.
                                                                                                                                                                                • Some roofing activities continue.
                                                                                                                                                                                • MEP work is ongoing.
                                                                                                                                                                                • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                  Laboratory and Office Buildings.
                                                                                                                                                                                  • On Saturday, May 31, exterior work on the first floor and roofing activity, weather permitting, will be underway. Interior drywall, elevator install and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                                                  • On Sunday, June 1, six workers will be doing roofing activity.
                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                    • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                    • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                    • Smaller concrete operations continue.
                                                                                                                                                                                    • Roof activities are underway.
                                                                                                                                                                                    • Elevators are being installed and inspected.
                                                                                                                                                                                    • MEP work is ongoing.
                                                                                                                                                                                    • Mechanical penthouse activities continue.
                                                                                                                                                                                    • Masonry work continues.
                                                                                                                                                                                    • Irrigation work will take place on Axel Way.
                                                                                                                                                                                    • Landscapers will be placing stones.
                                                                                                                                                                                    • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                    Treehouse Conference Center
                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                    • Work includes roofing install (weather permitting) with a crane operating, façade work, flooring, dry-wall and miscellaneous interior work on Saturday, May 31. 
                                                                                                                                                                                    • On Sunday, June1, approximately eight to ten roofers will be working with a few workers cleaning up the site.
                                                                                                                                                                                    Weekday Activities
                                                                                                                                                                                      • A small crew is scheduled to work installing facade clips and caulking from 3 to 11 p.m. using lifts.
                                                                                                                                                                                      • Cranes are assisting with roofing and terrace activities.
                                                                                                                                                                                      • Duct bank work will begin. 
                                                                                                                                                                                      • Framing and drywall continue.
                                                                                                                                                                                      • Elevator work continues.
                                                                                                                                                                                      • MEP activities are ongoing.
                                                                                                                                                                                      • Flooring work continues.
                                                                                                                                                                                      • Small concrete placements will take place.
                                                                                                                                                                                      • Bathroom work has begun.
                                                                                                                                                                                      Evening Thermal Work
                                                                                                                                                                                      • Underground water pipe investigative, repair and testing work may take place on weeknights in two areas near the Treehouse beginning Wednesday, June 4 for two weeks from 4 p.m. until midnight.
                                                                                                                                                                                      Greenway
                                                                                                                                                                                        • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                                        • Trees continue to be planted.
                                                                                                                                                                                        • Prep and utility work is underway for water features.
                                                                                                                                                                                        • Outcropping (boulder) install continues.
                                                                                                                                                                                        Streetscape
                                                                                                                                                                                        Weekend Activities
                                                                                                                                                                                        • On Saturday, May 31, structural soils will be installed along Trotting Avenue. All work will be contained within the site.
                                                                                                                                                                                        • No work is planned for Sunday, June1.
                                                                                                                                                                                        Weekday/night Activities
                                                                                                                                                                                          • Work and backfilling in the trench will take place on Trotting Avenue near the buildings.
                                                                                                                                                                                          • Night crews will be pre-clearing at the residential/hotel loading dock on Trotting Avenue using an excavator and truck from 9 p.m. to 5 a.m.
                                                                                                                                                                                          Evening Fiberoptic Manhole Work
                                                                                                                                                                                          • Fiber-optic work will take place at manholes on Milestone Street, and Axle Way inside the ERC site on Tuesday, June 3 from 5 p.m. to midnight
                                                                                                                                                                                          Building Mock-Ups
                                                                                                                                                                                          • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                          Eversource Conduit Project
                                                                                                                                                                                          • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                          General
                                                                                                                                                                                          • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                          • All projects will be working on Thursday, May 29 with limited deliveries during Harvard’s Commencement.
                                                                                                                                                                                          • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                            • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                            • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                            • A drone is scheduled to fly on Thursday, June 5 at 3 p.m
                                                                                                                                                                                          North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                          The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                          • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                          • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                          • Structure and box culvert activity continues. A crane on site will be needed for box culvert activity.
                                                                                                                                                                                          • Backfilling operations intermittently occur.
                                                                                                                                                                                          • Truck traffic will increase to load in material.
                                                                                                                                                                                          • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                          • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                          92 Seattle Street
                                                                                                                                                                                          • Project has received a COO.
                                                                                                                                                                                          • Replacing and repowering roof equipment is underway.
                                                                                                                                                                                          • Knee wall mock-up for the west wall repair is complete. Waiting for review to proceed with the work.  
                                                                                                                                                                                          • All work is targeting completion in four weeks.
                                                                                                                                                                                          175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                          • Window installation using boom lifts continues. Exterior wall framing continues.
                                                                                                                                                                                          • Window installation using boom lifts continues. Exterior wall framing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and the tower. More swing staging is coming in at the north tower. Brick work is in full swing and brick deliveries have increased. Mechanical, electrical, and plumbing trades continue to work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation in the south tower continues. Drywall work is scheduled to begin in June. A crane is arriving in the first week of June to support work on the north tower. Roof work continues on the 10th floor of the mid-rise building. An additional crane will be on site to load the 14th story roof later in June.
                                                                                                                                                                                          • During the week of June 2, excluding Sunday, the contractor will need to close South Campus Drive between 7 a.m. to 5 p.m. to accommodate lift and crane access. South Campus Drive will be open to traffic each day after 5 p.m.  
                                                                                                                                                                                          • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                          • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                          • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                          • On the new American Repertory Theater (ART) work site, mass timber installation continues for the next several months. Currently two cranes are operating. Daily wood deliveries continue. Mass Timber work continues on an adjacent section of the building closest to South Campus Drive through the month of May. Masonry work is underway. Additional trades are on site next week for block work, roof level parapet work, and slab on deck pours. This work is in preparation for roofers to begin work on Monday, June 23. Work will be taking place on lower plenum level block walls and roof topping slabs. Mechanical trades will begin work at the end of June.
                                                                                                                                                                                          • Steel detailing work continues ahead of waterproofing. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage.
                                                                                                                                                                                          • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                                                                                          • Work will be taking place at the affiliate housing building on the next two Saturdays, May 31, and June 7, to do some exterior wall sheathing, window installation, and interior framing, mechanical, electrical, and plumbing work. This work is dependent on weather.
                                                                                                                                                                                          • Also at the affiliate housing building, a small roofing crew will be working on Sunday, June 1, on the 10th floor in the center of the building away from the Continuum. This work will produce minimal noise. There won’t be any road closures or deliveries on Sunday, and the hoist and cranes will not be operational. Crew members will access the site through Gate B, adjacent to the Harvard track. Work hours will be 8 a.m. to no later than 4 p.m. Working on a Sunday is a last resort made necessary due to the series of rainy Saturdays experienced this spring. The project team appreciates the community’s understanding.
                                                                                                                                                                                          • A crew at the ART project will be working on mass timber on Saturday, May 31. No other work is planned this weekend for this project.
                                                                                                                                                                                          • As a component of Harvard’s public benefit commitments with the City of Boston, Harvard University Housing is working with Cambridge Landscaping to replace approximately 60 dead trees throughout Smith Field, adjacent to the new affiliate housing building. Several of those trees abut South Campus Drive adjacent to the Continuum. The work began on Tuesday, May 27, and will take several weeks to complete. The project scope also includes installation of a new accessible ramp between South Campus Drive and the park, which is in the approvals process.
                                                                                                                                                                                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                          • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                          210 North Harvard Street
                                                                                                                                                                                          • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                          • The bakery Sofra is open. 
                                                                                                                                                                                          168 Western Ave
                                                                                                                                                                                          • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                          • Mechanical roof work continues and is scheduled to be completed by the end of next week.
                                                                                                                                                                                          • Paving is planned for Tuesday, June 3 within the site fence.
                                                                                                                                                                                          • Storefront work is complete.
                                                                                                                                                                                          • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 

                                                                                                                                                                                          Anthony D'Isidoro

                                                                                                                                                                                          unread,
                                                                                                                                                                                          Jun 7, 2025, 1:09:55 PMJun 7
                                                                                                                                                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                          Harvard Construction Mitigation (Week of June 9, 2025)   

                                                                                                                                                                                          June 6, 2025

                                                                                                                                                                                          Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                          • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                          Enterprise Research Campus
                                                                                                                                                                                          Residential/Hotel
                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                          • On Saturday, June 7, the site will have several activities underway, weather permitting. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the mid-rise hoist infill area. A crane will be operating to the hotel curtainwall former hoist area. Paver work will be taking place on the east and south decks.  Elevator and miscellaneous interior work in all three buildings.
                                                                                                                                                                                          • On Sunday, June 8, six workers will be inside the hotel and high-rise building elevator shafts. Fifteen drywallers will be working at the elevator lobbies. Six plumbers and electricians will be working inside the buildings. Installation of pavers on the east and south decks will be done by a dozen workers. The former hoist area will be infilled with curtainwall by a dozen workers using a crane.
                                                                                                                                                                                          Weekday/night Activities 
                                                                                                                                                                                            • Crews are scheduled to work at the midrise off Trotting Avenue, on the first and second floor exterior façade from 3 to 11 p.m. Boom and scissor lifts and light towers pointed at the building will be operational.
                                                                                                                                                                                            • Night crews will be pre-clearing at the loading dock using an excavator and truck from 9 p.m. to 5 a.m.
                                                                                                                                                                                            • Eversource will working in Western and Trotting manholes on Monday and Wednesday to complete on site permanent power connections.
                                                                                                                                                                                            • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                                                            • At the midrise and high rise, the hoists have been removed, and infill work is underway.
                                                                                                                                                                                            • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                                                                                                                            • hotel.
                                                                                                                                                                                            • A crane is operating for infilling the hotel curtainwall former hoist area.
                                                                                                                                                                                            • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                            • Elevators are being installed.
                                                                                                                                                                                            • Other concrete operations continue.
                                                                                                                                                                                            • Some roofing activities continue.
                                                                                                                                                                                            • MEP work is ongoing.
                                                                                                                                                                                            • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                            • Flooring and painting is underway.
                                                                                                                                                                                            Laboratory and Office Buildings
                                                                                                                                                                                            Weekend Activities
                                                                                                                                                                                            • On Saturday, June 7, exterior work on the first floor and roofing activity, weather permitting, will be underway. Interior drywall, elevator install and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                                                            • On Sunday, June 8, six workers will be in the elevator shafts and 12 to 15 workers may be doing roofing activity.
                                                                                                                                                                                            Weekday Activities
                                                                                                                                                                                              • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                              • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                              • Roof activities are underway.
                                                                                                                                                                                              • Elevators are being installed and inspected.
                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                              • Mechanical penthouse activities continue.
                                                                                                                                                                                              • Masonry work continues.
                                                                                                                                                                                              • Excavation for irrigation/landscaping work will continue on the east side of the buildings.
                                                                                                                                                                                              • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                              Treehouse Conference Center
                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                              • Work includes roofing install (weather permitting) with a crane operating, façade work, flooring, dry-wall and miscellaneous interior work on Saturday, June 7. A dry-wall delivery will take place in the morning.
                                                                                                                                                                                              • On Sunday, June 8, approximately six roofers will be working with a couple of laborers cleaning up the site. On the interior, three electricians will be working, and eight carpenters will be installing dry wall. 
                                                                                                                                                                                              Weekday/night Activities 
                                                                                                                                                                                                • A small crew is scheduled to work installing facade clips and caulking from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                • Cranes are assisting with roof and terrace activities.
                                                                                                                                                                                                • Skylight framing is underway on the roof.
                                                                                                                                                                                                • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                • Foundation work is underway for the north side bridge area.
                                                                                                                                                                                                • Duct bank work continues.
                                                                                                                                                                                                • Framing and drywall continue.
                                                                                                                                                                                                • Elevator work continues.
                                                                                                                                                                                                • MEP activities are ongoing.
                                                                                                                                                                                                • Flooring work continues.
                                                                                                                                                                                                • Small concrete placements will take place.
                                                                                                                                                                                                • Bathroom work has begun.
                                                                                                                                                                                                  Evening Thermal Work
                                                                                                                                                                                                  • Underground water pipe investigative, repair and testing work will continue on weeknights in two areas near the Treehouse for approximately two weeks from 4 p.m. until midnight.
                                                                                                                                                                                                  Greenway
                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                  • On Saturday, June 7 a crew will be working on the shared use path.
                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                    • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                                                    • Trees continue to be planted.
                                                                                                                                                                                                    • Prep and utility work is underway for water features.
                                                                                                                                                                                                    • Outcropping (boulder)install continues.
                                                                                                                                                                                                    Streetscape
                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                    • On Saturday, June 7, road curbing installation will be underway along Trotting Avenue. All work will be contained within the site.
                                                                                                                                                                                                    Weekday/night Activities
                                                                                                                                                                                                    • Work and backfilling in the trench will take place on Trotting Avenue near the buildings.
                                                                                                                                                                                                    • Night crews will be pre-clearing at the residential/hotel loading dock on Trotting Avenue using an excavator and truck from 9 p.m. to 5 a.m.
                                                                                                                                                                                                    Building Mock-Ups
                                                                                                                                                                                                    • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                    Eversource Conduit Project
                                                                                                                                                                                                    • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                    Fiberoptic Manhole Work
                                                                                                                                                                                                    • Comcast will be continuing daytime fiber-optic work at manholes inside the ERC site.
                                                                                                                                                                                                    General
                                                                                                                                                                                                    • The project’s work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                    • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                      • licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                      • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                      • A drone is scheduled to fly on Thursday, June 12 at 3 p.m.
                                                                                                                                                                                                    North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                    The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                    • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                    • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                    • Structure and box culvert activity continues. A crane on site will be needed for box culvert activity.
                                                                                                                                                                                                    • Backfilling operations intermittently occur.
                                                                                                                                                                                                    • Truck traffic will increase to load in material.
                                                                                                                                                                                                    • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                    • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                    92 Seattle Street
                                                                                                                                                                                                    • Project has received a COO.
                                                                                                                                                                                                    • Some roof activity may be needed after utility coordination.
                                                                                                                                                                                                    • Review of the knee wall mock-up for the west wall repair is underway with a schedule to follow.
                                                                                                                                                                                                    • All work is targeting completion in four weeks.
                                                                                                                                                                                                    175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                                    The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                                    • Window installation using boom lifts continues. Exterior wall framing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and the tower. More swing staging is coming in at the north tower. Brick work is in full swing and brick deliveries have increased. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation in the south tower continues. Drywall work is scheduled to begin in June. A crane is arriving in the first week of June to support work on the north tower. Roof work continues on the 10th floor of the mid-rise building. An additional crane will be on site to load the 14th story roof later in June. Tenant fit outs on floors 3-5 are progressing.
                                                                                                                                                                                                    • During the week of June 9, excluding Sunday the contractor will need to close South Campus Drive between 7 a.m. to 5 p.m. to accommodate lift and crane access. South Campus Drive will be open to traffic each day after 5 p.m.  
                                                                                                                                                                                                    • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                    • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                    • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                    • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                    • On the new American Repertory Theater (ART) work site, mass timber installation continues for the next several months. Currently two cranes are operating. Daily wood deliveries continue. Mass Timber work continues on an adjacent section of the building closest to South Campus Drive through June 11. Mass Timber installation has started on the front section of the building closest to North Harvard Street. Work Will shift to include the mid-section of the building by mid-July. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. Masonry work is underway. This work is in preparation for roofers to begin work on Monday, June 23. Mechanical trades will begin work at the end of June.
                                                                                                                                                                                                    • Steel detailing work continues ahead of waterproofing. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams and flooring have been installed in the first sector near the west stage.
                                                                                                                                                                                                    • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                                                                                                    • Work will be taking place at the affiliate housing building on the next two Saturdays, June 7, and June 14, to do some exterior wall sheathing, window installation, and interior framing, mechanical, electrical, and plumbing work. This work is dependent on weather.
                                                                                                                                                                                                    • A crew at the ART project will be working on mass timber on Saturday, June 7. No other work is planned this weekend for this project.
                                                                                                                                                                                                    • Also at the affiliate housing building, due recent delays brought on by repeated inclement weather, a small roofing crew may need to work on Sunday, June 15, on the 10th floor in the center of the building away from the Continuum. This work will produce minimal noise. There wouldn’t be any road closures or deliveries on Sunday, and the hoist and cranes would not be operational. Crew members would access the site through Gate B, adjacent to the Harvard track. Work hours will be 8 a.m. to no later than 4 p.m. Working on a Sunday is a last resort made necessary due to the series of rainy Saturdays experienced this spring. The project team appreciates the community’s understanding.
                                                                                                                                                                                                    • As a component of Harvard’s public benefit commitments with the City of Boston, Harvard University Housing is working with Cambridge Landscaping to replace approximately 60 dead trees throughout Smith Field, adjacent to the new affiliate housing building. Several of those trees abut South Campus Drive adjacent to the Continuum. The work began on Tuesday, May 27, and will take several weeks to complete. The project scope also includes installation of a new accessible ramp between South Campus Drive and the park, which is in the approvals process.
                                                                                                                                                                                                    • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                    • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                    210 North Harvard Street
                                                                                                                                                                                                    • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                    • The bakery Sofra is open. 
                                                                                                                                                                                                    168 Western Ave
                                                                                                                                                                                                    • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                    • Mechanical roof work continues and is scheduled to be completed by the end of next week.
                                                                                                                                                                                                    • Paving is complete.
                                                                                                                                                                                                    • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 

                                                                                                                                                                                                    Anthony D'Isidoro

                                                                                                                                                                                                    unread,
                                                                                                                                                                                                    Jun 14, 2025, 10:52:13 AMJun 14
                                                                                                                                                                                                    to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                    Harvard Construction Mitigation (Week of June 16, 2025)   

