Roadwork Notice
Roadwork is scheduled for the following streets. Dates are subject to change due to weather conditions.
Work hours will be approximately 7a-5p.
Please do not park in the streets as this will interfere with the scheduled work.
Please expect delays and seek alternate routes when possible.
Tuesday July 1st - Wednesday July 2nd - Lower structures.
Chamberlain St, Angelo Dr, Colella Farm Rd & Nicholas Rd
Monday July 7th - Thursday July 10th - Reclaim & grade.
Chamberlain St
Friday July 11th - Binder course of asphalt.
Chamberlain St
Monday July 14th - Thursday July 17th - Reclaim & grade.
Angelo Dr & Colella Farm Rd
Friday July 18th - Binder course of asphalt.
Angelo Dr & Colella Farm Rd
Monday July 21st - Adjust structures.
Chamberlain St, Angelo Dr & Colella Farm Rd
Monday July 21st - Thursday July 24th - Reclaim & grade
Nicholas Rd
Friday July 25th - Binder Course of asphalt
Nicholas Rd
Monday July 28th - Thursday July 31st - Reclaim & grade
Whalen Rd
Monday July 28th - Thursday July 31st - ADA sidewalk ramps
Colella Farm Rd & Nicholas Rd