Please find attached a reconciliation between DEEP's estimated costs per EDU of $44,416 to our estimated costs of $96,726 for sewers
(The difference of the overall estimate of approximately $132,000 to the $96,726 above is due to the fact that this analysis doesn't include the $25,780 estimated costs for Roads and Stormwater costs and the estimated $10,000 costs to connect)
The primary reasons for the differences are:
- Firstly, with regards to DEEP's presentation of the $44,416 per EDU costs, their analysis did not include operational costs and interest costs. We believe this was an oversight on DEEP's part, as all of the information we have, states clearly that DEEP does in fact include operating costs and interest costs in their assessment of affordability. If the State had properly included those costs, their $44,416 per EDU figure should have been $62,927.
- DEEP's figures included a construction contingency of 10% , and we provided a 23% contingency in our analysis (although our contingency isn't just for project overruns, it also considers a contingency for potential admin and legal costs and hiring a project manager and other variables). We absolutely hope, that we would not have to utilize that full contingency. But it is included, so that if the overruns are above the 10% threshold that the State suggests, that we wouldn't have to go back to homeowners for further bond approval. Also, one of the complaints of previous WPCA analysis was that the WPCA was not being realistic in suggesting that the project will only have a 10% overrun, and that the figure should be closer to 20%, which is routinely used in many construction estimates.
- Our 2025 Bid estimate provides for a 40% increase from the 2021 bids. This 40% comes exactly from the the bid differences that Old Colony, Sound View and the Shared Project received from their 2021 bids, to the bids they received in February 2025. The State only used a 31% difference. We believe our estimate represents the current market. I'm not sure why the State believes our bid will be 9% lower than the bids the other beaches received in February?
- We also include a 5% inflation of the bids. This is for two reasons. The first is that we will be going out to bid in June or July, and we believe the market is not improving, but getting more expensive. Hopefully we are wrong, but it would appear there are signs of increasing costs. Also, two of the bidders on the shared project have stated that they will continue to hold their bids open past the 120 day requirement, but that they are not going to commit that there will not be cost increases on their bids. So out of caution, we are utilizing this 5% for their bids also.
- The three contingencies above, are clearly cautious in nature. If the OLS community believes we are being too cautious and want to vote for a lower bond authorization amount, then that should be brought up in this forum, and in discussions and on May 20th. The dollar value of the additional contingencies we have in our estimates, compared to the State are $3.3 million of the overall bond authorization.
- Also, DEEP suggested that the operating costs would be $450 per year, and we have estimated at $1,192 per year. The major difference in our estimates, is that DEEP has not considered any funding for future capital expenditures on the project. This funding is specifically required in the CSA. The difference here is $2.6 million.
Marty