8/16/2025 - 12/31/2025: RMNC Air Handler Replacements

1 view
Skip to first unread message

PSU 2FIX

unread,
Jul 29, 2025, 11:49:04 AMJul 29
to impact-notic...@pdx.edu

UPCOMING IMPACT NOTICE

FOR IMMEDIATE DISTRIBUTION
* * Deans, Directors & Department Chairs: Please distribute to your department personnel * *

LOCATION: Richard and Maurine Neuberger Center (RMNC)

DURATION: 8/16/2025 to 12/31/2025

PROJECT INFORMATION: The two main building Air Handling Units (AHU-01 & 02) will be fully replaced as a part of this project. This project will have multiple impacts throughout it's duration that include three crane picks, brief electrical shut downs and impacts to the building's Heating Ventilation and Cooling Systems (HVAC). Future impact notices will be sent out to communicate all project impacts as they come up and in greater detail. Please note as a part of this project temporary HVAC systems will be installed in the building's penthouse so that the building temperatures will stay maintained through out this project. No relocation of building users should be required. Reference the attached diagram for more information.

PROJECT BENEFITS: Replace two aging Air Handler Units that are beyond their useful life. This project should reduce energy costs, make the building's HVAC system more reliable and maintainable.

IMPACT

- General construction noise & vibration shall be anticipated through out the duration of this project, especially for those users located on the 9th floor of the building.

- 08/16 - 09/15: Initial project mobilization & Temporary Heating and Cooling to be installed.

- 09/01 - 10/22: AHU-01 demolition and replacement will occur. (Phase 1). 

- 10/16 - 12/05: AHU-02 demolition and replacement will occur. (Phase 2). 

- 12/05 - 12/31: Final HVAC system tuning and commissioning; project close out activities

ACCESSIBILITY IMPACTS: None

PROJECT COORDINATORS:

NAME PHONE EMAIL
Matt Gall
503-725-6289
m...@pdx.edu
Quinn Soifer
503-725-4316
soi...@pdx.edu



ADDITIONAL INFORMATION:

If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407



--
Work Control Center
Facilities and Property Management
 
202 University Services Building
617 SW Montgomery
Portland, OR 97201
Phone: 503-725-2FIX
Email: 2F...@pdx.edu
 
~FPM creates a superior and vibrant urban campus environment~
---
You received this message because you are subscribed to the Google Groups "Richard and Maurine Neuberger Center Impact Notices" group.
To unsubscribe from this group and stop receiving emails from it, send an email to impact-notices-rmn...@pdx.edu.
To view this discussion visit https://groups.google.com/a/pdx.edu/d/msgid/impact-notices-rmnc-group/CAAKMd_4EYjrMhvn6Fyj2svw2TgSYybrYoK85JXrfiLwmGvf7Jg%40mail.gmail.com.
8/16/2025_Richard and Maurine Neuberger Center (RMNC)

PSU 2FIX

unread,
Sep 2, 2025, 11:29:32 AM (5 days ago) Sep 2
to impact-notic...@pdx.edu

UPCOMING IMPACT NOTICE

FOR IMMEDIATE DISTRIBUTION
* * Deans, Directors & Department Chairs: Please distribute to your department personnel * *

LOCATION: Richard and Maurine Neuberger Center (RMNC)

DURATION: 9/5/2025 to 12/31/2025

PROJECT INFORMATION: UPDATE 8/29/25: The RMNC Air Handling Unit (AHU-01 & 02) Upgrades project start date has been delayed, due the cancellation of a crane pick planned for Saturday 9/6/25. A future impact notice will be sent out to communicate project impacts once the updated schedule is available.

PROJECT BENEFITS: Replace two aging Air Handler Units that are beyond their useful life. This project should reduce energy costs, make the building's HVAC system more reliable and maintainable.

IMPACT

-General construction noise & vibration shall be anticipated through out the duration of this project, especially for those users located on the 9th floor of the building. 

- DATES TBD: Initial project mobilization. 

- DATES TBD: AHU-01 demolition and replacement will occur. (Phase 1).

-10/16 - 12/05: AHU-02 demolition and replacement will occur. (Phase 2). 

-12/05 - 12/31: Final HVAC system tuning and commissioning; project close out activities

ACCESSIBILITY IMPACTS: None

PROJECT COORDINATORS:

NAMEPHONEEMAIL
Matt Gall
503-725-6289
m...@pdx.edu
Quinn Soifer
503-725-4316
soi...@pdx.edu



ADDITIONAL INFORMATION:

If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407

Work Control Center

Facilities and Property Management

202 University Services Building

617 SW Montgomery

Portland, OR 97201

Phone: 503-725-2FIX

Email: 2F...@pdx.edu

Click Here for the Work Control Center Online 


~ Supporting Student Success ~





To view this discussion visit https://groups.google.com/a/pdx.edu/d/msgid/impact-notices-rmnc-group/CAAKMd_7huLQxjqKwNKJdLxzeF3LRmVFKfrOt1wgUvbGN98XRmw%40mail.gmail.com.
Reply all
Reply to author
Forward
0 new messages