Backing out incorrect to do entries

34 views
Skip to first unread message

Nancy Pittman

unread,
Aug 22, 2013, 10:41:49 AM8/22/13
to versiono...@googlegroups.com
For a task, a developer accidently entered 1500 left in the to do column instead of 15.  He immediately corrected it , but that number was added to the total number of hours for the sprint and the burndown chart is elevated by 1485.
 
See attachment.
 
Thanks
 
Incorrect To Do.docx

Lindsay Chung

unread,
Aug 23, 2013, 10:09:53 AM8/23/13
to versiono...@googlegroups.com

To fix this, you need to enter -1500 in the same field to counter-balance it.

--
You received this message because you are subscribed to the Google Groups "VersionOne-users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to versionone-use...@googlegroups.com.
To post to this group, send email to versiono...@googlegroups.com.
Visit this group at http://groups.google.com/group/versionone-users.
For more options, visit https://groups.google.com/groups/opt_out.

Click here to report this email as spam.





Capital Access Network, Inc. is the parent company of AdvanceMe, Inc. and NewLogic Business Loans, Inc.
This e-mail is intended as a confidential communication to the named recipient. If you are not the intended recipient, please (1) forward the e-mail back to the sender and (2) delete it from your computer system. Do not print, copy or save any of the information or attachments. The use or disclosure of the information contained herein by a person other than the intended recipient may expose you to legal liability. Thank you for your cooperation.


This message has been scanned for malware by Websense. www.websense.com

Reply all
Reply to author
Forward
0 new messages