                                                                                                                                                                                                    June 13, 2025

                                                                                                                                                                                                    Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                    • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                    Enterprise Research Campus
                                                                                                                                                                                                    Residential/Hotel
                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                    • On Saturday, June 14, the site will have several activities underway, weather permitting. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the mid-rise hoist infill area. Paver work will be taking place on the east and south decks.  Elevator and miscellaneous interior work in all three buildings.
                                                                                                                                                                                                    • On Sunday, June 15, six workers will be inside the hotel and high-rise building elevator shafts.  Six electricians will be working inside the hotel. Another six workers will be cleaning inside the midrise.
                                                                                                                                                                                                    Weekday/night Activities
                                                                                                                                                                                                      • Crews are scheduled to work at the midrise off Trotting Avenue, on the first and second floor exterior façade from 3 to 11 p.m. Boom and scissor lifts and light towers pointed at the building will be operational.
                                                                                                                                                                                                      • Night crews will be installing conduit and backfilling at the loading dock using an excavator and truck from 9 p.m. to 5 a.m.
                                                                                                                                                                                                      • Eversource will be finishing permanent power.
                                                                                                                                                                                                      • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                                                                      • At the midrise and high rise, the hoists have been removed and infill work is underway.
                                                                                                                                                                                                      • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the
                                                                                                                                                                                                      • hotel.
                                                                                                                                                                                                      • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                                      • Elevators are being installed.
                                                                                                                                                                                                      • Other concrete operations continue.
                                                                                                                                                                                                      • Some roofing activities continue.
                                                                                                                                                                                                      • MEP work is ongoing.
                                                                                                                                                                                                      • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                                      • Flooring and painting is underway.
                                                                                                                                                                                                        Laboratory and Office Buildings.
                                                                                                                                                                                                        • On Saturday, June 14, exterior work on the first floor and roofing activity, weather permitting, will be underway. Interior drywall, elevator install and MEP work in the penthouse as well as general clean-up activities will occur. A roofing delivery and drywall delivery is expected.
                                                                                                                                                                                                        • No work is planned for Sunday, June 15.
                                                                                                                                                                                                        Weekday Activities
                                                                                                                                                                                                          • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                          • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                          • Smaller concrete operations continue.
                                                                                                                                                                                                          • Roof activities are underway.
                                                                                                                                                                                                          • Elevators are being installed and inspected.
                                                                                                                                                                                                          • MEP work is ongoing.
                                                                                                                                                                                                          • Mechanical penthouse activities continue.
                                                                                                                                                                                                          • Masonry work continues.
                                                                                                                                                                                                          • Structural soil backfill low voltage and irrigation install will take place on the east side of the buildings.
                                                                                                                                                                                                          • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                          Treehouse Conference Center
                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                          • Work includes roofing install (weather permitting), façade work, flooring, drywall and miscellaneous interior work including MEP work on Saturday, June 14. A drywall delivery will take place in the morning.
                                                                                                                                                                                                          • On Sunday, June 15, approximately six roofers will be working with a few laborers cleaning up the site. On the interior, four electricians will be working, and eight carpenters will be installing drywall.
                                                                                                                                                                                                          Weekday/night Activities
                                                                                                                                                                                                          • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                          • A crane is expected for a duct work delivery at the end of the week.
                                                                                                                                                                                                          • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                          • Duct bank excavation and install is occurring.
                                                                                                                                                                                                          • Framing and drywall continue.
                                                                                                                                                                                                          • Elevator work is underway.
                                                                                                                                                                                                          • MEP activities are ongoing.
                                                                                                                                                                                                          • Flooring work continues.
                                                                                                                                                                                                          • Small concrete placements will take place.
                                                                                                                                                                                                          • Bathroom work continues.
                                                                                                                                                                                                          Evening Thermal Work
                                                                                                                                                                                                          • Underground water pipe backfilling work will continue on weeknights in two areas near the Treehouse and one between the National Resilience Drive and Milestone Street from 4 p.m. until midnight.
                                                                                                                                                                                                          Greenway
                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                          • On Saturday, June 14 a crew will be planting trees.
                                                                                                                                                                                                          Weekday Activities
                                                                                                                                                                                                          • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                                                          • Trees continue to be planted.
                                                                                                                                                                                                          • Prep and utility work is underway for water features.
                                                                                                                                                                                                          • Outcropping (boulder)install continues.
                                                                                                                                                                                                          Streetscape
                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                          • On Saturday, June 14, road curbing and paver installation will be underway along Trotting Avenue. All work will be contained within the site.
                                                                                                                                                                                                          Weekday/night Activities
                                                                                                                                                                                                          • Daytime work includes curbing, paver install on Trotting Avenue near the buildings.
                                                                                                                                                                                                          • Night crews will be installing conduit and structural soil at the residential/hotel loading dock on Trotting Avenue using an excavator and truck from 9 p.m. to 5 a.m.
                                                                                                                                                                                                          Building Mock-Ups
                                                                                                                                                                                                          • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                          Eversource Conduit Project
                                                                                                                                                                                                          • Eversource electrical cabling will be taking place in the future along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                          Fiberoptic Manhole Work
                                                                                                                                                                                                          • Comcast will be continuing daytime fiber-optic work at manholes inside the ERC site.
                                                                                                                                                                                                          General
                                                                                                                                                                                                          • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.  All projects will be permitted to work on Juneteenth, Thursday, June 19.
                                                                                                                                                                                                          • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                            • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                            • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                            • A drone is scheduled to fly on Fridays, June 13 and 20, at 3 p.m.
                                                                                                                                                                                                          North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                          The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                          • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                          • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                          • Slide rail deliveries are expected to prepare for box culvert activity.
                                                                                                                                                                                                          • Structure and box culvert activity continues. A crane on site will be needed for box culvert activity.
                                                                                                                                                                                                          • Backfilling operations intermittently occur.
                                                                                                                                                                                                          • Truck traffic will increase to load in material.
                                                                                                                                                                                                          • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                          • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                          92 Seattle Street
                                                                                                                                                                                                          • Project has received a COO.
                                                                                                                                                                                                          • Some roof activity may be needed after utility coordination.
                                                                                                                                                                                                          • Review of the knee wall mock-up for the west wall repair is underway with a schedule to follow.
                                                                                                                                                                                                          • All work is targeting completion in four weeks.
                                                                                                                                                                                                          175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                                          The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                                          • Exterior wall framing continues. Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are on the mid-rise and the tower. More swing staging is coming to support work on the 14th level. Brick work is ongoing on the east and south face on the building and brick deliveries have increased. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation in the south tower continues. Drywall work has started. A crane is on site supporting work on the north tower. Roof work is ongoing on the 14th story penthouse roofs. A second crane is in use on the west side to feed the masonry work. This crane will be removed from the site in approximately three to four weeks. There is one month of work left for window sheathing and then swing staging will be back to install the roof on the 14th story. Tenant fit outs on floors 3-5 are progressing. Small utilities will start soon. Off-hour sheet rock deliveries will start at 3 p.m. and will go to 6 p.m. three times per week.
                                                                                                                                                                                                          • During the week of June 16, excluding Saturday and Sunday, the contractor will need to close South Campus Drive between 7 a.m. to 5 p.m. to accommodate crane access and a transformer delivery. South Campus Drive will be open to traffic each day after 5 p.m.
                                                                                                                                                                                                          • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                          • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                          • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                          • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                          • On the new American Repertory Theater (ART) work site, mass timber installation continues for the next several months. Currently three cranes are operating. Daily wood deliveries continue. Mass Timber work continues, and installation has started on the front section of the building closest to North Harvard Street along with columns, beams, and wall panels. Mass timber is wrapping up in the section of the building closest to McCurdy Track, with wall panels and chimney installation through Saturday. Work will shift to include the mid-section of the building by mid-July. Masonry work is underway. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. This work is in preparation for roofers to begin work at the end of the month. Work will be taking place on lower plenum level block walls and roof topping slabs. Mechanical trades will begin work at the end of June.
                                                                                                                                                                                                          • Steel detailing work continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams, and flooring have been installed in two sections of the new building.
                                                                                                                                                                                                          • Periodic adjustments will take place on the ART building mock-up to review design and constructability across North Harvard Street.
                                                                                                                                                                                                          • Work will be taking place at the affiliate housing building on the next two Saturdays, June 14 and June 21, to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on weather.
                                                                                                                                                                                                          • Both job sites have obtained permits to work on the Juneteenth holiday on Thursday, June 19.
                                                                                                                                                                                                          • A crew at the ART project will be working on mass timber on Saturday, June 14.
                                                                                                                                                                                                          • Also at the affiliate housing building, due to recent delays brought on by repeated inclement weather, a small roofing crew may need to work on Sunday, June 22, in the center of the building away from the Continuum. This work will produce minimal noise. There will not be any road closures or deliveries on Sunday, and the hoist and cranes will not be operational. Crew members would access the site through Gate B, adjacent to the Harvard track. Work hours will be 8 a.m. to no later than 4 p.m. Working on a Sunday is a last resort made necessary due to the series of rainy Saturdays experienced this spring. The project team appreciates the community’s understanding.
                                                                                                                                                                                                          • As a component of Harvard’s public benefit commitments with the City of Boston, Harvard University Housing is working with Cambridge Landscaping to replace approximately 60 dead trees throughout Smith Field, adjacent to the new affiliate housing building. Several of those trees abut South Campus Drive adjacent to the Continuum. The work began on Tuesday, May 27, and will take several weeks to complete. The project scope also includes installation of a new accessible ramp between South Campus Drive and the park, which is in the approvals process.
                                                                                                                                                                                                          • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                          • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                          210 North Harvard Street
                                                                                                                                                                                                          • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                          • The bakery Sofra is open. 
                                                                                                                                                                                                          168 Western Ave
                                                                                                                                                                                                          • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                          • Minor roof activity is finishing up.
                                                                                                                                                                                                          • Punch list and inspections are underway.
                                                                                                                                                                                                          • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western will be relocated on June 20. 
                                                                                                                                                                                                          • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 

                                                                                                                                                                                                          Anthony D'Isidoro

                                                                                                                                                                                                          unread,
                                                                                                                                                                                                          Jun 21, 2025, 9:05:01 AMJun 21
                                                                                                                                                                                                          to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                          Harvard Construction Mitigation (Week of June 23, 2025)   

                                                                                                                                                                                                          June 20, 2025

                                                                                                                                                                                                          Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                          • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                          Enterprise Research Campus
                                                                                                                                                                                                          Residential/Hotel
                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                          • On Saturday, June 21, the site will have several activities underway. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the mid-rise hoist infill area. Paver work will be taking place on the east and south decks.  Elevator and miscellaneous interior work in all three buildings.
                                                                                                                                                                                                          • On Sunday, June 22, six workers will be inside the hotel and high-rise building elevator shafts.  Four electricians will be working inside the hotel with another four working in the mid-rise and high-rise building. Another six workers will be working on level 1. Six workers will be outside installing pavers. Twenty workers may be working on the high-rise façade installing green panels.
                                                                                                                                                                                                           Weekday/night Activities
                                                                                                                                                                                                          • Crews are scheduled to work in the evenings at the highrise, exterior façade from 3 to 11 p.m. on swing staging with portable light towers pointed at the building. Some minor panel finish work may take place at the mid rise.
                                                                                                                                                                                                          • On site loading dock evening activity is from 3 to 11 p.m.
                                                                                                                                                                                                          • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                                                                          • At the high rise, the hoist has been removed and infill work is underway.
                                                                                                                                                                                                          • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                          • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                                          • Elevators are being installed.
                                                                                                                                                                                                          • Other concrete operations continue.
                                                                                                                                                                                                          • Some roofing activities continue.
                                                                                                                                                                                                          • MEP work is ongoing.
                                                                                                                                                                                                          • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                                          • Flooring and painting is underway.
                                                                                                                                                                                                            Laboratory and Office Buildings
                                                                                                                                                                                                            Weekend Activities
                                                                                                                                                                                                            • On Saturday, June 21, exterior work on the first floor and roofing activity, weather permitting, will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                                                                            • No work is planned for Sunday, June 22.
                                                                                                                                                                                                            Weekday Activities
                                                                                                                                                                                                            • A crane will be on site starting Monday, June 23 for removal of the hoist, followed by dismantle of the loading dock.
                                                                                                                                                                                                            • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                            • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                            • Smaller concrete operations continue.
                                                                                                                                                                                                            • Roof activities are underway.
                                                                                                                                                                                                            • Elevators are being installed and inspected.
                                                                                                                                                                                                            • MEP work is ongoing.
                                                                                                                                                                                                            • Mechanical penthouse activities continue.
                                                                                                                                                                                                            • Masonry work continues.
                                                                                                                                                                                                            • Structural soil backfill, low voltage, concrete pad and granite curb install will take place on the east side of the buildings.
                                                                                                                                                                                                            • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                            Treehouse Conference Center
                                                                                                                                                                                                            Weekend Activities
                                                                                                                                                                                                            • Work includes underground piping to the cistern water tank on the west side of the site, air handler connections of the roof, flooring, drywall, elevator and miscellaneous interior work including MEP activity on Saturday, June 21.
                                                                                                                                                                                                            • On Sunday, June 22, four electricians will be connecting air handlers on the roof. 
                                                                                                                                                                                                            Weekday/night Activities
                                                                                                                                                                                                              • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                              • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                              • Duct bank excavation and install is occurring.
                                                                                                                                                                                                              • Framing and drywall continue.
                                                                                                                                                                                                              • Elevator work is underway.
                                                                                                                                                                                                              • MEP activities are ongoing.
                                                                                                                                                                                                              • Flooring work continues.
                                                                                                                                                                                                              • Small concrete placements will take place.
                                                                                                                                                                                                              • Bathroom work continues.
                                                                                                                                                                                                              • Painting will begin. 
                                                                                                                                                                                                              Evening Thermal Work
                                                                                                                                                                                                              • Underground water pipe backfilling work will continue on weeknights in two areas near the Treehouse and one between the National Resilience Drive and Milestone Street from 4 p.m. until midnight.
                                                                                                                                                                                                              Greenway
                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                              • On Saturday, June 21 a crew will be prepping for outcrop (boulder) feature.
                                                                                                                                                                                                              Weekday Activities
                                                                                                                                                                                                              • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                                                              • Trees continue to be planted.
                                                                                                                                                                                                              • Prep and utility work is underway for water features.
                                                                                                                                                                                                              • Outcropping (boulder)install continues.
                                                                                                                                                                                                              Streetscape
                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                              • On Saturday, June 21, road curbing and paver bases will be underway. All work will be contained within the site.
                                                                                                                                                                                                              Weekday/night Activities
                                                                                                                                                                                                              • Daytime work includes sidewalks, curbing, paver install near the buildings.
                                                                                                                                                                                                              • Evening crews will be prepping for the bike lane, curbing, railings, trash receptacles from 3 p.m. to 10 p.m. All work will be contained within the site.
                                                                                                                                                                                                              Building Mock-Ups
                                                                                                                                                                                                                • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                • A pedestrian pathway from the Hague Street lot to the street will be installed before the July 4 holiday.
                                                                                                                                                                                                                Eversource Conduit Project
                                                                                                                                                                                                                • Eversource electrical cabling continues along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                General
                                                                                                                                                                                                                  • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                  • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                    • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                    • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                    • A drone is scheduled to fly on Thursday, June 26, at 3 p.m.
                                                                                                                                                                                                                  North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                  The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                  • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                  • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                  • Slide rail deliveries are expected to prepare for box culvert activity.
                                                                                                                                                                                                                  • Structure and box culvert activity continues. A crane on site will be needed for box culvert activity.
                                                                                                                                                                                                                  • Backfilling operations intermittently occur.
                                                                                                                                                                                                                  • Truck traffic will increase to load in material.
                                                                                                                                                                                                                  • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                                  • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                  92 Seattle Street 
                                                                                                                                                                                                                  • Project has received a COO.
                                                                                                                                                                                                                  • Some roof activity may be needed after utility coordination.
                                                                                                                                                                                                                  • Review of the knee wall mock-up for the west wall repair is underway with a schedule to follow.
                                                                                                                                                                                                                  • All work is targeting completion in four weeks.
                                                                                                                                                                                                                  175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                                                  The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                                                                                                                                                  • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are in place around the job site. Brick work is ongoing on the courtyard and west side of the building and brick deliveries have increased. An additional crane will arrive in July on the west side of the building to support brick installation. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation has started in the north tower. Drywall work continues. A crane is on site supporting work on the north tower. There is one month of work left for window sheathing and then swing staging will be back to install the roof on the 14th story. Small utilities will start soon. Off-hour sheet rock deliveries will start at 3 p.m. and will go to 6 p.m. three times per week. Telecom duct bank installation will begin early this week. Window installation is ongoing.
                                                                                                                                                                                                                  • During the week of June 23, excluding Saturday and Sunday, the contractor will need to close South Campus Drive periodically between 7:00 a.m. to 5:00 p.m. to accommodate crane access and a transformer delivery. South Campus Drive will be open to traffic each day after 5:00 p.m.
                                                                                                                                                                                                                  • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                  • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                  • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                  • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                  • On the new American Repertory Theater (ART) work site, mass timber installation continues for the next several months. One crane has been removed from the site. Daily wood deliveries continue. Mass Timber work continues, and installation has started on the front section of the building closest to North Harvard Street along with columns, beams, and wall panels. Mass timber is wrapping up Stairs are being installed in the section of the building closest to McCurdy Track and a concrete roof slab will be poured this week with a pump truck within the site fence. Work will shift to include the mid-section of the building by mid-July. Masonry work is underway. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. This work is in preparation for roofers to begin work at the end of the month. Mechanical systems layout is underway and trades will begin work at the end of June.
                                                                                                                                                                                                                  • Steel detailing work continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams, and flooring have been installed in two sections of the new building.
                                                                                                                                                                                                                  • Periodic work will take place on the ART building mock-up to review design and constructability across North Harvard Street. Steel will be on site June 30, and a crane will be in the area along with a steel trailer.
                                                                                                                                                                                                                  • Work will be taking place at the affiliate housing building on the next two Saturdays, June 21 and June 28, to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on weather.
                                                                                                                                                                                                                  • A crew at the ART project will be working on mass timber on Saturday, June 21.
                                                                                                                                                                                                                  • As a component of Harvard’s public benefit commitments with the City of Boston, Harvard University Housing is working with Cambridge Landscaping to replace approximately 60 dead trees throughout Smith Field, adjacent to the new affiliate housing building. Several of those trees abut South Campus Drive adjacent to the Continuum. The work began on Tuesday, May 27, and will take several weeks to complete. The project scope also includes installation of a new accessible ramp between South Campus Drive and the park, which is in the approvals process.
                                                                                                                                                                                                                  • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                                                                                                  • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                  210 North Harvard Street
                                                                                                                                                                                                                  • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                  • The bakery Sofra is open. 
                                                                                                                                                                                                                  168 Western Ave
                                                                                                                                                                                                                  • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                  • Minor roof activity is finishing up.
                                                                                                                                                                                                                  • Punch list and inspections are underway.
                                                                                                                                                                                                                  • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western will be relocated on June 20. 
                                                                                                                                                                                                                  • The Swiss Bakers bakery operation is temporarily relocated to 9 Travis Street while their space gets renovated. 

