LOCATION: Blackstone Residence Hall (BLKS), Millar Library (ML), Montgomery Residence Hall (MONT), Simon Benson House (SBH)
DURATION: 6/24/2026 from 7:00:00 AM to 12:00:00 PM
PROJECT INFORMATION: During the morning of Tuesday 6/23/26, concrete trucks will be delivering concrete to the Blackstone site. Vehicles will be staged along Harrison between Park and 10th Ave and will enter and exit via 10th Ave. Cones / delineation will be provided around the staged equipment, and a spotter will assist with guiding equipment to and from the Harrison staging area. See attached map for additional detail.
PROJECT BENEFITS: To support the New Housing Building project.
IMPACT: Impacts will include some vehicle / equipment noise and a narrower pedestrian pathway on Harrison adjacent to Blackstone.
ACCESSIBILITY IMPACTS: The north half of Harrison adjacent to Blackstone will be blocked for vehicle staging. The south side of Harrison will remain open to pedestrians. Montgomery Street can be used as an alternate route if desired.
PROJECT COORDINATORS:
| NAME | PHONE | |
|---|---|---|
| Tom Maki |
(971) 930-0535 |
t...@urbanresourcesinc.com |
| |
|
|
| |
|
|
ADDITIONAL INFORMATION:
If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407
Work Control Center
Facilities and Property Management
202 University Services Building
617 SW Montgomery
Portland, OR 97201
Phone: 503-725-2FIX
Email: 2F...@pdx.edu
Click Here for the Work Control Center Online
LOCATION: Blackstone Residence Hall (BLKS), Millar Library (ML), Montgomery Residence Hall (MONT), Simon Benson House (SBH)
DURATION: 6/25/2026 from 7:00:00 AM to 12:00:00 PM
PROJECT INFORMATION: During the morning of
Thursday 6/25, concrete trucks will be delivering concrete to the Blackstone site. Vehicles will be staged along Harrison between Park and 10th Ave and will enter and exit via 10th Ave. Cones / delineation will be provided around the staged equipment, and a spotter will assist with guiding equipment to and from the Harrison staging area. See attached map for additional detail.
PROJECT BENEFITS: To support the New Housing Building project.
IMPACT: Impacts will include some vehicle / equipment noise and a narrower pedestrian pathway on Harrison adjacent to Blackstone.
ACCESSIBILITY IMPACTS: The north half of Harrison adjacent to Blackstone will be blocked for vehicle staging. The south side of Harrison will remain open to pedestrians. Montgomery Street can be used as an alternate route if desired.
PROJECT COORDINATORS:
| NAME | PHONE | |
|---|---|---|
| Tom Maki | (971) 930-0535 | t...@urbanresourcesinc.com |
ADDITIONAL INFORMATION:
If the above coordinator(s) are unavailable, please contact: 503-725-3738
Emergencies call Campus Public Safety: 503-725-4407
Work Control Center
Facilities and Property Management
202 University Services Building
617 SW Montgomery
Portland, OR 97201
Phone: 503-725-2FIX
Email: 2F...@pdx.edu
Click Here for the Work Control Center Online