On Tue, 18 Jun 2013 14:08:30 +0100, The Natural Philosopher
The information IS correct. Elexon was "National Grid Settlements" for a
number of years, it is now operated at arms length.
The live data they have for generation and transfers is supplied to them by
National Grid with an accuracy of 0.1% Submissions for generation and
interconnector availability are from the generation or interconnector operator
and are submitted electronically.
The common pool of data is supplied back to National Grid and selected parts of
the data are supplied back to generation and interconnector operators.
You fail to understand that a connection to the grid made be made but the
generation may not generate for some time after the date of that connection.
>> As far as the London array there was a peak of around 120MW last Friday on each
>> of the four blocks, so around 480MW of a possible 628MW
>
>Says who?
bmreports
The information is in there for every single generating unit that has
operational metering dating back to 2008
The London array, or at least part of it connected to the grid under reference
T_LARYW-1 first generated and exported to the grid at around 18:00 on the 4th
January 2013 (initially 25MW peaking to 35MW at 21:00)
>And where did it go to?
It's an infinite bus. No one knows.
>>> Last time I looked I found no actual story saying 'yay! london array is
>>> working'
>>>
>>> And they don't normally miss an opportunity...
>>> #
>>> Their web site says
>>> "The project should be fully operational by Spring 2013."
>>>
>>> And yet its been in the elexon spreadsheet for over six months. As
>>> available capacity.
>>>
>>> I rest my case.
>> Generation is entered in the various spreadsheets at the point at which a
>> connection is made and power, either import or export can occur (for instance
>> conventional generation will be declared yet may not generate anything for an
>> extended period of time, purely taking an infeed for commissioning purposes) A
>> couple of GW of CCGT generation is currently in exactly that position and will
>> not generate commercially for another 5 months or so.
>Well in which case its a moot point as to whether or not BM reports
>should be quoting it as 'available' on their site.
They are not quoting it as being available. The figure listed for wind
generation is the sum total of all generation for which operational metering is
in place. That is made very clear. The declaration of actual maximum
availability is submitted by the same mechanism as any other generation
operator. It appears in the individual BM Reporting unit data after the data
has become historic and for advance notification, as a combined total by fuel
type in the "2 - 14 days and 2 - 52 weeks Output Usable By Fuel Type"
>But if you want to say that there is 7GW plus of available capacity on
>the grid from metered wind farms, be my guest. The fact is that in
>reality it has never ever, even on high wind days generated more than....
There is connection capacity provided for 7136MW, and I would not expect the
output to reflect that, it doesn't for any other fuel type. You only need to see
the wind entry for 2 - 14 days and 2 - 52 weeks Output Usable By Fuel Type to
see that. For wind it currently doesn't even reach 7GW 52 weeks hence but a few
weeks / months from now you might see vastly different figures.
>mysql> select max(wind) from day;
>+-----------+
>| max(wind) |
>+-----------+
>| 5304 |
>+-----------+
>
>5.3GW. Ever. Even with the best possible wind conditions.
>
>So wind is even shittier than we thought.
>
>>
You fail to understand that a connection does not mean 100% availability for
generation (and this applies to all plant types not just wind)
5304MW generated from a declared availability of 5877MW seems somewhere about
right in near ideal conditions. The maximum amount of wind generation able to
be connected to the grid, given section 36 consent under the electricity act
1990, and equipped with operational metering, IS EXACTLY 7136MW. 1GW of it
might be still in the factory or on a barge, 0.5GW of it might be undergoing
mechanical tests on site, the rest might be broken, or with a flock of seagulls
perched on a blade, or on fire.
It is not possible for anyone other than the grid system operator to determine
availability in real time (obviously an operator of generation knows their own
availability) You can get a feel for the situation two days in advance but
current day figures are not available nor those at the time of gate closure.
Historically you can look at the individual notifications on a per unit basis
and the balancing actions.
I explained it to you in basic terms and you still don't seem to be able to
understand the concept. Perhaps this 'real life' (gas) scenario may help.
Day 0 600MW of CCGT capacity is given consent by DECC
Day 1 -> Day 300 A new overhead line and 400kV substation is built.
Day 1 Construction of the new CCGT commences on site
Day 300 A physical connection to the grid is made
Day 300 Operational Metering is enabled
Day 300 Plant appears on bmreports
Day 300 Plant appears on displays at National Control
Day 301 Generator HV circuit breaker closed and the generator transformer is
back energised
Day 302 a backfeed of 1MW continuous is taken
Day 350 There are peaks of 10MW five times a day as large auxiliary plant is
energised
Day 410 Load tests commence at all power levels from 0 - 600MW
Day 449 Commissioning complete
Day 450 Generating plant handed over to operator, money changes hands
Day 450 Commercial load commences
Day 450 Generator output appears in sum total of availability for that plant
type on bmreports
Day 450 -> Submissions by the operator to the grid system operator (via elexon)
are made for generating capacity at 600MW
Day 451 at 0801 a cooling pump fails and will be out of service for 30 days
A resubmitted generating capacity limit is made as 500MW starting at settlement
period 16 on day 451 and continuing for 30 days.
The overall maximum output of the plant doesn't permanently change
The figure in the "2-14 Days Ahead Output Usable By Fuel Type (graph)" reflects
this temporary reduced capacity of 500MW
If the CCGT was the only one on the system then the figure in "Generation By
Fuel Type (table)" will be 500MW
The figure in bmreports for that particular unit shows a reduced figure for the
settlement period concerned and will continue to do so until after the
generation availability is redeclared.
The figure in the spreadsheet* associated with the BM reporting unit will always
remain as 600MW unless there is a permanent redeclaration (i.e the plant stops
CCGT operation and goes Open cycle on say one GT at a reduced output of 200MW)
* The only thing you won't find in the 'public' area of bmreports is the
conventional and nuclear plant equivalent of the wind spreadsheet - it's a
restricted document.
--