                                                                                                                                                                                                                  Anthony D'Isidoro

                                                                                                                                                                                                                  unread,
                                                                                                                                                                                                                  Jun 28, 2025, 10:18:42 AMJun 28
                                                                                                                                                                                                                  to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                  Harvard Construction Mitigation (Week of June 30, 2025)   

                                                                                                                                                                                                                  June 27, 2025

                                                                                                                                                                                                                  Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                  • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                  Enterprise Research Campus
                                                                                                                                                                                                                  Residential/Hotel
                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                  • On Saturday, June 28, the site will have several activities underway. Exterior green panel installation and activity will take place on the midrise and high-rise residential buildings with several boom lifts operating including the mid-rise hoist infill area. Paver work will be taking place on the east and south decks. Elevator and miscellaneous interior work is ongoing in all three buildings.
                                                                                                                                                                                                                  • On Sunday, June 29, eight workers will be inside the hotel and high-rise building elevator shafts. Twelve workers will be onsite to conduct cleaning operations in the high-rise and mid-rise buildings. Twelve workers will be on site for drywall exterior ground floor facade activities on the southwest corner, boom lift, studs and boards at main entrance of high-rise. Eight workers will be conducting interior taping. It is possible that workers will be on swing staging on the high-rise of the south and east sides of the building. Three workers will begin removal of the mast climbers on the south side of the high-rise.
                                                                                                                                                                                                                  Weekday/Night Activities
                                                                                                                                                                                                                  • Fire alarm testing will begin Friday at 9 a.m. and may continue into Saturday morning.
                                                                                                                                                                                                                  • Crews are scheduled to work in the evenings at the high-rise, exterior façade from 3 to 11 p.m. on swing staging with portable light towers pointed at the building. Some minor panel finish work may take place at the mid rise.
                                                                                                                                                                                                                  • On site loading dock evening activity is from 3 to 11 p.m.
                                                                                                                                                                                                                  • Podium deck activities will occur from 11 p.m. – 7 a.m., including this Friday night into Saturday morning.
                                                                                                                                                                                                                  • Exterior wall sheathing, panel clips and green exterior panels are being installed on the residential buildings.
                                                                                                                                                                                                                  • At the high rise, the hoist has been removed and infill work is underway.
                                                                                                                                                                                                                  • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                  • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                                                  • Elevators are being installed.
                                                                                                                                                                                                                  • Other concrete operations continue.
                                                                                                                                                                                                                  • Some roofing activities continue.
                                                                                                                                                                                                                  • MEP work is ongoing.
                                                                                                                                                                                                                  • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                                                  • Flooring and painting is underway.
                                                                                                                                                                                                                  Laboratory and Office Buildings
                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                  • On Saturday, June 28, exterior work on the first floor and roofing activity, weather permitting, will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as general clean-up activities will occur. Demolition of the loading dock will take place.
                                                                                                                                                                                                                  • No work is planned for Sunday, June 29.
                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                  • A crane is on site for removal of the hoist, followed by dismantle of the loading dock.
                                                                                                                                                                                                                  • The loading dock will begin to be demolished.
                                                                                                                                                                                                                  • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                  • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                  • Smaller concrete operations continue.
                                                                                                                                                                                                                  • Roof activities are underway.
                                                                                                                                                                                                                  • Elevators are being installed and inspected.
                                                                                                                                                                                                                  • MEP work is ongoing.
                                                                                                                                                                                                                  • Mechanical penthouse activities continue.
                                                                                                                                                                                                                  • Masonry work continues.
                                                                                                                                                                                                                  • Structural soil backfill, low voltage, concrete pad and granite curb install will take place on the east side of the buildings.
                                                                                                                                                                                                                  • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                  Treehouse Conference Center
                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                  • Work includes underground piping to the cistern water tank on the west side of the site, flooring, drywall, elevator and miscellaneous interior work including MEP activity on Saturday, June 28.
                                                                                                                                                                                                                  • On Sunday, June 29, eight to ten electricians will be connecting air handlers on the roof.
                                                                                                                                                                                                                  Weekday/Night Activities
                                                                                                                                                                                                                  • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                                  • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                                  • Duct bank excavation and install is occurring.
                                                                                                                                                                                                                  • Framing and drywall continue.
                                                                                                                                                                                                                  • Elevator work is underway.
                                                                                                                                                                                                                  • MEP activities are ongoing.
                                                                                                                                                                                                                  • Flooring work continues.
                                                                                                                                                                                                                  • Small concrete placements will take place.
                                                                                                                                                                                                                  • Bathroom work continues.
                                                                                                                                                                                                                  • Painting will begin.
                                                                                                                                                                                                                  Evening Thermal Work
                                                                                                                                                                                                                  • Underground water pipe backfilling work will continue on weeknights in two areas near the Treehouse and one between the National Resilience Drive and Milestone Street from 4 p.m. until midnight.
                                                                                                                                                                                                                  Greenway
                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                  • On Saturday, June 28 a crew will be prepping for outcrop (boulder) feature deliveries.
                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                    • Landscaping crews continue prepping for hardscape and tree planting.
                                                                                                                                                                                                                    • Trees continue to be planted.
                                                                                                                                                                                                                    • Prep and utility work is underway for water features.
                                                                                                                                                                                                                    • Outcropping (boulder) install continues.
                                                                                                                                                                                                                    Streetscape
                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                    • On Saturday, June 28, the crews will be on Trotting Ave. installing gravel for curbing and sidewalks, as well as loading dock work.
                                                                                                                                                                                                                    Weekday/Night Activities
                                                                                                                                                                                                                    • Daytime work includes sidewalks, curbing, paver install near the buildings. Piping will begin to be installed along Milestone St.
                                                                                                                                                                                                                    The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                                                    • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are in place around the job site. Brick work is ongoing on the courtyard and west side of the building and brick deliveries have increased. An additional crane will arrive in July on the west side of the building to support brick installation. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation is ongoing in the north tower. Drywall work continues. A crane is on site supporting work on the north tower. There is one month of work left for window sheathing and then swing staging will be back to install the roof on the 14th story. Small utilities will start soon. Off-hour sheet rock deliveries will start at 3 p.m. and will go to 6 p.m. three times per week. Telecom duct bank installation has started. Window installation is ongoing. Multiple masonry crews will soon be working on all sides of the building,
                                                                                                                                                                                                                    • Next week, the week of June 30, excluding Saturday, Sunday, and the 4th of July, the contractor will need to close South Campus Drive periodically between 7 a.m. to 5 p.m. South Campus Drive will be open to traffic each day after 5 p.m.
                                                                                                                                                                                                                    • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                    • As always, when South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                    • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                    • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                    • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Installation continues on the front section of the building closest to North Harvard Street along with columns, beams, and wall panels. Stairs are being installed in the section of the building closest to McCurdy Track. Work will shift to include the mid-section of the building by mid-July. Masonry work is underway. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. Mechanical equipment will be on site starting on Monday, June 30, after the first roof section is weather tight. Roofing work on west stage fly tower started last week.
                                                                                                                                                                                                                    • Steel detailing continues. A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, trusses, stairs, wall panels, beams, and flooring have been installed in two sections of the new building.
                                                                                                                                                                                                                    • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                    • Periodic work will take place on the ART building mock-up to review design and constructability across North Harvard Street. Steel will be on site June 30 and July 1, and a crane will be in the area along with a steel trailer. Detailing will continue through July 11.
                                                                                                                                                                                                                    • Work will be taking place at the affiliate housing building on Saturday, June 28, to do some fireproofing, exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on weather. Ther is no work planned on the affiliate housing site on Saturday, July 5.
                                                                                                                                                                                                                    • A crew at the ART project will be working on mass timber on Saturday, June 28.
                                                                                                                                                                                                                    • Both job sites are closed on Friday, July 4, for the holiday.
                                                                                                                                                                                                                    • As a component of Harvard’s public benefit commitments with the City of Boston, Harvard University Housing is working with Cambridge Landscaping to replace approximately 60 dead trees throughout Smith Field, adjacent to the new affiliate housing building. Several of those trees abut South Campus Drive adjacent to the Continuum. The work began on Tuesday, May 27, and is expected to be finished in about one week. The project scope also includes installation of a new accessible ramp between South Campus Drive and the park, which is in the approvals process.
                                                                                                                                                                                                                    • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                    • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                    210 North Harvard Street
                                                                                                                                                                                                                    • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                    • The bakery Sofra is open. 
                                                                                                                                                                                                                    168 Western Ave
                                                                                                                                                                                                                    • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                    • An air handler replacement is needed on the roof. A crane will be on site to assist with this work.
                                                                                                                                                                                                                    • Punch list and inspections are underway.
                                                                                                                                                                                                                    • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated.

                                                                                                                                                                                                                    Anthony D'Isidoro

                                                                                                                                                                                                                    unread,
                                                                                                                                                                                                                    Jul 9, 2025, 4:21:59 PMJul 9
                                                                                                                                                                                                                    to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                    Harvard Construction Mitigation (Week of July 7, 2025)   

                                                                                                                                                                                                                    July 7, 2025

                                                                                                                                                                                                                    Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                    • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                    Enterprise Research Campus
                                                                                                                                                                                                                    Residential/Hotel

                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                    • On Saturday, July 5, exterior louvers and lighting will be installed at the high-rise residential building with several boom lifts operating. Elevator and miscellaneous interior work is ongoing in all three buildings.
                                                                                                                                                                                                                    • On Sunday, June 6, 12 workers will be inside the midrise and high-rise building elevator shafts. Eight workers will be onsite to conduct cleaning operations in the mid-rise building. Six workers will be in the mid-rise installing tile.
                                                                                                                                                                                                                    Weekday/Night Activities
                                                                                                                                                                                                                    • Preparation is underway for a temporary certificate of occupancy this week in the midrise residential building
                                                                                                                                                                                                                    • Fire standpipe testing will take place on Tuesday 5 a.m. and will result in water flowing into nearby drains at Western Avenue and inside the site.
                                                                                                                                                                                                                    • Crews are scheduled to work in the evenings at the high-rise, exterior façade from 3 to 11 p.m. on swing staging with portable light towers pointed at the building.
                                                                                                                                                                                                                    • Exterior curtainwall installation will take place on the highrise with temporary lighting into the evening activity from 3 to 11 p.m.
                                                                                                                                                                                                                    • Paver activities and possible interior highrise work will occur from 11 p.m. – 7 a.m.
                                                                                                                                                                                                                    • Exterior wall sheathing, panel clips and green exterior panels are being installed on the highrise building.
                                                                                                                                                                                                                    • At the high rise, the hoist has been removed and infill work is underway.
                                                                                                                                                                                                                    • Ground floor work is underway on all three buildings, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                    • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                                                    • Elevator installation activity continues.
                                                                                                                                                                                                                    • Smaller concrete operations continue.
                                                                                                                                                                                                                    • MEP work is ongoing.
                                                                                                                                                                                                                    • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                                                    • Flooring and painting are underway.
                                                                                                                                                                                                                    Laboratory and Office Buildings
                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                    • No work is planned this weekend.
                                                                                                                                                                                                                    Weekday Activities
                                                                                                                                                                                                                    • A crane will be on site to install infill curtainwall where the hoist was located.
                                                                                                                                                                                                                    • The loading dock demolition is finishing.
                                                                                                                                                                                                                    • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                    • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                    • Smaller concrete operations continue.
                                                                                                                                                                                                                    • Roof activities are underway.
                                                                                                                                                                                                                    • Elevators are being installed and inspected.
                                                                                                                                                                                                                    • MEP work is ongoing.
                                                                                                                                                                                                                    • Mechanical penthouse activities continue.
                                                                                                                                                                                                                    • Masonry work continues.
                                                                                                                                                                                                                    • Structural soil backfill, low voltage, concrete pad and granite curb install will take place on the east side of the buildings.
                                                                                                                                                                                                                    • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                    Treehouse Conference Center
                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                    • Work includes flooring, drywall, elevator and miscellaneous interior work including MEP activity on Saturday, July 5.
                                                                                                                                                                                                                    • On Sunday, July 6, twelve roofers will be working.
                                                                                                                                                                                                                    Weekday/Night Activities
                                                                                                                                                                                                                      • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                                      • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                                      • Duct bank excavation and install is occurring.
                                                                                                                                                                                                                      • Framing and drywall continue.
                                                                                                                                                                                                                      • Elevator work is underway.
                                                                                                                                                                                                                      • MEP activities are ongoing.
                                                                                                                                                                                                                      • Flooring work continues.
                                                                                                                                                                                                                      • Small concrete placements will take place.
                                                                                                                                                                                                                      • Bathroom work continues.
                                                                                                                                                                                                                      • Painting is underway.
                                                                                                                                                                                                                      • Connection work
                                                                                                                                                                                                                      Evening Thermal Work
                                                                                                                                                                                                                      • Underground backfilling work and final connection work to the Treehouse may take place from 4 p.m. until midnight.
                                                                                                                                                                                                                      Greenway
                                                                                                                                                                                                                      Weekday Activities
                                                                                                                                                                                                                      • Landscaping crews continue prepping for hardscape.
                                                                                                                                                                                                                      • Light pole bases are being installed.
                                                                                                                                                                                                                      • Prep and utility work is underway for water features.
                                                                                                                                                                                                                      • Outcropping (boulder) install continues.
                                                                                                                                                                                                                        Streetscape
                                                                                                                                                                                                                        Weekday/Night Activities
                                                                                                                                                                                                                        • Daytime work includes sidewalks, curbing, paver install near the buildings. Piping will begin to be installed along Milestone St.
                                                                                                                                                                                                                        • Evening crews will be prepping for the bike lane, curbing, railings, trash receptacles from 3 p.m. to 10 p.m. All work will be contained within the site.
                                                                                                                                                                                                                        Building Mock-Ups
                                                                                                                                                                                                                        • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                        • A pedestrian pathway from the Hague Street lot to the street is being completed.
                                                                                                                                                                                                                        Eversource Conduit Project
                                                                                                                                                                                                                        • Eversource electrical cabling and splicing continues along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                        General
                                                                                                                                                                                                                          • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                          • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                            • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                            • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                            • A drone is scheduled to fly on Thursday, July 10, at 3 p.m.
                                                                                                                                                                                                                          North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                          The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                          • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                          • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                          • Pipe installation continues and slide rail removal will begin.
                                                                                                                                                                                                                          • Backfilling operations intermittently occur.
                                                                                                                                                                                                                          • Truck traffic will increase to load in material.
                                                                                                                                                                                                                          • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                                          • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                            92 Seattle Street 
                                                                                                                                                                                                                              • Project has received a COO.
                                                                                                                                                                                                                              • Eversource will be working at 38 Travis Steet and Rena Path.
                                                                                                                                                                                                                              • Review of the knee wall mock-up for the west wall repair is underway with a schedule to follow.
                                                                                                                                                                                                                              • All work is targeting completion in four weeks.
                                                                                                                                                                                                                              175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                                                              • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are in place around the job site. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. The operating crane will move into a different on-site location on Monday, July 7. An additional crane will arrive on Monday, July 14 to place a generator on the roof. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues. Miscellaneous deliveries to the hoist will continue. Elevator installation is ongoing in the north tower. Drywall work continues and dry wall deliveries take place 3 p.m. to 6 p.m. three times per week and will start every Saturday, beginning July 12, for the rest of the summer as fit outs continue. On the south side of the tower, crews will be erecting scaffolding. Framing and sheathing will be substantially complete by the end of July. Window installation is ongoing. Small utilities inside the site continue. Telecom duct bank installation is ongoing.
                                                                                                                                                                                                                              • Next week, the week of July 7, excluding Saturday, Sunday, the contractor will need to close South Campus Drive periodically between 7 a.m. to 5 p.m. The road will close on Monday, July 7 to relocate the crane. South Campus Drive will be open to traffic each day after 5:00 p.m.
                                                                                                                                                                                                                              • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                              • As always, when South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                              • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                              • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Installation continues on the front section of the building closest to North Harvard Street along with columns, beams, and wall panels. Work will shift to the west to continue the front section by mid-July. Masonry work is underway. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. Mechanical system prep work is underway with equipment on site. Roofing work on west stage fly tower continues.
                                                                                                                                                                                                                              • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, stairs, wall panels, beams, and flooring have been installed in two sections of the new building with the front in progress.
                                                                                                                                                                                                                              • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                              • Periodic work will take place on the ART building mock-up to review design and constructability across North Harvard Street. Detailing will continue through July 11. Balustrades will arrive next week and steel detailing will take place with the finish trades will come to the site mid-July.
                                                                                                                                                                                                                              • No work is planned on either project for the holiday weekend July 4, 5 and 6.
                                                                                                                                                                                                                              • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                              • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                              210 North Harvard Street
                                                                                                                                                                                                                              • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                              • The bakery Sofra is open. 
                                                                                                                                                                                                                              168 Western Ave
                                                                                                                                                                                                                              • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                              • An air handler replacement is on the roof will be completed by Tuesday. A crane will be on site to assist with this work.
                                                                                                                                                                                                                              • Blue phone installation on the exterior of the building is planned for next Wednesday.
                                                                                                                                                                                                                              • Punch list and inspections are underway.
                                                                                                                                                                                                                              • Demobilization of the site fence and trailers is planned for next Tuesday and Wednesday.
                                                                                                                                                                                                                              • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated.

