LOCATION: Smith Memorial Student Union (SMSU)
DURATION: 5/29/2026 to 6/3/2026 from 5:00:00 AM to 8:00:00 AM
PROJECT INFORMATION: The SMSU Re-Roof Project will be replacing the existing roof system.
Upcoming construction activities:
Boom truck pick to lift roofing supplies onto the roof.
PROJECT BENEFITS: The new roofing system will provide improved weather protection, enhance the building's energy efficiency, and prevent future water intrusion, ensuring a more comfortable environment for all students and staff.
IMPACT: See attached diagram showing impacts.
The Pedestrian Pathway between SW Park and SW Broadway on the south side of SMSU will be minimized from 5:00AM - 8:00AM. Entrances to Smith Memorial Union will be open per normal operation.
Fourth floor spaces, Suite 433, Rooms 435, 435A, 435B, 437, 438 and Suite 439 located directly underneath the crane landing area will remain closed during lift operations.
ACCESSIBILITY IMPACTS: - Entrances: All entrances remain open, specific exterior pathways or doorways may be temporarily redirected during crane lifts or material delivery.
- Alternative Routes: If a specific pathway or entrance is temporarily closed, directional signage will be posted to the nearest alternative.
PROJECT COORDINATORS:
| NAME | PHONE | |
|---|---|---|
| Anthony Moreschi |
503-725-2837 |
more...@pdx.edu |
| Quinn Soifer |
503-725-4316 |
soi...@pdx.edu |
| |
|
|
ADDITIONAL INFORMATION:
If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407
Work Control Center
Facilities and Property Management
202 University Services Building
617 SW Montgomery
Portland, OR 97201
Phone: 503-725-2FIX
Email: 2F...@pdx.edu
Click Here for the Work Control Center Online
~ Supporting Student Success ~