Assigning Tasks from Template to Existing Story

36 views
Skip to first unread message

christo...@mcafee.com

unread,
Feb 14, 2012, 5:58:33 AM2/14/12
to VersionOne-users
Hi,

is there some smart way of assigning tasks from a story template to an
existing story? E.g. I want to assign common standard tasks to a
story, but not when creating it, but rather at the time the story is
selected into an iteration backlog. I'm currently using "Plan Story" -
> "Copy Tasks and Tests" and copy the tasks from the template to the
story, which doesn't feel like the most efficient way one can imagine
for this...

Thanks, Christoph



Wortman, Bret D.

unread,
Feb 14, 2012, 7:24:27 AM2/14/12
to versiono...@googlegroups.com
Actually, the appropriate time to plan the story _is_ when it's brought into the iteration backlog. Prior to that, it should be groomed as a story and sliced more thinly rather than broken into tasks.


Bret

Hi,

Thanks, Christoph

--
You received this message because you are subscribed to the Google Groups "VersionOne-users" group.
To post to this group, send email to versiono...@googlegroups.com.
To unsubscribe from this group, send email to versionone-use...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/versionone-users?hl=en.

Luanne

unread,
Feb 14, 2012, 11:41:53 AM2/14/12
to VersionOne-users
There are 2 uses of Templates

- Generating Stories/Backlog items (which includes the tasks/tests)
- Copying tasks/tests during planning from the "Plan Story/Backlog
Item" option

There really is no harm in having the tasks there ahead of time...you
can remove the ones you dont' need and add the unique ones during
planning.

If that still doesn't sit well with you then make 2 templates: 1 to
generate stories from and 1 to copy tasks from

-Luanne