Moving tasks around

18 views
Skip to first unread message

Sarah George

unread,
Feb 23, 2019, 3:53:47 AM2/23/19
to accelo-c...@googlegroups.com
Quick question,

Sometimes I don't finish all the tasks in a milestone or project and need to relocate it to a different milestone/project so that it's not lost, it's just re-assigned to handle later. 

Is there a quick way to do that? For milestones I gather I can change a project plan although that's pretty fiddly... What do you all do?

Thanks!
– Sarah

Jason Rainbird

unread,
Feb 23, 2019, 4:16:36 AM2/23/19
to accelo-c...@googlegroups.com
Hi Sarah,

At the moment it's not possible to relocate Tasks! Feel free to add votes to my suggestion because this is a big bug bear for us. 

It's easy to create tasks and this is the problem. We need to relocate them Tickets or Projects etc.

The only option, is to cancel the task (it's not possible to delete tasks) and then create a new task later on. 


--
You received this message because you are subscribed to the Google Groups "The Accelo Community" group.
To unsubscribe from this group and stop receiving emails from it, send an email to accelo-communi...@googlegroups.com.
To post to this group, send email to accelo-c...@googlegroups.com.
Visit this group at https://groups.google.com/group/accelo-community.
To view this discussion on the web visit https://groups.google.com/d/msgid/accelo-community/CAA4Cr0nm6sp6ZVwOvKV55wnhNXCeEZ-yT-vtmHWNDaMA4wO_Bw%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

Sarah George

unread,
Feb 23, 2019, 4:25:06 AM2/23/19
to accelo-c...@googlegroups.com
Thanks Jason,

I found your suggestion & voted :)  I haven’t been using Accelo long but this one has got me a couple of times already.

– Sarah


Lissa Meade, GRAYBOX

unread,
Feb 25, 2019, 3:00:09 PM2/25/19
to The Accelo Community
I run into this frequently. I found out the hard way years ago that if you move a task out of a milestone, or move a sub-milestone anywhere but laterally, then any associated time entries become detached and are instead logged against the project. Also, if the time has been billed already then they are locked and can't be relocated back to the tasks they came from, which seriously messes with your budget tracking ability.  

There are several ways to deal with this, based on what you need:

If you want to relocate a task or milestone somewhere NOT laterally, such as out of a parent milestone AND there is no time logged against it already then it's easiest to just cancel it or remove it from the project plan and recreate it in a new project plan. If it's staying in the same project plan then it's okay to move it as long as the move doesn't change any other tasks or milestones in the process that have had time logged against them. 

If you want to relocate a task or milestone somewhere NOT laterally, such as out of a parent milestone AND there is time logged against it already then: 
  1. I reduce the budget to the existing task(s) to whatever has already been used and then Complete it.
  2. I create a new task with the remaining budget wherever it needs to go. 
  3. I make a note (in the task description and/or project comments) of what I did and where the budget came from. 
If you just need to keep it off someone's task board and resourcing outlook then you can soon put tasks/milestones/projects on pause, rather than unassigning it and leaving it in an active state. Previously, Pause status didn't do that, but they had us test the new functionality and with a few changes we are able to do it. I'm not sure when this is going to be available for everyone, so keep your eye on the Accelo updates that they email out.  

Make sense?