Here's info on the US 29 interchnages to be built:
(from
Maryland Department of Transportation
Consolidated Transportation Program
FY 2002-2007

)

They don't tell what kind of interchanges but I'd suspect that they'll be
diamonds or maybe parclos. Who knows they're may even be roundabouts in
these interchanges.

US 29 @ Randolph/Cherry Hill Road :

Final Engineering and Right-of-way underway. Construction of a detour road
around the
intersection to provide for future utility relocations is underway.

DAILY TRAFFIC : (USAGE IMPACTS)

CURRENT (2000) -

60,000

PROJECTED (2025) -

97,650

According to the construction funding this project will be finished some
time in 2005

//

US 29 @ Briggs Chaney Road:

It sounds like Briggs Chaney will go over US 29.

STATUS:

Final Engineering underway. Right-of-way to begin during current fiscal
year.

DAILY TRAFFIC : (USAGE IMPACTS)

CURRENT (2000) -

58,000

PROJECTED (2025) -

95,450

Construction is set to start in 2004 and be complete 2007+.

//

US 29 @ MD 198:

STATUS:

Final Engineering and Right-of-way underway. Construction to begin during
budget fiscal

year.

DAILY TRAFFIC : (USAGE IMPACTS)

CURRENT (2000) -

49,500

PROJECTED (2025) -

92,200

Construction to be finished in 2006. US 29 will be relocated to the east
from just south of MD 198 to just north of Dustin Road. A partial
interchange will be constructed at Dustin Road. Also it said:

Direct bus service ramps to and from the Burtonsville Park and Ride Lot will
be included.

And here are the four others:

Study to construct interchanges at Stewart Lane, Tech Road,
Musgrove/Fairland

Road, Greencastle Road and Blackburn Road.

Final engineering is underway and there is funding for ROW but not
construction.

And as for Howard county:

US 29 @ Johns Hopkins / Gorman Roads interchange:

STATUS:

Right-of-way and construction underway.

DAILY TRAFFIC : (USAGE IMPACTS)

CURRENT (2000) -

100,000 (US 29)

15,800 (Hopkins/Gorman)

PROJECTED (2025) -

134,000 (US 29)

39,000 (Hopkins/Gorman)

This is to be completed next year.

Brian Polidoro

--
Index of My Road Related Sites - http://mahn0.tripod.com


-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=
*** Usenet.com - The #1 Usenet Newsgroup Service on The Planet! ***
http://www.usenet.com
Unlimited Download - 19 Seperate Servers - 90,000 groups - Uncensored
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=

0 new messages