Roadwork Notice

4 views
Skip to first unread message

Mike Mansir

unread,
Aug 25, 2023, 9:00:10 AM8/25/23
to Public Works at Work for You, Hopkinton Notices

Roadwork Notice Update


Roadwork is scheduled to continue on the following streets. 


Appaloosa Cir 

Ridge Rd 

Breakneck Hill Rd 

Glen Rd- From Lumber St (S) to Breakneck Hill (W) 

Gibbon Rd


Dates are subject to change due to weather conditions.


8/28-9/1 - Adjust structures to grade and adjust sidewalk ramps.

8/30-9/5 - Excavate and install asphalt binder course in cul de sacs and intersections where the cold in place recycling equipment could not do.

9/6-9/8 - Install the top course of asphalt on the full length of each project.


Work hours will be approximately 7a-5p.


Please use caution as all structures will be raised above the existing pavement   1 ½” in preparation for the installation of the surface course of asphalt.


Please expect delays and seek alternate routes when possible.