                                                                                                                                                                                                                              Anthony D'Isidoro

                                                                                                                                                                                                                              unread,
                                                                                                                                                                                                                              Jul 12, 2025, 4:48:57 PMJul 12
                                                                                                                                                                                                                              to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                              Harvard Construction Mitigation (Week of July 14, 2025)   

                                                                                                                                                                                                                              July 11, 2025

                                                                                                                                                                                                                              Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                              • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                              Enterprise Research Campus
                                                                                                                                                                                                                              Residential/Hotel
                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                              • On Saturday, July 12, many activities will be taking place including paving activities off Trotting Avenue and near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the buildings. Elevator and miscellaneous interior work is ongoing in all three buildings.
                                                                                                                                                                                                                              • On Sunday, July 13, inside the high-rise building a crew of eight will be working inside the elevator shafts, another eight will be onsite to conduct cleaning operations, and 18 workers will be installing carpeting. Outside the high rise building, 12 workers will be installing pavers, 20 will be installing panels and five will be installing overhead protection above newly installed pavers in the former hoist area.
                                                                                                                                                                                                                              Weekday/Night Activities
                                                                                                                                                                                                                              • Various testing and inspections will be ongoing in preparation for a temporary certificate of occupancy later this week in the midrise residential building.
                                                                                                                                                                                                                              • Trotting Avenue is being prepared for a partial opening after occupancy.
                                                                                                                                                                                                                              • Crews are scheduled to work in the evenings and nighttime at the high-rise, exterior façade from 3 p.m. to 5 a.m. on swing staging the former hoist infill area with portable light towers pointed at the building.
                                                                                                                                                                                                                              • Paver activities and possible interior highrise work will occur from 11 p.m. – 7 a.m.
                                                                                                                                                                                                                              • Exterior wall sheathing, panel clips and green exterior panels are being installed on the highrise building.
                                                                                                                                                                                                                              • Ground floor work is underway on the highrise, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                              • Mast climber scaffolding and swing staging are set up on the high-rise building.
                                                                                                                                                                                                                              • Elevator installation and start up activity continues.
                                                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                                                              • Framing, drywall and bathroom installation are taking place inside the buildings.
                                                                                                                                                                                                                              • Flooring and painting are underway.
                                                                                                                                                                                                                              Laboratory and Office Buildings
                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                              • On Saturday, July 12, the concrete pad at the former hoist area will be demolished. Exterior first floor work and roofing activity, weather permitting, will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                                                                                              • No work is scheduled for Sunday, July 13.
                                                                                                                                                                                                                              Weekday Activities
                                                                                                                                                                                                                              • A crane will be finishing on site to install infill curtainwall where the hoist was located.
                                                                                                                                                                                                                              • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                              • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                                                              • Roof activities are underway.
                                                                                                                                                                                                                              • Elevators are being installed and inspected.
                                                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                                                              • Mechanical penthouse activities continue.
                                                                                                                                                                                                                              • Masonry work continues.
                                                                                                                                                                                                                              • Pre-clear, structural soil backfill and granite curb will take place on the east side of the buildings.
                                                                                                                                                                                                                              • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                              Treehouse Conference Center
                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                              • On Saturday, July 12, a crane will be on site for some start up roof work, and cistern tank install work will take place. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                              • No work is scheduled for Sunday, July 13.
                                                                                                                                                                                                                              Weekday/Night Activities
                                                                                                                                                                                                                                • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                                                • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                                                • Duct bank excavation and install is occurring.
                                                                                                                                                                                                                                • Framing and drywall continue.
                                                                                                                                                                                                                                • Elevator work is underway.
                                                                                                                                                                                                                                • MEP activities are ongoing.
                                                                                                                                                                                                                                • Flooring and ceiling work continues.
                                                                                                                                                                                                                                • Small concrete placements will take place.
                                                                                                                                                                                                                                • Bathroom work continues.
                                                                                                                                                                                                                                • Painting is underway.
                                                                                                                                                                                                                                  Greenway
                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                  • On Saturday, July 12, irrigation systems are being installed on the shared-use path.
                                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                                    • Landscaping crews continue prepping for hardscape.
                                                                                                                                                                                                                                    • Light pole bases are being installed.
                                                                                                                                                                                                                                    • Utility and backfilling work are underway for water features.
                                                                                                                                                                                                                                    • Outcropping (boulder) install continues.
                                                                                                                                                                                                                                    Streetscape
                                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                                    • On Saturday, July 12, sidewalk and curbing work will take place.
                                                                                                                                                                                                                                    Weekday Activities
                                                                                                                                                                                                                                    • Paver install continues north of the loading dock on Trotting with preclearing needed. Sidewalks, curbing, paver install near the buildings. Piping will continue to be installed along Milestone St.
                                                                                                                                                                                                                                    Building Mock-Ups
                                                                                                                                                                                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                      • A pedestrian pathway from the Hague Street lot to the street is installed.
                                                                                                                                                                                                                                      Eversource Conduit Project
                                                                                                                                                                                                                                      • Eversource electrical manhole work and splicing continues along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                      General
                                                                                                                                                                                                                                        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                        • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                          • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                          • A drone is scheduled to fly on Thursday, July 17, at 3 p.m.
                                                                                                                                                                                                                                        North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                        • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                        • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                                        • Pipe installation continues and slide rail removal will continue.
                                                                                                                                                                                                                                        • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                        • Truck traffic will increase to load in material.
                                                                                                                                                                                                                                        • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                                                        • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                                          92 Seattle Street
                                                                                                                                                                                                                                            • Project has received a COO.
                                                                                                                                                                                                                                            • Eversource will be working at 38 Travis Steet and Rena Path.
                                                                                                                                                                                                                                            • The west wall repair is expected to be underway next week.
                                                                                                                                                                                                                                            • All work is targeting completion in four weeks.
                                                                                                                                                                                                                                            175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                                                                            The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                                                                            • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple swing stages are in place around the job site. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. The operating crane moved into a different on-site location last week and a second crane was mobilized on July 7. The site fence was extended to fit the crane. An additional crane will arrive on Monday, July 14 to place a generator and hoist equipment up to the tower roof/penthouse. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation is ongoing in the north tower. Drywall work continues and dry wall deliveries take place 3 p.m. to 6 p.m. three times per week and will start every Saturday, beginning July 12, for the rest of the summer as fit outs continue. On the south side of the tower, crews will be erecting scaffolding. Small utilities inside the site continue. Telecom duct bank installation is ongoing. Framing and sheathing are complete on the tower. Roofing and window installation are ongoing.
                                                                                                                                                                                                                                            • Next week, the week of July 14, excluding Saturday and Sunday, the contractor will need to close South Campus Drive periodically between 7 a.m. to 5 p.m. South Campus Drive will be open to traffic each day after 5 p.m.
                                                                                                                                                                                                                                            • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                            • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                            • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                                            • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                            • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front section of the building closest to North Harvard Street. Work will shift to the west to continue the front-section this month. Masonry work is underway. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. Mechanical system prep work is underway with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Roofing work on west stage fly tower continues.
                                                                                                                                                                                                                                            • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, stairs, wall panels, beams, and flooring have been installed in two sections of the new building with the front in progress.
                                                                                                                                                                                                                                            • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                                            • Work will be taking place at the affiliate housing building on the next two Saturdays, July 12 and 19, to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather.
                                                                                                                                                                                                                                            • A crew at the ART project will be working on mass timber on Saturday, July 12.
                                                                                                                                                                                                                                            • Periodic work will take place on the ART building mock-up to review design and constructability across North Harvard Street. Framing started last week, and steel detailing will take place with the finish trades coming to the site this month.
                                                                                                                                                                                                                                            • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                            • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                            210 North Harvard Street
                                                                                                                                                                                                                                            • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                            • The bakery Sofra is open. 
                                                                                                                                                                                                                                            168 Western Ave
                                                                                                                                                                                                                                            • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                                            • Blue phone installation on the exterior will take place.
                                                                                                                                                                                                                                            • Punch list and inspections are underway.
                                                                                                                                                                                                                                            • Demobilization of the site fence and trailers took place.
                                                                                                                                                                                                                                            • Roof commissioning and patch work is underway.
                                                                                                                                                                                                                                            • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated.

                                                                                                                                                                                                                                            Anthony D'Isidoro

                                                                                                                                                                                                                                            unread,
                                                                                                                                                                                                                                            Jul 19, 2025, 9:14:47 AMJul 19
                                                                                                                                                                                                                                            to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                            Harvard Construction Mitigation (Week of July 21, 2025)   

                                                                                                                                                                                                                                            July 18, 2025

                                                                                                                                                                                                                                            Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                                            • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                                            Enterprise Research Campus

                                                                                                                                                                                                                                            Residential/Hotel
                                                                                                                                                                                                                                            Weekend Activities
                                                                                                                                                                                                                                            • On Saturday, July 19, many activities will be taking place including paver install near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the buildings. Elevator and miscellaneous interior work are ongoing in hotel and high-rise buildings.
                                                                                                                                                                                                                                            • On Sunday, July 20, inside the high-rise building a crew of eight will be working inside the elevator shafts, another eight will be onsite to conduct cleaning operations. Outside the high-rise building, 12 workers will be installing pavers and 18 will be installing panels in the former hoist area.
                                                                                                                                                                                                                                            Weekday/Night Activities
                                                                                                                                                                                                                                            • Trotting Avenue will be open to the public next week with the start of occupancy in the midrise residential building.
                                                                                                                                                                                                                                            • Various testing and inspections will be ongoing in preparation for a temporary certificate of occupancy in early August in the high-rise residential building.
                                                                                                                                                                                                                                            • Crews are scheduled to work in the evenings and nighttime at the high-rise, exterior façade from 3 p.m. to 5 a.m. on swing staging the former hoist infill area with portable light towers pointed at the building.
                                                                                                                                                                                                                                            • Paver activities and possible interior high-rise work will occur from 11 p.m. – 7 a.m.
                                                                                                                                                                                                                                            • Exterior wall sheathing, panel clips and green exterior panels are being installed on the high-rise building.
                                                                                                                                                                                                                                            • Lobby and punch list work is finishing in the midrise.
                                                                                                                                                                                                                                            • Ground floor work is underway on the highrise, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                                            • Swing staging is in use on the east side of the high-rise building.
                                                                                                                                                                                                                                            • Elevator installation and start up activity continues.
                                                                                                                                                                                                                                            • Smaller concrete operations continue.
                                                                                                                                                                                                                                            • MEP work is ongoing.
                                                                                                                                                                                                                                            • Framing, drywall and bathroom installation are taking place inside the hotel and high-rise buildings.
                                                                                                                                                                                                                                            • Flooring and painting are underway.
                                                                                                                                                                                                                                            Laboratory and Office Buildings
                                                                                                                                                                                                                                            Weekend Activities
                                                                                                                                                                                                                                            • On Saturday, July 19, roofing activity and some first-floor work will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as general clean-up activities will occur.
                                                                                                                                                                                                                                            • On Sunday, July 20 four elevator workers will be on site.
                                                                                                                                                                                                                                            Weekday Activities
                                                                                                                                                                                                                                              • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                                              • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                                                                              • Roof and terrace activities are underway.
                                                                                                                                                                                                                                              • Elevators are being installed and inspected.
                                                                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                                                                              • Mechanical penthouse activities continue.
                                                                                                                                                                                                                                              • Masonry work continues.
                                                                                                                                                                                                                                              • Concrete form work will begin on the east side of the buildings. At Axle Way, excavation and backfilling structural soil and curbing install will be underway.
                                                                                                                                                                                                                                              • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                                              • Some drive lane striping and traffic coating will take place.
                                                                                                                                                                                                                                              Treehouse Conference Center
                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                              • On Saturday, July 19, roof activities, wood panel and façade installation will take place. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                                              • On Sunday, July 20, four electricians will be piping light poles in the laneway between the Treehouse and highrise/hotel.
                                                                                                                                                                                                                                              Weekday/Night Activities
                                                                                                                                                                                                                                                • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts.
                                                                                                                                                                                                                                                • Wood trim panels and other façade installation continue.
                                                                                                                                                                                                                                                • Duct bank excavation and install is occurring.
                                                                                                                                                                                                                                                • Roof activities continue.
                                                                                                                                                                                                                                                • Paver activities will begin.
                                                                                                                                                                                                                                                • Light pole bases will be installed.
                                                                                                                                                                                                                                                • Framing and drywall continue.
                                                                                                                                                                                                                                                • Elevator work is underway.
                                                                                                                                                                                                                                                • MEP activities are ongoing.
                                                                                                                                                                                                                                                • Flooring and ceiling work continues.
                                                                                                                                                                                                                                                • Small concrete placements will take place.
                                                                                                                                                                                                                                                • Bathroom work continues.
                                                                                                                                                                                                                                                • Painting is underway.
                                                                                                                                                                                                                                                  Greenway
                                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                                  • Drain reinstall work will take place on Saturday, July 19.
                                                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                                                    • Landscaping crews continue prepping for hardscape.
                                                                                                                                                                                                                                                    • Utility and backfilling work are underway for water features.
                                                                                                                                                                                                                                                    • Outcropping (boulder)install continues.
                                                                                                                                                                                                                                                      Streetscape
                                                                                                                                                                                                                                                      Weekday Activities
                                                                                                                                                                                                                                                      • Stone drainage, light pole bases and structural soil will be placed on Trotting Avenue, north of the loading dock. Sidewalks, curbing, paver install near the buildings.  Irrigation work and prep for sidewalk work will take place along Milestone St.
                                                                                                                                                                                                                                                      Building Mock-Ups
                                                                                                                                                                                                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                                      • A pedestrian pathway from the Hague Street lot to the street is installed.
                                                                                                                                                                                                                                                      Eversource Conduit Project
                                                                                                                                                                                                                                                      • Eversource electrical manhole work and splicing continues along Western Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                                      General
                                                                                                                                                                                                                                                      • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                      • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                                        • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                        • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                                        • A drone is scheduled to fly on Thursday, July 24, at 3 p.m.
                                                                                                                                                                                                                                                      North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                                      The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                                      • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                                      • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                                                      • Pipe installation continues and slide rail removal will continue.
                                                                                                                                                                                                                                                      • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                                      • Brick inverts are being installed.
                                                                                                                                                                                                                                                      • Truck traffic will increase to load in material.
                                                                                                                                                                                                                                                      • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                                                                      • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                                                      92 Seattle Street
                                                                                                                                                                                                                                                      • Project has received a COO.
                                                                                                                                                                                                                                                      • Eversource will be working at 38 Travis Steet and Rena Path.
                                                                                                                                                                                                                                                      • The west wall repair is expected to be underway next week.
                                                                                                                                                                                                                                                      • All work is targeting completion in four weeks.
                                                                                                                                                                                                                                                      175 North Harvard Street, 100 South Campus Drive 
                                                                                                                                                                                                                                                      The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART).
                                                                                                                                                                                                                                                      • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. Two cranes are operating on site on different areas of the building. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation is ongoing in the north tower. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3 p.m. to 6 p.m. and on Saturdays, throughout the summer. Small utilities inside the site continue. Telecom duct bank installation is ongoing. Framing and sheathing are complete on the tower. Roofing and window installation are ongoing. Smaller concrete placements continue. Next week, the week of July 21, excluding Saturday and Sunday, the contractor will need to close South Campus Drive periodically between 7 a.m. to 5 p.m. South Campus Drive will be open to traffic each day after 5 p.m.
                                                                                                                                                                                                                                                      • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                                      • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                                      • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                                                      • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                                      • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front section of the building closest to North Harvard Street. Work will shift to the west to continue the front-section this month. Masonry work is underway. Additional trades are on site for block work, roof level parapet work, and slab on deck pours. Mechanical system prep work is underway with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Roofing work on west continues.
                                                                                                                                                                                                                                                      • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, stairs, wall panels, beams, and flooring have been installed in two sections of the new building with the front in progress.
                                                                                                                                                                                                                                                      • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                                                      • Work will be taking place at the affiliate housing building on Saturday, 19 to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather.
                                                                                                                                                                                                                                                      • A crew at the ART project will be working on mass timber on Saturday, July 19.
                                                                                                                                                                                                                                                      • Periodic work will take place on the ART building mock-up to review design and constructability across North Harvard Street. Framing started last week, and steel detailing will take place with the finish trades coming to the site this month.
                                                                                                                                                                                                                                                      • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                      • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                                      210 North Harvard Street
                                                                                                                                                                                                                                                      • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                                      • The bakery Sofra is open. 
                                                                                                                                                                                                                                                      168 Western Ave
                                                                                                                                                                                                                                                      • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                                                      • Modifications to the Blue Phone foundation on the exterior building will take place.
                                                                                                                                                                                                                                                      • Walking pads are being placed on the roof next week.
                                                                                                                                                                                                                                                      • Punch list and inspections are underway.
                                                                                                                                                                                                                                                      • Demobilization of the site fence and trailers took place.
                                                                                                                                                                                                                                                      • Roof commissioning and patch work is underway.
                                                                                                                                                                                                                                                      • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated.

                                                                                                                                                                                                                                                      Anthony D'Isidoro

                                                                                                                                                                                                                                                      unread,
                                                                                                                                                                                                                                                      Jul 26, 2025, 9:11:16 AMJul 26
                                                                                                                                                                                                                                                      to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                      Harvard Construction Mitigation (Week of July 28, 2025)   

