3/20/2026 - 4/17/2026: (RMNC) HVAC Interruption for Testing

0 views
Skip to first unread message

PSU 2FIX

unread,
Mar 19, 2026, 3:58:22 PM (14 days ago) Mar 19
to impact-notic...@pdx.edu

UPCOMING IMPACT NOTICE

FOR IMMEDIATE DISTRIBUTION
* * Deans, Directors & Department Chairs: Please distribute to your department personnel * *

LOCATION: Richard and Maurine Neuberger Center (RMNC)

DURATION: 3/20/2026 to 4/17/2026

PROJECT INFORMATION: RMNC Heating Ventilation and Air Conditioning (HVAC) Upgrade Project - Testing and Balancing As part of the RMNC Air Handler Upgrade Project, the building systems will undergo Air System Testing and Balancing to confirm airflows are as designed. Contractor will require approximately two days for each floor, according to the following schedule: 3/20 & 3/23 7th Floor 3/23 - 3/25 3rd Floor 3/25 - 3/26 7th Floor 3/27 & 4/3 8th Floor 3/30 - 3/31 5th Floor 4/1 - 4/2 1st Floor 4/7 - 4/8 2nd Floor 4/8 - 4/9 9th floor 4/10 - 4/17 Punchlist and make-up dates These dates are flexible, if any adjustments are needed to accommodate occupants or events.

PROJECT BENEFITS: Balancing the HVAC system improves system performance and improves occupant comfort.

IMPACT: TAB personnel will need to access ceiling HVAC supply all floor spaces to are used to working in occupied spaces, and accommodating occupant needs would begin in the penthouse and move to the unoccupied 4th floor on Monday/Tuesday can proceed with TAB on each floor in any sequence estimate it will take about a day per floor will only need to be in each room/space about 5 minutes to measure flow would not generally not to get above the ceiling, unless they need to troubleshoot a broken terminal unit box

ACCESSIBILITY IMPACTS: None

PROJECT COORDINATORS:

NAME PHONE EMAIL
Matt Gall
503-725-6289
m...@pdx.edu
Quinn Soifer
503-725-4316
soi...@pdx.edu



ADDITIONAL INFORMATION:

If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407



--
Work Control Center
Facilities and Property Management
 
202 University Services Building
617 SW Montgomery
Portland, OR 97201
Phone: 503-725-2FIX
Email: 2F...@pdx.edu
 
~FPM creates a superior and vibrant urban campus environment~
---
You received this message because you are subscribed to the Google Groups "Richard and Maurine Neuberger Center Impact Notices" group.
To unsubscribe from this group and stop receiving emails from it, send an email to impact-notices-rmn...@pdx.edu.
To view this discussion visit https://groups.google.com/a/pdx.edu/d/msgid/impact-notices-rmnc-group/CAAKMd_4%3DxeWtkYF985B9qziqijbgdTrVRVozWdSkN6MCDy-D%2BQ%40mail.gmail.com.
3/20/2026_Richard and Maurine Neuberger Center (RMNC)

PSU 2FIX

unread,
Mar 19, 2026, 6:38:36 PM (14 days ago) Mar 19
to impact-notic...@pdx.edu
UPDATE: Please see below for updated details and correct formatting. 

UPCOMING IMPACT NOTICE

FOR IMMEDIATE DISTRIBUTION
* * Deans, Directors & Department Chairs: Please distribute to your department personnel * *

LOCATION: Richard and Maurine Neuberger Center (RMNC)

DURATION: 3/20/2026 to 4/17/2026

PROJECT INFORMATION: RMNC Heating Ventilation and Air Conditioning (HVAC) Upgrade Project - Testing and Balancing As part of the RMNC Air Handler Upgrade Project, the building systems will undergo Air System Testing and Balancing to confirm airflows are as designed. Contractor will require approximately two days for each floor, according to the following schedule:

3/20 & 3/23 7th Floor 

3/23 - 3/25 3rd Floor 

3/25 - 3/26 7th Floor 

3/27 & 4/3 8th Floor 

3/30 - 3/31 5th Floor 

4/1 - 4/2 1st Floor 

4/7 - 4/8 2nd Floor 

4/8 - 4/9 9th floor 

4/10 - 4/17 Punchlist and make-up dates 

These dates are flexible, if any adjustments are needed to accommodate occupants or events.

PROJECT BENEFITS: Balancing the HVAC system improves system performance and improves occupant comfort.

IMPACT: TAB personnel will: 

- Need to access ALL ceiling HVAC supply diffusers, but will coordinate exact timing directly with space occupants, to accommodate occupant needs
- Estimate it will take about two days to complete each floor
- Only need to be in each room/space about 5 minutes to measure flow
- Not generally need to get above the ceiling, unless they are troubleshooting a broken terminal unit box


ACCESSIBILITY IMPACTS: None

PROJECT COORDINATORS:

NAMEPHONEEMAIL
Matt Gall
503-725-6289
m...@pdx.edu
Quinn Soifer
503-725-4316
soi...@pdx.edu



ADDITIONAL INFORMATION:

If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407

Work Control Center

Facilities and Property Management

202 University Services Building

617 SW Montgomery

Portland, OR 97201

Phone: 503-725-2FIX

Email: 2F...@pdx.edu

Click Here for the Work Control Center Online 


~ Supporting Student Success ~


To view this discussion visit https://groups.google.com/a/pdx.edu/d/msgid/impact-notices-rmnc-group/CAAKMd_6QNGp-gAHwHpKJh6Vxr_0G2gHwYX4w5yMbAUsA1RxH9g%40mail.gmail.com.
03_20_26_Impact Notice - RMNC Air Handler Replacements - Building-wide Testing and Balancing_REV1.pdf
Reply all
Reply to author
Forward
0 new messages