I-25 North Express Lanes Project Newsletter
|
|
Construction impacts for the week of
March 23, 2025
|
|
|
Mead to Berthoud
The speed limit on the project has been lowered to 65 mph. Please obey speed limit signs.
Monday through Saturday, 7 a.m. to 5 p.m., Weld County Road 38, west of I-25, will have brief intermittent closures, controlled by flaggers, to allow truck access for dirt hauling.
Wednesday, 9 p.m. to 5 a.m., there will be a southbound I-25 full closure under Weld County Road 34 for bridge deck panel installation. In addition, the following closures will be in place:
- Eastbound and westbound WCR 34 over I-25
- E. Frontage Road at I-25, north of WCR 34
- Northbound I-25 left lane, under WCR 34
- Northbound I-25 off-ramp to WCR 34
Detours will be in place:
- Southbound I-25 traffic will be rerouted using the off- and on-ramps at WCR 34, and northbound I-25 will have a left lane closure. No turning movements will be allowed on or off WCR 34 during this time.
- Eastbound WCR 34 traffic will turn south on County Road 7, turn east on Colorado Highway 66, and turn north on Colorado Boulevard to WCR 34.
- Westbound WCR 34 traffic will turn south on Colorado Boulevard, turn west on CO 66, and turn north on CR 7 to WCR 34.
- Southbound E. Frontage Road traffic will turn east on Weld County Road 36, turn south on Colorado Boulevard, and turn west on Weld County Road 32 to the E. Frontage Road.
- Northbound E. Frontage Road traffic will turn east on WCR 32, turn north on Colorado Boulevard, and turn west on WCR 36 to the E. Frontage Road.
- For I-25 access to WCR 34, traffic will be directed to the I-25 and CO 66 interchange and follow other routes to the east or west.
Thursday, 9 p.m. to 5 a.m., the northbound I-25 right lane and off-ramp to WCR 34 will be closed for bridge deck panel installation.
- Traffic will continue north to Colorado Highway 56, turn around and enter southbound I-25 at WCR 34.
Friday at 9 p.m. through Saturday at 9 p.m., the southbound I-25 on-ramp from WCR 34 will be closed for pipe installation and asphalt work.
- Traffic on WCR 34 intending to travel south will turn north to CO 56, turn around and enter southbound I-25.
|
|
|
Additional Closures:
Due to supplier issues, the temporary closure of Valley Road under I-25 has been rescheduled to start on Monday, March 31 at 9 p.m. This ongoing closure, in place through summer 2025, will allow crews to install bridge girders over the road on Monday and Tuesday night and perform additional work to reconstruct the bridge. Motorists should plan accordingly as no detour route is available.
The temporary closure of Weld County Road 32 under I-25, east of Mead, has also been rescheduled to April 2 - 5, 7 and 8, 7 a.m. to 5 p.m., to allow crews to install new bridge girders over the roadway.
- Westbound WCR 32 traffic will take the East I-25 Frontage Road south to Mulligan Street, turn east to County Road 9.5, turn south to CO 66, turn west to Weld County Road 7, and turn north to WCR 32.
- Eastbound WCR 32 traffic will take WCR 7 south to CO 66, turn east to WCR 9.5, and turn north to WCR 32.
Southbound I-25 traffic shifted to the northbound lanes between CO 56 and Colorado Highway 66 into a head-to-head configuration and will be in place through 2025.
Approximately one mile of the southbound I-25 Express Lane, between mile points 251 and 250, from approximately Weld County Road 44 to Weld County Road 46, is closed through late 2027.
|
|
Construction on I-25 North Express Lanes: Mead to Berthoud
The project team recorded a presentation video with general project information, including schedule, scope, travel impacts, ways to connect with the project and more!
Community members are encouraged to watch the presentation video and submit any feedback or questions to the project team at northi25ex...@gmail.com.
|
|
Berthoud to Johnstown
No major traffic impacts this week.
|
|
Johnstown to Fort Collins
Segments 6, 7 and 8 have reached substantial completion and will have no further closures at this time.
|
|
Additional Information
For specific lane closures and traffic impacts from Sunday, March 23 - Saturday, March 29, please use this interactive map on the project webpage. To display full details on the traffic impacts, please click on any of the color-shaded areas on the map to see the full details. A pop-up on the left side of your screen will outline the details of the lane closures.
Construction activities are weather-dependent and subject to change. Please watch for construction vehicles entering and exiting mainline I-25 and obey all posted signage in construction zones. Your safety and the safety of our crews is our highest priority.
The I-25 North Express Lanes Project provides a Courtesy Patrol during commute hours (6 to 9 a.m. and 3:30 to 6:30 p.m.) to assist with disabled vehicles within the Project limits from Johnstown to Fort Collins.
|
|
About the Project
Communities along the I-25 North corridor are expanding rapidly, contributing to major economic growth in northern Colorado. The Colorado Department of Transportation is supporting this growth by delivering the expansion of I-25 North. Improvements are currently underway along I-25 between Berthoud and Fort Collins (with more to come from Mead to Berthoud).
This project brings economic, environmental and quality of life benefits for northern Coloradans by:
- Making safety improvements to reduce the number of crashes and fatalities.
- Decreasing travel time and increasing trip reliability.
- Reducing emissions and improving freight efficiency.
- Improve congestion and safety.
- Rebuilding aging and obsolete infrastructure.
- Improving bicycle, pedestrian and transit connectivity.
|
|
|
|
Copyright © 2023 Colorado Department of Transportation, All rights reserved.
Our mailing address is:
Colorado Department of Transportation
2829 W Howard Pl
Denver, CO 80204-2305
You are receiving this email because you requested information regarding construction updates for the I-25 North Express Lanes Project. Update your preferences or unsubscribe from this list.
|
|
|
|
|