                                                                                                                                                                                                                                                      July 25, 2025

                                                                                                                                                                                                                                                      Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank 
                                                                                                                                                                                                                                                      • Thermal striping in the Harvard Business School lot will take place this fall. 
                                                                                                                                                                                                                                                      Enterprise Research Campus 
                                                                                                                                                                                                                                                      Residential/Hotel
                                                                                                                                                                                                                                                      Weekend Activities 
                                                                                                                                                                                                                                                      • On Saturday, July 26, many activities will be taking place including paver install near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the buildings. Elevator and miscellaneous interior work are ongoing in hotel and high-rise buildings. 
                                                                                                                                                                                                                                                      • On Sunday, July 27, at the high rise building 12 workers will be installing panels in the former hoist area and another 25 workers will be installing pavers, planters and more. Inside the high rise, a crew of four will be working in elevator shafts, another eight to 12 will be onsite to conduct cleaning and punch-list operations. 
                                                                                                                                                                                                                                                      Weekday/Night Activities 
                                                                                                                                                                                                                                                      • Trotting Avenue is open to the public as the midrise residential building begins to be occupied. 
                                                                                                                                                                                                                                                      • Various testing and inspections will be ongoing in preparation for a temporary certificate of occupancy in early August in the high-rise residential building. Periodic alarms will be heard. 
                                                                                                                                                                                                                                                      • Crews are scheduled to work in the evenings and nighttime at the high-rise, exterior façade from 3 p.m. to 5 a.m. on swing staging the former hoist infill area with portable light towers pointed at the building. 
                                                                                                                                                                                                                                                      • Paver activities and interior high-rise work will occur from 3 p.m. to 11 p.m. 
                                                                                                                                                                                                                                                      • Exterior wall sheathing, panel clips and green exterior panels are being installed on the high-rise building. 
                                                                                                                                                                                                                                                      • Lobby and punch list work is finishing in the midrise. 
                                                                                                                                                                                                                                                      • Ground floor work is underway on the highrise, including soffit panel installation using lifts at the hotel. 
                                                                                                                                                                                                                                                      • Swing staging is in use on the east side of the high-rise building. 
                                                                                                                                                                                                                                                      • Elevator installation and start up activity continues. 
                                                                                                                                                                                                                                                      • Smaller concrete operations continue. 
                                                                                                                                                                                                                                                      • MEP work is ongoing. 
                                                                                                                                                                                                                                                      • Framing, drywall and bathroom installation are taking place inside the hotel and high-rise buildings. 
                                                                                                                                                                                                                                                      • Flooring and painting are underway. 
                                                                                                                                                                                                                                                      • Punch-list finish activities on many floors inside the highrise. 
                                                                                                                                                                                                                                                      Laboratory and Office Buildings 
                                                                                                                                                                                                                                                      Weekend Activities 
                                                                                                                                                                                                                                                      • On Saturday, July 26, roofing activity and some first-floor work will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as general clean-up activities will occur. 
                                                                                                                                                                                                                                                      • On Sunday, July 27 eight workers will be doing detail roofing activity. 
                                                                                                                                                                                                                                                      Weekday Activities 
                                                                                                                                                                                                                                                      • Tuesday, July 29 a crane is expected to place trees and soils on the north terrace. 
                                                                                                                                                                                                                                                      • Boom lifts are active around the perimeter of the buildings. 
                                                                                                                                                                                                                                                      • Level 1 soffit and exterior work is underway. 
                                                                                                                                                                                                                                                      • Smaller concrete operations continue. 
                                                                                                                                                                                                                                                      • Roof and terrace activities are underway. 
                                                                                                                                                                                                                                                      • Elevators are being installed and inspected. 
                                                                                                                                                                                                                                                      • MEP work is ongoing. 
                                                                                                                                                                                                                                                      • Mechanical penthouse activities continue. 
                                                                                                                                                                                                                                                      • Stone masonry work continues especially at the former temp loading dock location. 
                                                                                                                                                                                                                                                      • Concrete form and placement on the east side of the buildings. At Axle Way, excavation and backfilling structural soil and curbing install will be underway. 
                                                                                                                                                                                                                                                      • Framing, drywall and bathroom install are underway. 
                                                                                                                                                                                                                                                      • Some drive lane striping and traffic coating will take place. 
                                                                                                                                                                                                                                                      Treehouse Conference Center 
                                                                                                                                                                                                                                                      Weekend Activities 
                                                                                                                                                                                                                                                      • On Saturday, July 26, roof activities, wood panel and façade installation will take place. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity. 
                                                                                                                                                                                                                                                      • On Sunday, July 27, four workers will be detailing on the roof and six workers will be doing façade work. 
                                                                                                                                                                                                                                                      Weekday/Night Activities 
                                                                                                                                                                                                                                                        • A small crew is scheduled to work on the facade from 3 to 11 p.m. using lifts. 
                                                                                                                                                                                                                                                        • Wood trim panels and other façade installation continue. 
                                                                                                                                                                                                                                                        • Duct bank excavation and install is occurring. 
                                                                                                                                                                                                                                                        • Roof activities continue. 
                                                                                                                                                                                                                                                        • Paver activities will begin. 
                                                                                                                                                                                                                                                        • Granite work continues on exterior ground floor. 
                                                                                                                                                                                                                                                        • Elevator work is underway. 
                                                                                                                                                                                                                                                        • MEP activities are ongoing. 
                                                                                                                                                                                                                                                        • Flooring and ceiling work continues. 
                                                                                                                                                                                                                                                        • Small concrete placements will take place. 
                                                                                                                                                                                                                                                        • Bathroom work continues. 
                                                                                                                                                                                                                                                        • Painting is underway. 
                                                                                                                                                                                                                                                        • Finish, tile and mill work are ongoing. 
                                                                                                                                                                                                                                                        Greenway
                                                                                                                                                                                                                                                        Weekend Activities 
                                                                                                                                                                                                                                                        • On Saturday, July 26, irrigation work will be underway. 
                                                                                                                                                                                                                                                        Weekday Activities 
                                                                                                                                                                                                                                                        • Landscaping crews continue working on the shared-use path. 
                                                                                                                                                                                                                                                        • Stone and backfilling work are underway for water features. 
                                                                                                                                                                                                                                                        • Outcropping (boulder)install continues. 
                                                                                                                                                                                                                                                        • Excavating for footing for bio-swales 
                                                                                                                                                                                                                                                        Streetscape 
                                                                                                                                                                                                                                                        Weekend Activities 
                                                                                                                                                                                                                                                        • On Saturday, July 26 crews will be running conduit and irrigation lines.  
                                                                                                                                                                                                                                                        Weekday Activities 
                                                                                                                                                                                                                                                        • Concrete prep and placement for sidewalks on Trotting Avenue, north of the loading dock. Curbing, paver install near the buildings.  Irrigation work and sidewalk work will take place along Milestone St. 
                                                                                                                                                                                                                                                        Building Mock-Ups 
                                                                                                                                                                                                                                                        • Building mockups are on the corner of Hague and Rotterdam Streets. 
                                                                                                                                                                                                                                                        Eversource Conduit Project 
                                                                                                                                                                                                                                                        • Eversource electrical manhole work and splicing continues along Western Avenue. This public utility work is not under the supervision of ERC. 
                                                                                                                                                                                                                                                        General 
                                                                                                                                                                                                                                                        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m. 
                                                                                                                                                                                                                                                        • Drones will be in use bi-weekly to monitor construction progress on site. 
                                                                                                                                                                                                                                                        • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                          • Weekly flights are weather dependent and are scheduled one weekday morning. 
                                                                                                                                                                                                                                                          • A drone is scheduled to fly on Thursday, July 31, at 3 p.m. 
                                                                                                                                                                                                                                                        North Allston Storm Drain Extension Project (NASDEP) 
                                                                                                                                                                                                                                                        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site. 
                                                                                                                                                                                                                                                        • South of Science work between Rena Path and Rotterdam Street will continue this week. 
                                                                                                                                                                                                                                                        • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.  
                                                                                                                                                                                                                                                        • Pipe and manhole installation continues 
                                                                                                                                                                                                                                                        • Backfilling operations intermittently occur.  
                                                                                                                                                                                                                                                        • Brick inverts are being installed.  
                                                                                                                                                                                                                                                        • Truck traffic will increase to load in material.  
                                                                                                                                                                                                                                                        • A temporary drainage bypass system with an operator is running. 
                                                                                                                                                                                                                                                        • A generator and motorized dewatering equipment operate on site. 
                                                                                                                                                                                                                                                          92 Seattle Street   
                                                                                                                                                                                                                                                            • Project has received a COO.  
                                                                                                                                                                                                                                                            • The west wall repair is underway and will be completed in two weeks.  
                                                                                                                                                                                                                                                            • Some light work on the roof will take place.  
                                                                                                                                                                                                                                                            • A permanent exterior sign will be completed. 
                                                                                                                                                                                                                                                            • All work is targeting completion in four weeks.  
                                                                                                                                                                                                                                                              175 North Harvard Street Project 
                                                                                                                                                                                                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):  
                                                                                                                                                                                                                                                              • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation. Some swing staging will be removed by early August. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. Two cranes are operating on site on different areas of the building. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation remains ongoing in the north tower. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3 p.m. to 6 p.m. and on Saturdays, throughout the summer. Small utilities inside the site continue. Telecom duct bank installation and backfill is underway. Framing and sheathing are complete on the tower. Roofing installation is ongoing. Window installation continues with less than 100 windows remaining. Smaller concrete placements continue.  
                                                                                                                                                                                                                                                              • South Campus Drive will be closed to vehicles between 7:00 a.m. to 5:00 p.m. on Monday, July 28, to accommodate a crane needed to hoist roofing materials. For the remainer of the week of July 28, excluding Saturday and Sunday, the contractor will need to close South Campus Drive periodically between 7:00 a.m. to 5:00 p.m. The road will be open to traffic each day after 5:00 p.m.  
                                                                                                                                                                                                                                                              • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.  
                                                                                                                                                                                                                                                              • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.  
                                                                                                                                                                                                                                                              • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.  
                                                                                                                                                                                                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.  
                                                                                                                                                                                                                                                              • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front section of the building closest to North Harvard Street. Stair installation is underway. Work will shift to the west to continue the front section this month. Additional trades are on site for masonry work, roof level parapet work, and slab on deck pours. Mechanical system work is underway with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Roofing work continues. Some drywall work is taking place. Exterior wall work has begun.  
                                                                                                                                                                                                                                                              • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, stairs, wall panels, beams, and flooring have been installed in two sections of the new building with work on the front of the building in progress.  
                                                                                                                                                                                                                                                              • Drones are flying over the site on a bi-weekly basis to capture project progress.  
                                                                                                                                                                                                                                                              • Work will be taking place at the affiliate housing building on Saturdays, July 26, and August 2, to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather. Some Saturday work can be expected each week going forward.  
                                                                                                                                                                                                                                                              • A crew at the ART project will be working on mass timber and some roofing on Saturday, July 26. Saturday work is expected through the winter.  
                                                                                                                                                                                                                                                              • Finishes and design review of the stage flip-up gallery will take place the week of July 28 at the ART building mock-up across North Harvard Street.  
                                                                                                                                                                                                                                                              • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.  
                                                                                                                                                                                                                                                              • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.  
                                                                                                                                                                                                                                                              210 North Harvard Street  
                                                                                                                                                                                                                                                              • Eversource or Verizon will remove an old pole and power line.  
                                                                                                                                                                                                                                                              • The bakery Sofra is open.   
                                                                                                                                                                                                                                                              168 Western Ave  
                                                                                                                                                                                                                                                              • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.  
                                                                                                                                                                                                                                                              • Blue Phone installation is complete.  
                                                                                                                                                                                                                                                              • Walking pads are being placed on the roof next week. 
                                                                                                                                                                                                                                                              • Punch list and inspections are underway. 
                                                                                                                                                                                                                                                              • Demobilization of the site fence and trailers took place.  
                                                                                                                                                                                                                                                              • Roof commissioning work is underway.  
                                                                                                                                                                                                                                                              • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated.  

                                                                                                                                                                                                                                                              Anthony D'Isidoro

                                                                                                                                                                                                                                                              unread,
                                                                                                                                                                                                                                                              Aug 3, 2025, 10:09:06 AMAug 3
                                                                                                                                                                                                                                                              to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                              Harvard Construction Mitigation (Week of August 4, 2025)   

                                                                                                                                                                                                                                                              August 1, 2025

                                                                                                                                                                                                                                                              Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                                                              • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                                                              Enterprise Research Campus
                                                                                                                                                                                                                                                              Residential/Hotel
                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                              • On Saturday, August 2, many activities will be taking place including paver install near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the buildings, especially focused on lobby work in the highrise. Elevator and miscellaneous interior work are ongoing in hotel and high-rise buildings.
                                                                                                                                                                                                                                                              • On Sunday, August 3, at the high rise building 12 workers will be installing panels in the former hoist area and another 25 workers will be installing pavers, planters and more. Inside the high rise, a crew of four will be working in elevator shafts. Crews will be onsite to conduct cleaning and doing punch-list operations and will painting. Each activity will have eight to 12 workers. Another six workers and 12 plumbers will be working in kitchens and bathrooms.
                                                                                                                                                                                                                                                              Weekday/Night Activities
                                                                                                                                                                                                                                                              • Trotting Avenue is open to the public as the midrise residential building begins to be occupied.
                                                                                                                                                                                                                                                              • Various testing and inspections will be ongoing in preparation for a temporary certificate of occupancy in early August in the high-rise residential building. Periodic alarms will be heard.
                                                                                                                                                                                                                                                              • Crews are scheduled to work in the evenings and nighttime at the high-rise, exterior façade from 3 p.m. to 5 a.m. on swing staging the former hoist infill area with portable light towers pointed at the building.
                                                                                                                                                                                                                                                              • Paver activities and interior high-rise work will occur from 3 p.m. to 11 p.m.
                                                                                                                                                                                                                                                              • Exterior wall sheathing, panel clips and green exterior panels are being installed on the high-rise building.
                                                                                                                                                                                                                                                              • Lobby and punch list work is finishing in the midrise.
                                                                                                                                                                                                                                                              • Ground floor work is underway on the highrise, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                                                              • Swing staging is in use on the east side of the high-rise building.
                                                                                                                                                                                                                                                              • Elevator installation and start up activity continues.
                                                                                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                                                                                              • Framing, drywall and bathroom installation are taking place inside the hotel and high-rise buildings.
                                                                                                                                                                                                                                                              • Flooring and painting are underway.
                                                                                                                                                                                                                                                              • Punch-list finish activities on many floors inside the highrise.
                                                                                                                                                                                                                                                              Laboratory and Office Buildings
                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                              • On Saturday, August 2, roofing activity, level 1exterior and south side site work will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as miscellaneous clean-up activities will occur. 
                                                                                                                                                                                                                                                              • On Sunday, August 3, four elevator workers will be inside the shafts.
                                                                                                                                                                                                                                                              Weekday Activities
                                                                                                                                                                                                                                                                • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                                                                • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                                                                • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                • Roof and terrace activities are underway.
                                                                                                                                                                                                                                                                • Elevators are being installed and inspected.
                                                                                                                                                                                                                                                                • MEP work is ongoing.
                                                                                                                                                                                                                                                                • Mechanical penthouse activities continue.
                                                                                                                                                                                                                                                                • Masonry work continues.
                                                                                                                                                                                                                                                                • At Axle Way, excavation and backfilling structural soil and curbing install will be underway.
                                                                                                                                                                                                                                                                • Irrigation and paver install are underway.
                                                                                                                                                                                                                                                                • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                                                                • Finish, tile and millwork are ongoing.
                                                                                                                                                                                                                                                                • Some drive lane striping and traffic coating will take place.
                                                                                                                                                                                                                                                                • Garage work continues.
                                                                                                                                                                                                                                                                • Bike storage is being installed.
                                                                                                                                                                                                                                                                Treehouse Conference Center
                                                                                                                                                                                                                                                                Weekend Activities
                                                                                                                                                                                                                                                                • On Saturday, Aug 2, roof activities, wood panel and façade installation will take place. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                                                                • On Sunday, August 3, eight site workers will be excavating and doing stone work.
                                                                                                                                                                                                                                                                Weekday/Night Activities
                                                                                                                                                                                                                                                                • A site crew will be excavating to place stone, install trench drains, shallow utilities and prepping for pavers from 5 p.m. to 10 p.m.
                                                                                                                                                                                                                                                                • Wood trim panels and other façade installation continue six days a week.
                                                                                                                                                                                                                                                                • Roof activities continue.
                                                                                                                                                                                                                                                                • Elevator work is underway.
                                                                                                                                                                                                                                                                • MEP activities are ongoing.
                                                                                                                                                                                                                                                                • Flooring and ceiling work continues.
                                                                                                                                                                                                                                                                • Bathroom work continues.
                                                                                                                                                                                                                                                                • Painting is underway.
                                                                                                                                                                                                                                                                • Finish,tile and mill work are ongoing.
                                                                                                                                                                                                                                                                • Small concrete placements will take place.
                                                                                                                                                                                                                                                                  Greenway
                                                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                                                  • On Saturday, August 2, preparation for footings and paver install will take place.
                                                                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                                                                    • Landscaping crews continue working on the shared-use path.
                                                                                                                                                                                                                                                                    • Water feature install work is underway.
                                                                                                                                                                                                                                                                    • Outcropping (boulder)install continues.
                                                                                                                                                                                                                                                                    • Excavating and prep for footings for bio-swales.
                                                                                                                                                                                                                                                                    Streetscape and Western Avenue
                                                                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                                                                    • On Saturday, August 2, structural soil work on Trotting Avenue and placing stone on Milestone Street will be underway.
                                                                                                                                                                                                                                                                    Weekday Activities
                                                                                                                                                                                                                                                                      • Concrete prep and placement for sidewalks on Trotting Avenue, north of the loading dock. Curbing, paver install near the buildings. 
                                                                                                                                                                                                                                                                      • Irrigation work and sidewalk work will take place along Milestone St.
                                                                                                                                                                                                                                                                      • Temporary lighting and trenching work have begun inside the fence along Western Avenue.
                                                                                                                                                                                                                                                                      Building Mock-Ups
                                                                                                                                                                                                                                                                      • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                                                      Eversource Conduit Project
                                                                                                                                                                                                                                                                      • Eversource electrical manhole work and splicing continues along Western Avenue and at Trotting Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                                                      General
                                                                                                                                                                                                                                                                        • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                                        • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                                                          • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                                          • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                                                          • A drone is scheduled to fly on Thursday, August 7, at 3 p.m.
                                                                                                                                                                                                                                                                        North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                                                        The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                                                        • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                                                        • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                                                                        • Pipe and manhole installation continues
                                                                                                                                                                                                                                                                        • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                                                        • Brick inverts are finishing installation.
                                                                                                                                                                                                                                                                        • Truck traffic will increase to load in material.
                                                                                                                                                                                                                                                                        • A temporary drainage bypass system with an operator is running.
                                                                                                                                                                                                                                                                        • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                                                                          92 Seattle Street  
                                                                                                                                                                                                                                                                            • Project has received a COO.
                                                                                                                                                                                                                                                                            • The west wall repair is underway and will be completed in August.  
                                                                                                                                                                                                                                                                            • Some light work on the roof will take place.
                                                                                                                                                                                                                                                                            • A permanent exterior sign will be completed.
                                                                                                                                                                                                                                                                            • All work is targeting completion in four weeks.
                                                                                                                                                                                                                                                                              175 North Harvard Street Project Construction Impacts
                                                                                                                                                                                                                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                                                                                                                                                                                                              • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation and masonry. Some swing staging will be removed this month. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. Two cranes are operating on site on different areas of the building. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation remains ongoing in the north tower. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3 p.m. to 6 p.m. and on Saturdays, throughout the summer. Interior framing is ongoing. Small utilities inside the site continue. Roofing installation is ongoing. The tower roof will be installed by mid-August. Window installation continues with less than 35 windows left to install on the north side. Smaller concrete placements continue.
                                                                                                                                                                                                                                                                              • South Campus Drive will be closed to vehicles between 7:00 a.m. to 5:00 p.m. intermittently during the week of August 4, excluding Saturday and Sunday. The road will be open to traffic each day after 5:00 p.m.
                                                                                                                                                                                                                                                                              • The contractor may need to utilize one lane of Ivy Lane in front of the project gate to unload materials. Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                                                              • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                                                              • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                                                              • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front sections of the building closest to North Harvard Street. Stair installation is underway. Work has shifted to the west to continue the front section this month. Additional trades are on site for masonry work, roof level parapet work, and slab on deck pours. Mechanical system work is underway with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Roofing work continues. Parapet work on the higher roofs is underway. The roof is complete on the section closets to the Harvard track. Some drywall work is taking place. Exterior wall work has begun. Brick scaffolding will start August 11.
                                                                                                                                                                                                                                                                              • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed. Columns, beams, stairs, wall panels, beams, and flooring have been installed in two sections of the new building with work on the front of the building in progress. The crew mobilized a crane on site while removing a larger crane last week.
                                                                                                                                                                                                                                                                              • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                                                                              • Work will be taking place at the affiliate housing building on Saturdays, August 2, and August 9, to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather. Some Saturday work can be expected each week going forward.
                                                                                                                                                                                                                                                                              • Some work on Sunday, August 3, is also expected at the affiliate housing building for roofing activity to expedite weather tightness on the 14-story structure. This work will take place on the north side of the project (the HU track side) and will not create any significant noise. Work will start at 8:00 a.m. and be finished by 4:00 p.m. The hoist and large equipment will not be operating, and all roads will remain open.
                                                                                                                                                                                                                                                                              • A crew at the ART project will be working on mass timber and some roofing on Saturday, August 2. Saturday work is expected through the winter.
                                                                                                                                                                                                                                                                              • Finishes and design review of the stage flip-up gallery took place last week at the ART building mock-up across North Harvard Street, which was decommissioned on August 1.
                                                                                                                                                                                                                                                                              • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                                                                                                                                                              • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                                                              210 North Harvard Street
                                                                                                                                                                                                                                                                              • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                                                              • The bakery Sofra is open. 
                                                                                                                                                                                                                                                                              168 Western Ave
                                                                                                                                                                                                                                                                              • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                                                                              • Walking pads are being placed on the roof next week.
                                                                                                                                                                                                                                                                              • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated.  
                                                                                                                                                                                                                                                                                CONTACT US 

                                                                                                                                                                                                                                                                                Anthony D'Isidoro

                                                                                                                                                                                                                                                                                unread,
                                                                                                                                                                                                                                                                                Aug 10, 2025, 7:25:49 AMAug 10
                                                                                                                                                                                                                                                                                to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                                                Harvard Construction Mitigation (Week of August 11, 2025)   

