Requisition's DateDoc in Unprocessed Document

54 views
Skip to first unread message

Anozi Mada

unread,
Dec 4, 2016, 10:37:02 PM12/4/16
to iDempiere
Right now if you view requisition in unprocessed document, the document date value is taken from M_Requisition.DateRequired instead of M_Requisition.DateDoc. I've created an example in test.idempiere.org, you can search for requisition 900001.
The fix is simply alter the view to use M_Requisition.DateDoc as DateDoc.

Regards,
Anozi Mada

Carlos Antonio Ruiz Gómez

unread,
Dec 6, 2016, 9:40:38 AM12/6/16
to iDempiere

Anozi Mada

unread,
Dec 6, 2016, 10:02:43 PM12/6/16
to iDempiere
Thank you Carlos.