3/27/2026: LH - Delayed Elevator Service

0 views
Skip to first unread message

PSU 2FIX

unread,
Mar 18, 2026, 7:06:01 PMMar 18
to Impact-Noti...@pdx.edu, accessibility...@pdx.edu, Disability Resource Center

UPCOMING IMPACT NOTICE

FOR IMMEDIATE DISTRIBUTION
* * Deans, Directors & Department Chairs: Please distribute to your department personnel * *

LOCATION: Lincoln Hall (LH)

DURATION: 3/27/2026 from 12:00:00 PM to 4:00:00 PM

PROJECT INFORMATION: Kone Elevator will be on-site to perform the State Required 5 year elevator testing on the following Lincoln Hall elevators: Elevator #25 - testing from 11:00 AM to 1:00 PM Elevator #74 - testing from 1:00 PM to 2:30 PM Elevator #73 - testing from 2:30 PM to 4:00 PM

PROJECT BENEFITS: 5 year state required testing will ensure proper elevator emergency life safety operation.

IMPACT: The elevators will be out of service during the testing duration. There will be no. elevator service to the basement while testing elevator #73. Anticipate some noise from the elevator shaft at each location during the duration of testing.

ACCESSIBILITY IMPACTS: There will be no basement elevator service while testing elevator #73. If ADA access is required during this time, please contact the Work Control Center.

PROJECT COORDINATORS:

NAME PHONE EMAIL
James Kavalec
971-275-7235
kav...@pdx.edu
Tom Jodry
503-523-6860
tom....@kone.com
Work Control Center
503-725-2349
2f...@pdx.edu

ADDITIONAL INFORMATION:

If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407



3/27/2026_Lincoln Hall (LH)