                                                                                                                                                                                                                                                                                August 8, 2025

                                                                                                                                                                                                                                                                                Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                                                                                • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                                                                                Enterprise Research Campus
                                                                                                                                                                                                                                                                                Residential/Hotel
                                                                                                                                                                                                                                                                                Weekend Activities
                                                                                                                                                                                                                                                                                • On Saturday, August 9, many activities will be taking place including paver install near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the buildings, especially focused on lobby work in the Highrise. Elevator and miscellaneous interior work are ongoing in hotel and high-rise buildings.
                                                                                                                                                                                                                                                                                • On Sunday, August 10, at the high rise building 12 workers will be installing panels in the former hoist area and another 25 workers will be installing pavers, planters and more. Inside the high rise, a crew of two will be working in elevator shafts.
                                                                                                                                                                                                                                                                                Weekday/Night Activities
                                                                                                                                                                                                                                                                                  • Trotting Avenue is open to the public as the midrise residential building begins to be occupied.
                                                                                                                                                                                                                                                                                  • Various testing and inspections will be ongoing in preparation for a temporary certificate of occupancy and residential occupancy next week in the high-rise residential building. Periodic alarms will be heard.
                                                                                                                                                                                                                                                                                  • Crews are scheduled to work in the evenings at the high-rise, exterior façade from 3 p.m. to 11 p.m. on swing staging the former hoist infill area with portable light towers pointed at the building.
                                                                                                                                                                                                                                                                                  • Paver activities may occur after hours.
                                                                                                                                                                                                                                                                                  • Exterior wall sheathing, panel clips and green exterior panels are being installed on the high-rise building.
                                                                                                                                                                                                                                                                                  • Punch list work is finishing in the midrise and Highrise.
                                                                                                                                                                                                                                                                                  • Ground floor work is underway on the hotel, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                                                                                  • Elevator installation and start up activity continues.
                                                                                                                                                                                                                                                                                  • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                                  • MEP work is ongoing.
                                                                                                                                                                                                                                                                                  • Framing, drywall and bathroom installation are taking place inside the hotel.
                                                                                                                                                                                                                                                                                  • Flooring and painting are underway.
                                                                                                                                                                                                                                                                                  Laboratory and Office Buildings
                                                                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                                                                  • On Saturday, August 9, roofing activity, level 1exterior and south side site work will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as miscellaneous clean-up activities will occur. 
                                                                                                                                                                                                                                                                                  • On Sunday, August 10, no work will be taking place on site.
                                                                                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                                                                                    • Boom lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                                                                                    • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                                                                                    • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                                    • Roof and terrace activities are underway.
                                                                                                                                                                                                                                                                                    • Elevators are being installed and inspected.
                                                                                                                                                                                                                                                                                    • MEP work is ongoing.
                                                                                                                                                                                                                                                                                    • Mechanical penthouse activities continue.
                                                                                                                                                                                                                                                                                    • Masonry work continues.
                                                                                                                                                                                                                                                                                    • At Axle Way, concrete sidewalk will be placed.
                                                                                                                                                                                                                                                                                    • Excavation for a bio-cell structure at Trotting Avenue will take place.
                                                                                                                                                                                                                                                                                    • Irrigation and paver install are underway.
                                                                                                                                                                                                                                                                                    • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                                                                                    • Finish, tile and millwork are ongoing.
                                                                                                                                                                                                                                                                                    • Some drive lane striping and traffic coating will take place.
                                                                                                                                                                                                                                                                                    • Garage work continues.
                                                                                                                                                                                                                                                                                    • Bike storage is being installed.
                                                                                                                                                                                                                                                                                    Treehouse Conference Center
                                                                                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                                                                                    • On Saturday, August 9, roof activities, wood panel and façade installation will take place. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                                                                                    • On Sunday, August 10, approximately 35 workers will be prepping for pavers, doing façade, roof and elevator work.
                                                                                                                                                                                                                                                                                    Weekday/Night Activities
                                                                                                                                                                                                                                                                                      • A site crew will be excavating to place stone, install trench drains, shallow utilities and prepping for pavers from 5 p.m. to 10 p.m.
                                                                                                                                                                                                                                                                                      • Wood trim panels and other façade installation continue six days a week.
                                                                                                                                                                                                                                                                                      • Roof activities continue.
                                                                                                                                                                                                                                                                                      • Elevator work is underway.
                                                                                                                                                                                                                                                                                      • MEP activities are ongoing.
                                                                                                                                                                                                                                                                                      • Flooring and ceiling work continues.
                                                                                                                                                                                                                                                                                      • Bathroom work continues.
                                                                                                                                                                                                                                                                                      • Painting is underway.
                                                                                                                                                                                                                                                                                      • Finish, tile and mill work are ongoing.
                                                                                                                                                                                                                                                                                      • Small concrete placements will take place.
                                                                                                                                                                                                                                                                                        Greenway
                                                                                                                                                                                                                                                                                        Weekend Activities
                                                                                                                                                                                                                                                                                        • On Saturday, August 9, preparation for footings and paver install will take place.
                                                                                                                                                                                                                                                                                        Weekday Activities
                                                                                                                                                                                                                                                                                          • Landscaping crews continue working on the shared-use path.
                                                                                                                                                                                                                                                                                          • Water feature install work is underway.
                                                                                                                                                                                                                                                                                          • Outcropping (boulder)install continues.
                                                                                                                                                                                                                                                                                          • Excavating and prep for footings for bio-swales.
                                                                                                                                                                                                                                                                                          • Placing smaller footings will take place in the grove area.
                                                                                                                                                                                                                                                                                          Streetscape and Western Avenue
                                                                                                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                                                                                                          • On Saturday, August 9, structural soil work on Trotting Avenue and placing stone on Milestone Street will be underway.  
                                                                                                                                                                                                                                                                                          Weekday Activities
                                                                                                                                                                                                                                                                                          • Concrete prep and placement for sidewalks on Trotting Avenue, north of the loading dock. Curbing, paver install near the buildings. 
                                                                                                                                                                                                                                                                                          • Irrigation work and sidewalk work will take place along Milestone St.
                                                                                                                                                                                                                                                                                          • Temporary lighting and trenching work have begun inside the fence along Western Avenue.
                                                                                                                                                                                                                                                                                          Building Mock-Ups
                                                                                                                                                                                                                                                                                          • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                                                                          Eversource Conduit Project
                                                                                                                                                                                                                                                                                          • Eversource electrical manhole work and splicing continues along Western Avenue and at Trotting Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                                                                          General
                                                                                                                                                                                                                                                                                          • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                                                          • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                                                                            • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                                                            • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                                                                            • A drone is scheduled to fly on Thursday, August 14, at 3 p.m.
                                                                                                                                                                                                                                                                                          North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                                                                          The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                                                                          • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                                                                          • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                                                                                          • Pipe and manhole installation continues
                                                                                                                                                                                                                                                                                          • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                                                                          • Brick inverts are complete.
                                                                                                                                                                                                                                                                                          • A CCTV camera will be placed through the system next week.
                                                                                                                                                                                                                                                                                          • Concrete demolition using a jack hammer and removal from site will take place next week within the site behind the Hague St parking lot.
                                                                                                                                                                                                                                                                                          • The temporary drainage bypass system is operating and will be removed pending camera results.
                                                                                                                                                                                                                                                                                          • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                                                                                            92 Seattle Street
                                                                                                                                                                                                                                                                                              • Project has received a COO.
                                                                                                                                                                                                                                                                                              • East ramp repair work is underway and will be completed in August.  
                                                                                                                                                                                                                                                                                              • A permanent exterior sign will be completed.
                                                                                                                                                                                                                                                                                              175 North Harvard Street Project Construction Impacts
                                                                                                                                                                                                                                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                                                                                                                                                                                                                              • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation and masonry. Some swing staging will be removed this month. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. Two cranes are operating on site on different areas of the building. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation remains ongoing in the north tower. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3 p.m. to 6 p.m. and on Saturdays, throughout the summer. Interior framing is ongoing. Small utilities inside the site continue. Roofing installation is ongoing. The tower roof will be installed by mid-August. Window installation continues with less than 30 windows left to install on the north side. Smaller concrete placements continue.
                                                                                                                                                                                                                                                                                              • South Campus Drive will be closed to vehicles between 7:00 a.m. to 4:00 p.m. from Monday, August 11 through Friday, August 15, to provide for crane access on the roof. The road will be open to traffic each day after 5:00 p.m.
                                                                                                                                                                                                                                                                                              • On Thursday, August 14, and Friday, August 15, the site fence near the crosswalk to the park will be shifted partly into Ivy Lane to allow for crane access to set parapet caps on the 8th story of the building. Ivy Lane one-way traffic will be maintained during this activity. Cones and signage will be in place to direct traffic and an HUPD detail will be present to assist.
                                                                                                                                                                                                                                                                                              • Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                                                                              • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                                                                              • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                                                                              • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front sections of the building closest to North Harvard Street and roofing has started on one of these sections. Additional trades are on site for masonry work, roof level parapet work, and slab on deck pours. Mechanical system work is underway with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Parapet work on the higher roofs is underway. The roof work is wrapping up on two of the three back sections of the building. Some drywall work is taking place. Exterior façade work has begun. Brick scaffolding will start on Monday, August 11. Mass timber on the building’s mid-section facing North Harvard will be up on Saturday, August 23, after which the contractor will start working on the front section of the building closest to Ivy Lane on Monday, August 25. Staging is going up to support the brick façade work.
                                                                                                                                                                                                                                                                                              • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed.
                                                                                                                                                                                                                                                                                              • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                                                                                              • Work will be taking place at the affiliate housing building on Saturdays, August 9, and August 16, to do some exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather. Some Saturday work can be expected each week going forward.
                                                                                                                                                                                                                                                                                              • Some work on Sunday, August 10, is also expected at both the affiliate housing building and the ART site. The housing building will have a small crew of seven workers roofing to expedite building weather tightness. This work will take place on a lower roof on the courtyard side of the building and will not create any significant noise. Work will start at 8:00 a.m. and be finished by 4:00 p.m. The hoist and large equipment will not be operating, and all roads will remain open. At the ART site, a crew of four workers will be placing a vapor barrier on the section of the building facing North Harvard Street, closest to the McCurdy Track.
                                                                                                                                                                                                                                                                                              • Finishes and design review of the stage flip-up gallery took place last week at the ART building mock-up across North Harvard Street, which was decommissioned on August 1.
                                                                                                                                                                                                                                                                                              • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                                                                                                                                                                              • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                                                                              210 North Harvard Street
                                                                                                                                                                                                                                                                                              • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                                                                              • The bakery Sofra is open. 
                                                                                                                                                                                                                                                                                              168 Western Ave
                                                                                                                                                                                                                                                                                              • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk.
                                                                                                                                                                                                                                                                                              • Walking pads are being placed on the roof next week.
                                                                                                                                                                                                                                                                                              • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated. 

                                                                                                                                                                                                                                                                                              Anthony D'Isidoro

                                                                                                                                                                                                                                                                                              unread,
                                                                                                                                                                                                                                                                                              Aug 16, 2025, 8:39:38 AMAug 16
                                                                                                                                                                                                                                                                                              to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                                                              Harvard Construction Mitigation (Week of August 18, 2025)   

                                                                                                                                                                                                                                                                                              August 15, 2025

                                                                                                                                                                                                                                                                                              Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                                                                                              • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                                                                                              Enterprise Research Campus
                                                                                                                                                                                                                                                                                              Residential/Hotel
                                                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                                                              • On Saturday, August 16, many activities will be taking place including paver install near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the buildings, especially focused on lobby work in the highrise. Elevator and miscellaneous interior work are ongoing in hotel with punch-list work in the high-rise building.
                                                                                                                                                                                                                                                                                              • On Sunday, August 17, at the high rise building 12 workers will be installing panels in the former hoist area and another 25 workers will be installing pavers, planters and more. Inside the high rise and hotel, a crew of four working in elevator shafts. Six painters will be working in the highrise.
                                                                                                                                                                                                                                                                                              Weekday/Night Activities
                                                                                                                                                                                                                                                                                              • Trotting Avenue is open to the public as the midrise and highrise residential buildings (Verra) begin to be occupied.
                                                                                                                                                                                                                                                                                              • Pre-testing will be ongoing in preparation for a temporary certificate of occupancy in late September in the hotel.
                                                                                                                                                                                                                                                                                              • Crews are scheduled to work in the evenings at the high-rise, exterior façade from 3 p.m. to 11 p.m. on swing staging the former hoist infill area with portable light towers pointed at the building.
                                                                                                                                                                                                                                                                                              • Paver activities continue.
                                                                                                                                                                                                                                                                                              • Exterior wall sheathing, panel clips and green exterior panels are being installed on the high-rise building at the former hoist area.
                                                                                                                                                                                                                                                                                              • Punch list work is finishing in the midrise and continuing in the highrise.
                                                                                                                                                                                                                                                                                              • Ground floor work is underway on the hotel, including soffit panel installation using lifts at the hotel.
                                                                                                                                                                                                                                                                                              • Elevator installation and start up activity continues.
                                                                                                                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                                                                                                                              • Framing, drywall and bathroom installation are taking place inside the hotel.
                                                                                                                                                                                                                                                                                              • Flooring and painting are underway.
                                                                                                                                                                                                                                                                                              Laboratory and Office Buildings
                                                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                                                              • On Saturday, August 16, roofing activity, level 1 exterior and south side site work will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as miscellaneous clean-up activities will occur. 
                                                                                                                                                                                                                                                                                              • On Sunday, August 17 no work will take place.
                                                                                                                                                                                                                                                                                              Weekday Activities
                                                                                                                                                                                                                                                                                              • A small crane will be on site next week to load railings.
                                                                                                                                                                                                                                                                                              • Boom and scissor lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                                                                                              • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                                                                                              • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                                              • Roof and terrace activities including paver install are underway.
                                                                                                                                                                                                                                                                                              • Elevators are being installed and inspected.
                                                                                                                                                                                                                                                                                              • MEP work is ongoing.
                                                                                                                                                                                                                                                                                              • Mechanical penthouse activities continue.
                                                                                                                                                                                                                                                                                              • Stone masonry work continues.
                                                                                                                                                                                                                                                                                              • At Axle Way, concrete sidewalk will be placed.
                                                                                                                                                                                                                                                                                              • Excavation for a bio-cell structure at Trotting Avenue will take place.
                                                                                                                                                                                                                                                                                              • Irrigation and concrete pad placement.
                                                                                                                                                                                                                                                                                              • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                                                                                              • Finish, tile and millwork are ongoing.
                                                                                                                                                                                                                                                                                              • Garage work continues.
                                                                                                                                                                                                                                                                                              • Bike storage is being installed.
                                                                                                                                                                                                                                                                                              Treehouse Conference Center
                                                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                                                              • On Saturday, August 16, wood panel and façade installation and some roof activities will take place. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                                                                                              • On Sunday, August 17, approximately 12 workers rearranging and cleaning up the laydown area and doing interior elevator work.
                                                                                                                                                                                                                                                                                              Weekday/Night Activities
                                                                                                                                                                                                                                                                                                • A site crew will be excavating to place stone, install trench drains, shallow utilities and prepping for pavers from 5 p.m. to 10 p.m.
                                                                                                                                                                                                                                                                                                • Wood trim panels and other façade installation continue six days a week.
                                                                                                                                                                                                                                                                                                • Roof activities continue.
                                                                                                                                                                                                                                                                                                • Elevator work is underway.
                                                                                                                                                                                                                                                                                                • MEP activities are ongoing.
                                                                                                                                                                                                                                                                                                • Flooring and ceiling work continues.
                                                                                                                                                                                                                                                                                                • Bathroom and kitchen work continues.
                                                                                                                                                                                                                                                                                                • Painting is underway.
                                                                                                                                                                                                                                                                                                • Finish tile and mill work are ongoing.
                                                                                                                                                                                                                                                                                                • Small concrete placements will take place.
                                                                                                                                                                                                                                                                                                  Greenway
                                                                                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                                                                                  • On Saturday, August 16, excavation in the bio-swale areas will take place.
                                                                                                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                                                                                                  • Trees will be delivered and planted.
                                                                                                                                                                                                                                                                                                  • Landscaping crews continue working on the shared-use path.
                                                                                                                                                                                                                                                                                                  • Water feature install work is underway.
                                                                                                                                                                                                                                                                                                  • Outcropping (boulder)install continues.
                                                                                                                                                                                                                                                                                                  • Excavating and prep for footings for bio-swales.
                                                                                                                                                                                                                                                                                                  Streetscape and Western Avenue
                                                                                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                                                                                  • On Saturday, August 16, stone layers will be set on Trotting Avenue.  
                                                                                                                                                                                                                                                                                                  Weekday Activities
                                                                                                                                                                                                                                                                                                    • Concrete prep and placement for sidewalks on Trotting Avenue, north of the loading dock. Curbing, paver install near the buildings. 
                                                                                                                                                                                                                                                                                                    • Irrigation work and sidewalk work will take place along Milestone St.
                                                                                                                                                                                                                                                                                                    • Temporary lighting pole and trenching work continue inside the fence along Western Avenue.
                                                                                                                                                                                                                                                                                                    Building Mock-Ups
                                                                                                                                                                                                                                                                                                    • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                                                                                    Eversource Conduit Project
                                                                                                                                                                                                                                                                                                    • Eversource electrical manhole work and splicing continues along Western Avenue and at Trotting Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                                                                                    General
                                                                                                                                                                                                                                                                                                    • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                                                                    • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                                                                                      • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                                                                      • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                                                                                      • A drone is scheduled to fly on Thursday, August 21, at 3 p.m.
                                                                                                                                                                                                                                                                                                    North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                                                                                    The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                                                                                    • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                                                                                    • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes.
                                                                                                                                                                                                                                                                                                    • Pipe and manhole installation continues
                                                                                                                                                                                                                                                                                                    • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                                                                                    • Brick inverts are finishing up.
                                                                                                                                                                                                                                                                                                    • A CCTV camera will be placed through the system.
                                                                                                                                                                                                                                                                                                    • Concrete demolition using a jack hammer and removal from site within the site behind the Hague St parking lot is complete.
                                                                                                                                                                                                                                                                                                    • The temporary drainage bypass system is operating and will be removed pending camera results.
                                                                                                                                                                                                                                                                                                    • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                                                                                                    • Science Drive restoration work will start the first week of September.
                                                                                                                                                                                                                                                                                                    92 Seattle Street
                                                                                                                                                                                                                                                                                                      • Project has received a COO.
                                                                                                                                                                                                                                                                                                      • East ramp repair work is underway and will be completed in August.  
                                                                                                                                                                                                                                                                                                      • Flooring contractor will mobilize at a later date.
                                                                                                                                                                                                                                                                                                      • Interior signage is ongoing and a permanent exterior sign will be completed.
                                                                                                                                                                                                                                                                                                      175 North Harvard Street Project Construction Impacts
                                                                                                                                                                                                                                                                                                      The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                                                                                                                                                                                                                                      • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation and masonry. Scaffolding is being installed on the west corner and is complete inside the courtyard. Some swing staging is being removed this month. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. Brick topping off on the mid-rise and south side is expected mid-September. Mechanical, electrical, and plumbing trades continue work on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation remains ongoing in the north tower. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3 p.m. to 6 p.m. and on Saturdays, throughout the summer. Interior framing is ongoing. Small utilities inside the site continue. Roofing installation is ongoing. The 14-story roof is ongoing and will be finished in about one week. A third crane this week loaded the last of the materials to the roof. Window installation continues. Smaller concrete placements continue. Finishes on the lower floors are ongoing. The bike storage room will begin in the fall.
                                                                                                                                                                                                                                                                                                      • South Campus Drive will be closed to vehicles periodically between 7:00 a.m. to 4:00 p.m. during the week of August 18, to provide for crane access to the roof. The road will be open to traffic each day after 5:00 p.m.
                                                                                                                                                                                                                                                                                                      • Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                                                                                      • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                                                                                      • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                                                                                                      • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                                                                                      • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front sections of the building closest to North Harvard Street and roofing is underway on one of these sections. Roofing materials are delivered by crane once per week. Additional trades are on site for masonry work, roof level parapet work, and slab on deck pours. Mechanical system work is ongoing with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Parapet work on the higher roofs is underway. The roof work is wrapping up on two of the three back sections of the building. Drywall work is taking place. Exterior façade work has begun. Brick scaffolding started last week. Mass timber on the building’s mid-section facing North Harvard will continue for another two weeks after which the contractor will start working on the front section of the building closest to Ivy Lane. Staging is going up to support the brick façade work. Curtain wall work will begin at the end of the month on the section of the building closest to Harvard’s track. 
                                                                                                                                                                                                                                                                                                      • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed.
                                                                                                                                                                                                                                                                                                      • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                                                                                                      • Work will be taking place at the affiliate housing building on Saturdays, August 16, and August 23, to work on exterior wall sheathing, window sealants, and interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather. Some Saturday work can be expected each week going forward.
                                                                                                                                                                                                                                                                                                      • A crew at the ART project will be working on mass timber and some roofing on Saturday, August 16. Saturday work is expected through the winter.
                                                                                                                                                                                                                                                                                                      • On Sunday, August 17, the housing building will have two small crews doing interior electrical and spray foam work inside the building.
                                                                                                                                                                                                                                                                                                      • Finishes and design review of the stage flip-up gallery took place last week at the ART building mock-up across North Harvard Street, which was decommissioned on August 1.
                                                                                                                                                                                                                                                                                                      • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                                                                                                                                                                                      • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                                                                                      • Utility valve work will be taking place inside the gate between the projects off South Campus Drive.
                                                                                                                                                                                                                                                                                                      210 North Harvard Street
                                                                                                                                                                                                                                                                                                      • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                                                                                      • The bakery Sofra is open. 
                                                                                                                                                                                                                                                                                                      168 Western Ave
                                                                                                                                                                                                                                                                                                      • National Grid has completed the gas pipe connection and will replace the asphalt with concrete on the sidewalk. This work should be completed in two weeks.
                                                                                                                                                                                                                                                                                                      • Walking pads are being placed on the roof.
                                                                                                                                                                                                                                                                                                      • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated. 
                                                                                                                                                                                                                                                                                                        CONTACT US 

