Dear TPAM Community, 

Please take the time to review the repair schedule below from DR Horton. It provides specific unit numbers and dates for upcoming repairs. 

Action Required: 

If your unit is listed in the repair schedule please ensure that your gates are unlocked and that the exterior of your unit is accessible to contractors.

If you own a Nelson unit then your backyard can only be accessed by going through the house. You are required to sign the attached COVID-19 waiver and return it to twhi...@kasdancdlaw.com

All work begins at 8:00 AM. 

Stucco repair and painting (keep gates unlocked):

Unit 1032: December 11, 14, 15, 16, 21, 22

Unit 1044: December 11, 14, 15, 16, 21, 22

Unit 1047: December 11, 14, 15, 16, 21, 22

Unit 1075: December 11, 14, 15, 16, 22, 23

Unit 1076: December 14, 15, 16, 17, 22, 23

Unit 1084: December 14, 15, 16, 17, 22, 23

Unit 1087: December 14, 15, 16, 17, 28, 29

Unit 1088: December 14, 15, 16, 17, 28, 29

Unit 1090: December 15, 16, 17, 18, 28, 29

Unit 1096: December 15, 16, 17, 18, 28, 29

Unit 1105: December 16, 17, 18, 28, 29

Unit 1121: December 15, 16, 17, 18, 28, 29

Unit 1123: December 24, 28, 29, 30, 31

Unit 1124: December 24, 28, 29, 30, 31

Unit 1126: December 24, 28, 29, 30, 31

Unit 1140: December 24, 28, 29, 30, 31

Unit 1142: December 28, 29, 30, 31, January 4, 5

Unit 1148: December 28, 29, 30, January 4, 5

Unit 1156: December 28, 29, 30, January 4, 5

Unit 1179: December 28, 29, 30, January 4, 5

Unit 1188: December 29, 30, 31, January 4, 5

Unit 1192: December 29, 30, 31, January 4, 5

Unit 1195: December 29, 30, 31, January 4, 5

Unit 1198: December 29, 30, 31, January 4, 5, 6

Unit 1232: December 30, 31, January 4, 5, 6

Unit 1234: December 30, 31, January 4, 5, 6

Unit 1235: December 30, 31, January 4, 5, 6

Unit 1237: December 30, 31, January 4, 5, 6, 7

Unit 1272: December 31, January 4, 5, 6, 7

Unit 1283: December 31, January 4, 5, 6, 7

Unit 1284: December 31, January 4, 5, 6, 7

Unit 1297: December 31, January 4, 5, 6, 7

Unit 1300: January 4, 5, 6, 7, 8

Unit 1308: January 4, 5, 6, 7, 8

Unit 1329: January 4, 5, 6, 7, 8

Unit 1340: January 5, 6, 7, 8, 11

Unit 1341: January 5, 6, 7, 8, 11

Unit 1346: January 5, 6, 7, 8, 11

Unit 1347: January 5, 6, 7, 8, 11

Unit 1356: January 6, 7, 8, 11, 12

Unit 1357: January 6, 7, 8, 11, 12

Unit 1369: January 6, 7, 8, 11, 12

Unit 1370: January 6, 7, 8, 11, 12

Unit 1371: January 6, 7, 8, 11, 12

 

AC Electrical Disconnect Boxes

Unit 1091: December 17

Unit 1092: December 17

Unit 1093: December 17

 

Roofs

Building 17 (Units: 1043, 1044, 1045): January 18, 19, 20

Building 48 (Units: 1136, 1137, 1138): January 18, 19, 20

Building 49 (Units: 1139, 1140, 1141): January 20, 21, 22

Building 53 (Units: 1151, 1152, 1153): January 21, 22

Building 56 (Units: 1157, 1158, 1159): January 25, 26, 27

Building 57 (Units: 1160, 1161, 1162): January 25, 26, 27

Building 58 (Units: 1163, 1164, 1165): January 26, 27, 28

Building 61 (Units: 1172, 1173, 1174): January 1/28, 1/29

Building 66 (Units: 1193, 1194, 1195): January 27, 28, 29

Building 79 (Units: 1235, 1236, 1237): December 21, 22, 23

Building 81 (Units: 1241, 1242, 1243): December 21, 22, 23

Building 83 (Units: 1244, 1245, 1246): December 28, 29, 30

Building 88 (Units: 1259, 1260, 1261): December 28, 29, 30

Building 92 (Units: 1171, 1172, 1173): December 30, 31, January 1

Building 97 (Units: 1286, 1287, 1288): December 30, 31, January 1

Building 104 (Units: 1307, 1308, 1309): January 4, 5, 6

Building 108 (Units: 1319, 1320, 1321): January 5, 6, 7

Building 114 (Units: 1337, 1338, 1339): January 6, 7, 8

Building 118 (Units: 1349, 1350, 1351): January 6, 7, 8,

Building 120 (Units: 1355, 1356, 1357): January 11, 12, 13

Building 121 (Units: 1358, 1359, 1360): January 12, 13, 14

Building 123 (Units: 1364, 1365, 1366): January 13, 14, 15

Building 126 (Units: 1373, 1374, 1375): January 13, 14, 15

 

Regards,

 

Community Management

 

manag...@thepalmsatmesa.org

 

www.thepalmsatmesa.org

2020-12-11 - LT Kasdan re second supplemental repair schedule (stucco, roofs, HVAC, SGDs).pdf