                                                                                                                                                                                                                                                                                                        Anthony D'Isidoro

                                                                                                                                                                                                                                                                                                        unread,
                                                                                                                                                                                                                                                                                                        Aug 23, 2025, 9:26:06 AM (14 days ago) Aug 23
                                                                                                                                                                                                                                                                                                        to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                                                                        Harvard Construction Mitigation (Week of August 25, 2025)   

                                                                                                                                                                                                                                                                                                        August 22, 2025

                                                                                                                                                                                                                                                                                                        Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                                                                                                        • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                                                                                                        Enterprise Research Campus
                                                                                                                                                                                                                                                                                                        As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.
                                                                                                                                                                                                                                                                                                        Residential/Hotel
                                                                                                                                                                                                                                                                                                        Weekend Activities
                                                                                                                                                                                                                                                                                                        • On Saturday, August 23, many activities will be taking place including paver install near the high-rise residential building with several boom lifts operating and workers on staging for panel installation. First floor work will take place in the hotel. Elevator and miscellaneous interior work are ongoing in hotel with punch-list work in the high-rise building.
                                                                                                                                                                                                                                                                                                        • On Sunday, August 24, at the high rise building 12 workers will be installing panels in the former hoist area and another 25 workers will be installing pavers, planters and more. Inside the high rise two workers will be in the elevators and hotel, a crew of five working in elevator shafts. Six painters will be working in the highrise.
                                                                                                                                                                                                                                                                                                        Weekday/Night Activities
                                                                                                                                                                                                                                                                                                          • Trotting Avenue is open to the public as the midrise and highrise residential buildings (Verra) begin to be occupied.
                                                                                                                                                                                                                                                                                                          • Crews are scheduled to work during the day and in the evenings at the high-rise, exterior façade from 7:00 a.m. to 7:00 p.m. on swing staging the former hoist area.
                                                                                                                                                                                                                                                                                                          • Paver activities continue.
                                                                                                                                                                                                                                                                                                          • Punch list work is finishing in the midrise and continuing in the highrise.
                                                                                                                                                                                                                                                                                                          • Testing and inspections will be ongoing in preparation for a temporary certificate of occupancy in late September in the hotel. Other hotel activities include:
                                                                                                                                                                                                                                                                                                            • Ground floor work including soffit panel installation using lifts
                                                                                                                                                                                                                                                                                                            • Elevator installation and start up activity
                                                                                                                                                                                                                                                                                                            • Finishing one topping slab concrete placements
                                                                                                                                                                                                                                                                                                            • MEP work
                                                                                                                                                                                                                                                                                                            • Framing, drywall and bathroom installation
                                                                                                                                                                                                                                                                                                            • Flooring and painting
                                                                                                                                                                                                                                                                                                            • Finish, tile and millwork
                                                                                                                                                                                                                                                                                                          Laboratory and Office Buildings
                                                                                                                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                                                                                                                          • On Saturday, August 23, roofing activity, level 1 exterior and south side site work will be underway. Interior drywall, elevator work and MEP work in the penthouse as well as miscellaneous clean-up activities will occur. 
                                                                                                                                                                                                                                                                                                          • On Sunday, August 24 no work will take place.
                                                                                                                                                                                                                                                                                                          Weekday Activities
                                                                                                                                                                                                                                                                                                            • Boom and scissor lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                                                                                                            • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                                                                                                            • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                                                            • Roof and terrace activities including paver install are underway.
                                                                                                                                                                                                                                                                                                            • Elevators are being installed and inspected.
                                                                                                                                                                                                                                                                                                            • MEP work is ongoing.
                                                                                                                                                                                                                                                                                                            • Mechanical penthouse activities continue.
                                                                                                                                                                                                                                                                                                            • Stone masonry work continues.
                                                                                                                                                                                                                                                                                                            • At Axle Way, irrigation work continues.
                                                                                                                                                                                                                                                                                                            • Excavation for a bio-cell structure at Trotting Avenue will take place.
                                                                                                                                                                                                                                                                                                            • Irrigation and concrete pad placement.
                                                                                                                                                                                                                                                                                                            • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                                                                                                            • Finish, tile and millwork are ongoing.
                                                                                                                                                                                                                                                                                                            • Garage work continues.
                                                                                                                                                                                                                                                                                                            Treehouse Conference Center
                                                                                                                                                                                                                                                                                                            Weekend Activities
                                                                                                                                                                                                                                                                                                            • On Saturday, August 23, wood panel and façade installation and some roof activities will take place. Crews will be installing pavers. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                                                                                                            • On Sunday, August 24, approximately 30 workers will be on site including two roofers and those doing interior elevator, ceiling, electrical and other miscellaneous work.
                                                                                                                                                                                                                                                                                                            Weekday/Night Activities
                                                                                                                                                                                                                                                                                                            • A site crew will be excavating to place stone, shallow utilities and pavers from 5:00 p.m. to 10:00 p.m.
                                                                                                                                                                                                                                                                                                            • Wood trim panels and other façade installation continue two shifts from 7:00 a.m. to 10:00 p.m.
                                                                                                                                                                                                                                                                                                            • Roof detail activities continue.
                                                                                                                                                                                                                                                                                                            • Elevator work is underway.
                                                                                                                                                                                                                                                                                                            • MEP activities are ongoing
                                                                                                                                                                                                                                                                                                            • Building systems start-up, testing and inspections in preparation for temporary certificate of occupancy in late September are underway.
                                                                                                                                                                                                                                                                                                            • Flooring and ceiling work continues.
                                                                                                                                                                                                                                                                                                            • Bathroom and kitchen work continues.
                                                                                                                                                                                                                                                                                                            • Painting is underway.
                                                                                                                                                                                                                                                                                                            • Finish, tile and mill work are ongoing.
                                                                                                                                                                                                                                                                                                            • Small concrete placements will take place.
                                                                                                                                                                                                                                                                                                              Greenway
                                                                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                                                                              • On Saturday, August 23, excavation in the bio-swale areas will take place.
                                                                                                                                                                                                                                                                                                              Weekday Activities
                                                                                                                                                                                                                                                                                                              • Landscaping crews continue installing pavers at the shared-use path.
                                                                                                                                                                                                                                                                                                              • Water feature install work continues with a concrete placement for its slab and other footings on Tuesday, August 26.
                                                                                                                                                                                                                                                                                                              • Outcropping (boulder)install continues.
                                                                                                                                                                                                                                                                                                              • Excavating and prep for footings for bio-swales.
                                                                                                                                                                                                                                                                                                              Streetscape and Western Avenue
                                                                                                                                                                                                                                                                                                              Weekend Activities
                                                                                                                                                                                                                                                                                                              • On Saturday, August 23, stone layers will be set on Trotting Avenue.  
                                                                                                                                                                                                                                                                                                              Weekday Activities
                                                                                                                                                                                                                                                                                                              • Footings and slab concrete placement on Trotting Avenue, north of the loading dock. 
                                                                                                                                                                                                                                                                                                              • Structural soils placing and irrigation and stone reservoir work will take place along Milestone St.
                                                                                                                                                                                                                                                                                                              • Temporary lighting pole and trenching work continue inside the fence along Western Avenue.
                                                                                                                                                                                                                                                                                                              Building Mock-Ups
                                                                                                                                                                                                                                                                                                              • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                                                                                              Eversource Conduit Project
                                                                                                                                                                                                                                                                                                              • Eversource electrical manhole work and splicing continues along Western Avenue and at Trotting Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                                                                                              General
                                                                                                                                                                                                                                                                                                              • The projects work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                                                                                                                                                                                              • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                                                                                                • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                                                                                • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                                                                                                • Drones are scheduled to fly on Tuesday, August 26 at 9:00 a.m. and Thursday, August 28 at 3:00 p.m.
                                                                                                                                                                                                                                                                                                              175 North Harvard Street Project
                                                                                                                                                                                                                                                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                                                                                                                                                                                                                                              • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation and masonry. Ramp removal will take place next week which will allow crews to continue on the scaffolding on north side of the building. Scaffolding is being installed on the west corner and is complete inside the courtyard. Some swing staging is being removed this month. Multiple masonry crews are working on all sides of the building. Brick work is expanding around the building and brick deliveries have increased. Brick topping off on the mid-rise and south side is expected mid-September. Mechanical, electrical, and plumbing trades continue working on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation remains ongoing in the north tower. Finish work on the lower floors has started. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3:00 p.m. to 6:00 p.m. and on Saturdays, throughout the summer. Interior framing is ongoing. Small utilities inside the site continue. Roofing installation is ongoing. The 14-story roof is ongoing. Exterior roof work includes one more crane day on Monday to finish unloading the material for the 14-story roof. Window installation continues. Smaller concrete placements continue. Finishes on the lower floors are ongoing. The bike storage room will begin in the fall. Topping off on the mid-rise and south side is expected in mid-September.
                                                                                                                                                                                                                                                                                                              • South Campus Drive will be closed to vehicles periodically between 7:00 a.m. to 4:00 p.m. during the week of August 25, to provide for crane access to the roof. The road will be open to traffic each day after 5:00 p.m.
                                                                                                                                                                                                                                                                                                              • Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                                                                                              • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                                                                                              • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers. 
                                                                                                                                                                                                                                                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                                                                                              • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front sections of the building closest to North Harvard Street . Two of the three back sections are getting weather tight. Roofing is underway on all sections and will be wrapping up soon on two of the three back sections of the building. Roofing materials are delivered by crane once per week. Additional trades are on site for masonry work, roof level parapet work, and slab on deck pours. Mechanical system work is ongoing with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Drywall work is taking place. Exterior façade work is underway. Brick scaffolding started two weeks ago. Mass timber on the building’s mid-section facing North Harvard will continue for another two weeks after which the contractor will start working on the front section of the building closest to Ivy Lane. Staging is up to support the brick façade work. Curtain wall work will begin at the end of the month on the section of the building closest to Harvard’s track.
                                                                                                                                                                                                                                                                                                              • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed.
                                                                                                                                                                                                                                                                                                              • Drones are flying over the site on a bi-weekly basis to capture project progress. The next drone flight is scheduled for Wednesday, August 27 at 11:30 a.m.
                                                                                                                                                                                                                                                                                                              • Work will be taking place at the affiliate housing building on Saturdays, August 23, and August 30, to work on exterior wall sheathing, interior framing, mechanical, electrical, and plumbing work, and masonry. This work is dependent on the weather. Some Saturday work can be expected each week going forward.
                                                                                                                                                                                                                                                                                                              • A crew at the ART project will be working on mass timber and exterior storm drain work on Saturday, August 23. Saturday work is expected through the winter.
                                                                                                                                                                                                                                                                                                              • There will not be any Sunday work on either job site this week.
                                                                                                                                                                                                                                                                                                              • No work is currently taking place at the ART building mock-up across North Harvard Street.
                                                                                                                                                                                                                                                                                                              • The project’s regular work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                                                                                                                                                                                                                                                                                              • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                                                                                              North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                                                                                              The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                                                                                              • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                                                                                              • Science Drive is narrowed with new line striping indicating the lanes. Restoration will take place later in September.
                                                                                                                                                                                                                                                                                                              • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                                                                                              • A CCTV camera inspection of the system is under review.   
                                                                                                                                                                                                                                                                                                              • The temporary drainage bypass system is operating and will be removed pending
                                                                                                                                                                                                                                                                                                                camera results.
                                                                                                                                                                                                                                                                                                              • A generator and motorized dewatering equipment operate on site. 
                                                                                                                                                                                                                                                                                                                92 Seattle Street
                                                                                                                                                                                                                                                                                                                  • Project has received a COO.
                                                                                                                                                                                                                                                                                                                  • East ramp repair work is underway and will be completed in August. 
                                                                                                                                                                                                                                                                                                                  • Flooring contractor will mobilize during Harvard’s winter break.
                                                                                                                                                                                                                                                                                                                  • Interior signage is ongoing and a permanent exterior sign will be completed in the near future.
                                                                                                                                                                                                                                                                                                                  210 North Harvard Street
                                                                                                                                                                                                                                                                                                                  • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                                                                                                  • The bakery Sofra is open. 
                                                                                                                                                                                                                                                                                                                  168 Western Ave
                                                                                                                                                                                                                                                                                                                  • National Grid has completed the gas pipe connection and is restoring the sidewalk.
                                                                                                                                                                                                                                                                                                                  • All the Swiss Bakers kitchen equipment from 9 Travis Street to 168 Western has been relocated. 

                                                                                                                                                                                                                                                                                                                  Anthony D'Isidoro

                                                                                                                                                                                                                                                                                                                  unread,
                                                                                                                                                                                                                                                                                                                  Aug 28, 2025, 8:56:32 AM (9 days ago) Aug 28
                                                                                                                                                                                                                                                                                                                  to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                                                                                  ACA: placard theft – a problem – (Jeff Sullivan, The Bulletin: August 28, 2025) 

                                                                                                                                                                                                                                                                                                                  The Allston Civic Association (ACA) met last week and discussed a slew of neighborhood issues and projects after taking the month of July off. 

                                                                                                                                                                                                                                                                                                                  Boston Police Department (BPD) District D-14 Community Service Officer Scott Stenstrom said over the last couple of weeks, there has been a rash of vehicular break-ins where handicap parking placards were stolen at the Boston Housing Authority development on Fidelis Way. 

                                                                                                                                                                                                                                                                                                                  “There were some warrants issued today actually for the arrest of an individual the detectives have identified,” he said. “Hopefully, we’ve put a rest to that, because there were quite a few break-ins where they’re stealing the handicapped placards.” 

                                                                                                                                                                                                                                                                                                                  ACA President Tony D’Isidoro reminded residents to always keep valuable possessions out of sight in their vehicles at the very least or don’t leave them there at all – and always lock your vehicles. Stenstrom said that’s what they recommend at the BPD, but with placards, it’s kind of a Catch 22.

                                                                                                                                                                                                                                                                                                                  “With placards, it’s tough because you need one to park where you’re parking, and parking is tight at Fidelis and you can’t really tell someone not to display it,” he said. “Unfortunately, people are taking advantage of that situation and they’re smashing windows and grabbing placards. Hope fully, we have that person in our custody and that will come to an end.” 

                                                                                                                                                                                                                                                                                                                  In other news, Boston Zero Waste Program Outreach and Communications Coordinator Hannah Mermin stopped by to lay out what the program is doing in the city and how it can specifically help Allston Brighton residents. 

                                                                                                                                                                                                                                                                                                                  Readers may be familiar with Allston’s recent modification from its ‘Allston Rock City’ moniker, as it has changed, at least to some, to ‘Allston Rat City.’

                                                                                                                                                                                                                                                                                                                  One of the biggest issues for rats, as Boston Environmental Services Assistant Commissioner John Ulrich has said time and time again, is their food source. If you can limit their food source you can limit their population and Mermin said the city, as part of its Zero Waste program, is offering residents rat-proof compost and trash bins to eligible residents. 

                                                                                                                                                                                                                                                                                                                  “These bins are rodent-proof, and we’ve tested them when the latch is on,” she said. “Sometimes you may even put a stone on top of the lid to really keep it shut if you have vicious rodents, but I promise they work. Even my parents, who are up in Maine where there are a lot of animals running around, they (the animals) don’t get in.” 

                                                                                                                                                                                                                                                                                                                  Go to BostonComposts.com for more information. 

                                                                                                                                                                                                                                                                                                                  She also pointed to Project Oscar, which allows residents to drop off food waste at several locations in partnership with Black Earth Compost. Residents are allowed to use any of the bins, but there is a code to open them: 2-1-4. Go to https://tinyurl.com/6yw8pp9j for a list of drop-off locations. 

                                                                                                                                                                                                                                                                                                                  Also at the meeting, Allston Village Main Streets (AVMS) Executive Director Alex Cornacchini stopped by to remind residents that the 28th annual Taste of Allston is next month, Sept. 20, at the Jackson Mann Community Center from 12 p.m. to 4 p.m. 

                                                                                                                                                                                                                                                                                                                  “We’re just trying to promote the fact that the Jackson Mann is still around and still doing programs, and we’re super hyped to be working with (Jackson Mann Director) Rosie Hanlon again too,” he said. “We’re also looking for volunteers and a few vendors. If you’re an art vendor, food vendor, retail and you’re interested please reach out to me. We’ve got almost all the slots filled up but we might have some room for some local people.” 

                                                                                                                                                                                                                                                                                                                  The event is free, and for more information go to https://www.tasteofallston.com  

                                                                                                                                                                                                                                                                                                                  In other news, the ACA heard from its new Office of Neighborhood Services (ONS) Liaison for Allston and Brighton, Jennifer Roberts. Roberts said she first moved into Allston and Brighton 10 years ago as a student. 

                                                                                                                                                                                                                                                                                                                  “I moved to Boston after school and I lived in Allston, as many do, and clearly I fell in love with the city because here I am, 10 years later,” she said.

                                                                                                                                                                                                                                                                                                                  The ACA also heard several development projects, listed with links to Boston Planning Department pages if applicable: 

                                                                                                                                                                                                                                                                                                                  170 Western Ave. Jay Walsh came to represent Maggie Lee and Dan Chen of Flint Cleaners for a 19-unit mixed-use development at Flint Cleaners. Lee and Walsh emphasized that Flint Cleaners, which has a history with the neighborhood, will return once construction is complete. 

                                                                                                                                                                                                                                                                                                                  449 Cambridge Street notice of project change to consolidate the project into 445-449 Cambridge St. https://tinyurl.com/2fyxxen5   

                                                                                                                                                                                                                                                                                                                  17 Bradbury St. – Attorney Jeff Drago represented the owner and said the plan is to build a new three-story building with three residential units and three parking spaces. 

                                                                                                                                                                                                                                                                                                                  201 Brighton Ave. mixed-use development with 96 units and 2,667 square feet of retail space. 

                                                                                                                                                                                                                                                                                                                  80 Gardner St. – adding 36 units on the side of an existing 24-unit building https://tinyurl.com/3wkj4sr3  

                                                                                                                                                                                                                                                                                                                  For upcoming ACA meetings, go to http://www.allstoncivicassociation.org/ 

                                                                                                                                                                                                                                                                                                                  Boston Bulletin (August 28, 2025):

                                                                                                                                                                                                                                                                                                                  Anthony D'Isidoro

                                                                                                                                                                                                                                                                                                                  unread,
                                                                                                                                                                                                                                                                                                                  Aug 31, 2025, 8:54:40 AM (6 days ago) Aug 31
                                                                                                                                                                                                                                                                                                                  to cleveland-cir...@googlegroups.com, AllstonBrighton2006, bacommunit...@googlegroups.com
                                                                                                                                                                                                                                                                                                                  Harvard Construction Mitigation (Week of September 2, 2025)   

                                                                                                                                                                                                                                                                                                                  August 29, 2025

                                                                                                                                                                                                                                                                                                                  Kresge Way and Extension of Thermal Pipes and Electrical Duct Bank
                                                                                                                                                                                                                                                                                                                  • Thermal striping in the Harvard Business School lot will take place this fall.
                                                                                                                                                                                                                                                                                                                  Enterprise Research Campus
                                                                                                                                                                                                                                                                                                                  Residential/Hotel
                                                                                                                                                                                                                                                                                                                  Weekend Activities
                                                                                                                                                                                                                                                                                                                  • On Saturday, August 30, many activities will be taking place including paver install near the high-rise residential building. First floor panel installation will be taking place. First floor work will take place in the hotel. Elevator and miscellaneous interior work are ongoing in hotel with punch-list/fit out work in the high-rise building. The hotel will begin placing a first floor topping slab which includes one integrated pumper/concrete truck operating off Trotting Avenue near the loading dock.
                                                                                                                                                                                                                                                                                                                  • On Sunday, August 31, the hotel will have a crew of 25 placing a first floor topping slab which includes one integrated pumper/concrete truck operating off Trotting Avenue near the loading dock. Inside the hotel, two workers will be working in the elevators.
                                                                                                                                                                                                                                                                                                                  • On Monday, September 1, the hotel will have a crew of 25 placing a first floor topping slab which includes one integrated pumper/concrete truck operating off Trotting Avenue near the loading dock.
                                                                                                                                                                                                                                                                                                                  Weekday/Night Activities
                                                                                                                                                                                                                                                                                                                    • Trotting Avenue is open to the public as the midrise and highrise residential buildings (Verra) begin to be occupied.
                                                                                                                                                                                                                                                                                                                    • Crews are scheduled to work during the day and in the evenings at the high-rise, exterior façade from 7 a.m. to 7 p.m. on the ground level at the former hoist area.
                                                                                                                                                                                                                                                                                                                    • Paver activities continue.
                                                                                                                                                                                                                                                                                                                    • Punch list work is finishing in the midrise and continuing in the highrise.
                                                                                                                                                                                                                                                                                                                    • Fitout work continues on level 8 and 13 in the highrise.
                                                                                                                                                                                                                                                                                                                    • Testing and inspections will be ongoing in preparation for a temporary certificate of occupancy in late September in the hotel. Other hotel activities include:
                                                                                                                                                                                                                                                                                                                      • Ground floor work including soffit panel installation using lifts
                                                                                                                                                                                                                                                                                                                      • Elevator installation and start up activity
                                                                                                                                                                                                                                                                                                                      • MEP work
                                                                                                                                                                                                                                                                                                                      • Framing, drywall and bathroom installation
                                                                                                                                                                                                                                                                                                                      • Flooring and painting
                                                                                                                                                                                                                                                                                                                      • Finish, tile and millwork
                                                                                                                                                                                                                                                                                                                      • Punchlist work has begun.
                                                                                                                                                                                                                                                                                                                    Laboratory and Office Buildings
                                                                                                                                                                                                                                                                                                                    Weekend Activities
                                                                                                                                                                                                                                                                                                                    • On Saturday, August 30, no work will take place.
                                                                                                                                                                                                                                                                                                                    • On Sunday, August 31 no work will take place.
                                                                                                                                                                                                                                                                                                                    Weekday Activities
                                                                                                                                                                                                                                                                                                                      • Boom and scissor lifts are active around the perimeter of the buildings.
                                                                                                                                                                                                                                                                                                                      • Level 1 soffit and exterior work is underway.
                                                                                                                                                                                                                                                                                                                      • Smaller concrete operations continue.
                                                                                                                                                                                                                                                                                                                      • Roof and terrace activities including paver install are underway.
                                                                                                                                                                                                                                                                                                                      • Elevators are being installed and inspected.
                                                                                                                                                                                                                                                                                                                      • MEP work is ongoing.
                                                                                                                                                                                                                                                                                                                      • Mechanical penthouse detail activities continue.
                                                                                                                                                                                                                                                                                                                      • Stone masonry work continues.
                                                                                                                                                                                                                                                                                                                      • At Axle Way, irrigation work continues.
                                                                                                                                                                                                                                                                                                                      • Excavation for a bio-cell structure and stone reservoir at Trotting Avenue will take place.
                                                                                                                                                                                                                                                                                                                      • Irrigation and concrete pad placement.
                                                                                                                                                                                                                                                                                                                      • Framing, drywall and bathroom install are underway.
                                                                                                                                                                                                                                                                                                                      • Finish, tile and millwork are ongoing.
                                                                                                                                                                                                                                                                                                                      • Garage work continues.
                                                                                                                                                                                                                                                                                                                      Treehouse Conference Center
                                                                                                                                                                                                                                                                                                                      Weekend Activities
                                                                                                                                                                                                                                                                                                                      • On Saturday, August 30, wood panel and façade installation and some roof activities will take place. Crews will be installing pavers. Interior work includes flooring, ceilings, elevator and miscellaneous work including MEP activity.
                                                                                                                                                                                                                                                                                                                      • On Sunday, August 31, approximately 20 workers including two roofers, façade work and those doing interior elevator, electrical and other miscellaneous work.
                                                                                                                                                                                                                                                                                                                      Weekday/Night Activities
                                                                                                                                                                                                                                                                                                                      • A site crew will be excavating to place stone, shallow utilities and pavers from 5 p.m. to 10 p.m.
                                                                                                                                                                                                                                                                                                                      • Wood trim panels and other façade installation continue two shifts from 7 a.m. to 10 p.m.
                                                                                                                                                                                                                                                                                                                      • Roof detail activities continue.
                                                                                                                                                                                                                                                                                                                      • Elevator work is underway.
                                                                                                                                                                                                                                                                                                                      • MEP activities are ongoing
                                                                                                                                                                                                                                                                                                                      • Building systems start-up, testing and inspections in preparation for temporary certificate of occupancy in late September are underway.
                                                                                                                                                                                                                                                                                                                      • Flooring and ceiling work continues.
                                                                                                                                                                                                                                                                                                                      • Bathroom and kitchen work continues.
                                                                                                                                                                                                                                                                                                                      • Painting is underway.
                                                                                                                                                                                                                                                                                                                      • Finish, tile and mill work are ongoing.
                                                                                                                                                                                                                                                                                                                      • Small concrete placements will take place.
                                                                                                                                                                                                                                                                                                                        Greenway
                                                                                                                                                                                                                                                                                                                        Weekend Activities
                                                                                                                                                                                                                                                                                                                        • On Saturday, August 30, no work will take place. 
                                                                                                                                                                                                                                                                                                                        Weekday Activities
                                                                                                                                                                                                                                                                                                                          • Landscaping crews continue installing pavers at the shared-use path.
                                                                                                                                                                                                                                                                                                                          • Water feature install work continues
                                                                                                                                                                                                                                                                                                                          • Outcropping (boulder)install continues.
                                                                                                                                                                                                                                                                                                                          • Excavating and footing work for bio-swales is underway.
                                                                                                                                                                                                                                                                                                                          Streetscape and Western Avenue
                                                                                                                                                                                                                                                                                                                          Weekend Activities
                                                                                                                                                                                                                                                                                                                          • On Saturday, August 30, no work will take place.  
                                                                                                                                                                                                                                                                                                                           Weekday/night Activities
                                                                                                                                                                                                                                                                                                                          • Crews will be working an extended shift into the night excavating and installing stone reservoirs from 1:45 p.m. to 11:45 p.m. from Tuesday, September 2 to Friday, September 5.
                                                                                                                                                                                                                                                                                                                          • Plant rail, trash receptacle and footings install on Trotting Avenue, north of the loading dock. Also a non-porous paving install will begin Wednesday, September 3 and continue through the week into the following week.
                                                                                                                                                                                                                                                                                                                          • Structural soils install and pipe camera investigation will take place inside the fence along Western Avenue.
                                                                                                                                                                                                                                                                                                                          Building Mock-Ups
                                                                                                                                                                                                                                                                                                                          • Building mockups are on the corner of Hague and Rotterdam Streets.
                                                                                                                                                                                                                                                                                                                          Eversource Conduit Project
                                                                                                                                                                                                                                                                                                                          • Eversource electrical manhole work and splicing continues along Western Avenue and at Trotting Avenue. This public utility work is not under the supervision of ERC.
                                                                                                                                                                                                                                                                                                                          General
                                                                                                                                                                                                                                                                                                                          • The projects work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays/Sundays/off hours as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                                                                                          • Crews, except those highlighted above at the hotel, will be off on Labor Day, Monday, September 1.
                                                                                                                                                                                                                                                                                                                          • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                                                                                                                                                                                                                                                                            • Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                                                                                                                                                                                                                                                                            • Weekly flights are weather dependent and are scheduled one weekday morning.
                                                                                                                                                                                                                                                                                                                            • A drone is scheduled to fly on Thursday, September 4, at 3 p.m.
                                                                                                                                                                                                                                                                                                                          North Allston Storm Drain Extension Project (NASDEP)
                                                                                                                                                                                                                                                                                                                          The NASDEP, a project designed for Boston Water and Sewer Commission (BWSC) to alleviate the existing inundated storm water systems in North Allston, continues with enabling work on the ERC site.
                                                                                                                                                                                                                                                                                                                          • South of Science work between Rena Path and Rotterdam Street will continue this week.
                                                                                                                                                                                                                                                                                                                          • Science Drive is narrowed into fall 2025 with new line striping indicating the lanes. Restoration will take place later in September.
                                                                                                                                                                                                                                                                                                                          • General site cleanup is underway.
                                                                                                                                                                                                                                                                                                                          • Backfilling operations intermittently occur.
                                                                                                                                                                                                                                                                                                                          • A CCTV camera inspection is under review.
                                                                                                                                                                                                                                                                                                                          • The temporary drainage bypass system is operating and will be removed pending camera results.
                                                                                                                                                                                                                                                                                                                          • A generator and motorized dewatering equipment operate on site.
                                                                                                                                                                                                                                                                                                                            92 Seattle Street
                                                                                                                                                                                                                                                                                                                              • Project has received a COO.
                                                                                                                                                                                                                                                                                                                              • East ramp repair work continues.
                                                                                                                                                                                                                                                                                                                              • Flooring contractor will mobilize during winter break.
                                                                                                                                                                                                                                                                                                                              • Installation of the permanent exterior sign will be completed in mid-September.
                                                                                                                                                                                                                                                                                                                              175 North Harvard Street Project Construction
                                                                                                                                                                                                                                                                                                                              The following is an overview of the work taking place at the 175 North Harvard construction site at the future location of the new Harvard University affiliate housing building and American Repertory Theatre (ART):
                                                                                                                                                                                                                                                                                                                              • Exterior swing staging and a scaffolding lift system are set up on the buildings to assist with curtainwall installation and masonry. Scaffolding is going up on the west and north side of the building. Scaffolding is complete inside the courtyard. Some swing staging is being removed this month. Multiple masonry crews are working on all sides of the building and brick deliveries have increased. Brick topping off on the mid-rise and south side is expected mid-September. Brickwork is currently placed up to the 3rd floor. Mechanical, electrical, and plumbing trades continue working on multiple levels. Interior fit outs and framing continues throughout the building. Miscellaneous deliveries to the hoist will continue. Elevator installation remains ongoing in the north tower. Finish work on the lower floors is ongoing. Drywall work continues and dry wall deliveries take place on Tuesdays and Thursdays from 3 p.m. to 6 p.m. and on Saturdays. Interior framing is ongoing. Small utilities inside the site continue. Roofing installation is ongoing. The 14-story roof was finished this week. Window installation continues. Smaller concrete placements continue. Finishes on the lower floors are ongoing. The bike storage room will begin in the fall.
                                                                                                                                                                                                                                                                                                                              • South Campus Drive will be closed to vehicles from 7 a.m. to 4 p.m. on Saturday, August 30, for crane access to install two-story windows along the west elevation. During the week of September 1, South Campus Drive will be closed to vehicles periodically from 7 a.m. to 4 p.m.to provide for crane access to the roof. The road will be open to traffic each day after 5 p.m.
                                                                                                                                                                                                                                                                                                                              • Access to Ivy Lane for the general public and the Continuum, Sloane’s, and Trader Joe’s deliveries will be a priority. If necessary, construction delivery vehicles will be diverted until they can unload in a way that does not impede traffic on Ivy Lane.
                                                                                                                                                                                                                                                                                                                              • When South Campus Drive is closed, all traffic leaving the Continuum and Trader Joe’s parking garage will be instructed to make a right turn only out of the garage. Signage will be provided to divert traffic as needed, and police details will be on site to provide assistance. The signage will be covered after the end of each shift so vehicles can use South Campus Drive.
                                                                                                                                                                                                                                                                                                                              • A light pole has been removed along the walking path adjacent to McCurdy Track along South Campus Drive to provide truck turn radius access for trailers.
                                                                                                                                                                                                                                                                                                                              • Wheel washing and street sweeping continue to ensure soil is not being tracked through the neighborhood streets.
                                                                                                                                                                                                                                                                                                                              • On the new American Repertory Theater (ART) work site, mass timber installation continues along with wood deliveries. Work continues on the front sections of the building closest to North Harvard Street, including the section closest to Ivy Lane and the Continuum. A crane will be relocating to this side of the site to support this work. Mass timber will be finished in the building’s front-facing mid-section by the end of next week. Two of the three back sections are being rendered weather tight. Staging is underway in prep for brick façade work. Roofing is underway on all sections, and will be wrapping up soon on two of the three back sections of the building. Roofing materials are delivered by crane once per week. Additional trades are on site for masonry work, roof level parapet work, and slab on deck pours. Mechanical system work is ongoing with equipment on site. All mechanical, electrical, and plumbing trades are mobilized. Drywall work is taking place. Exterior façade prep work is underway. Staging is up to support the brick façade work. Curtain wall work will begin at the end of the month on the section of the building closest to Harvard’s track.
                                                                                                                                                                                                                                                                                                                              • A police detail is assigned to North Harvard Street/South Campus Drive to help facilitate mass timber trailer deliveries. Wood protection trades and mechanical systems installation continues as mass timber gets installed.
                                                                                                                                                                                                                                                                                                                              • Drones are flying over the site on a bi-weekly basis to capture project progress.
                                                                                                                                                                                                                                                                                                                              • Work will be taking place at the affiliate housing building on Saturdays, August 30, and September 6. A small crew of laborers will be working on Saturday, August 30, with a crane on South Campus Drive to install second story windows along the west side of the building.
                                                                                                                                                                                                                                                                                                                              • Some Saturday work can be expected each week going forward.
                                                                                                                                                                                                                                                                                                                              • A crew at the ART project will NOT be working on Saturday, August 30. Saturday work can be expected through the winter.
                                                                                                                                                                                                                                                                                                                              • There will not be any Sunday work on either job site this week and both sites will be closed for the Labor Day holiday on Monday, September 1.
                                                                                                                                                                                                                                                                                                                              • There is no work currently taking place at the ART building mock-up across North Harvard Street.
                                                                                                                                                                                                                                                                                                                              • The project’s regular work hours are Monday through Friday, 7 a.m. and 6 p.m. and Saturdays as permitted by the City of Boston from 7 a.m. to 6 p.m.
                                                                                                                                                                                                                                                                                                                              • Off-hours water management may be needed for the ART mass timber roofs and structures during and after rain events.
                                                                                                                                                                                                                                                                                                                              210 North Harvard Street
                                                                                                                                                                                                                                                                                                                              • Eversource or Verizon will remove an old pole and power line.
                                                                                                                                                                                                                                                                                                                              • The bakery Sofra is open. 
                                                                                                                                                                                                                                                                                                                              168 Western Ave
                                                                                                                                                                                                                                                                                                                              • Project is substantially complete.
                                                                                                                                                                                                                                                                                                                              • National Grid gas work is complete.
                                                                                                                                                                                                                                                                                                                              • Light roof work will be ongoing.
                                                                                                                                                                                                                                                                                                                              Reply all
                                                                                                                                                                                                                                                                                                                              Reply to author
                                                                                                                                                                                                                                                                                                                              Forward
                                                                                                                                                                                                                                                                                                                              0 new messages