Free PMP Exam Sample Question

10 views
Skip to first unread message

The PM Podcast™

unread,
May 12, 2012, 4:19:33 AM5/12/12
to Enterprise-Pro...@googlegroups.com, Gabl...@googlegroups.com, International-Pr...@googlegroups.com, pmi...@googlegroups.com, PMI-...@googlegroups.com, PMI-PCC-Ref...@googlegroups.com, PMI...@googlegroups.com, PMI...@googlegroups.com, PMP-...@googlegroups.com, PMP-Pre...@googlegroups.com, PMP_...@googlegroups.com, PMP...@googlegroups.com, PMPI...@googlegroups.com, PMPL...@googlegroups.com, pm...@googlegroups.com, Project-M...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Manageme...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Management-Practices-T...@googlegroups.com, Project-Manage...@googlegroups.com, project-...@googlegroups.com, ProjectM...@googlegroups.com, Proje...@googlegroups.com, proj...@googlegroups.com, rochelle...@osp-international.com, Software-Proj...@googlegroups.com, TeamPM...@googlegroups.com, vn...@googlegroups.com
Hi All,

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

The type, quantities and assumptions made in determining the resources, basis of estimate for each resource, and availability of resources for each activity or work package is identified in which of the following documents?

A.) Resource Breakdown Structure
B.) Responsibility Assignment Matrix
C.) Resource Calendars
D.) Activity Resource Requirements

------------------------------
Hint: Carefully read the question. The question is asking for assumptions made in determining the resources, as well as the basis of estimates. This happens in the Estimate Activity Resources process. Think about the outputs of this process.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: The type, quantities and assumptions made in determining the resources, basis of estimate for each resource, and availability of resources for each activity or work package is identified in the Estimate Activity Resources process. Resource Calendars identify only type, quantity, availability, and capabilities of resources.
Reference: PMBOK Guide 4th Edition, page 145

The PM Podcast™

unread,
May 18, 2012, 9:07:07 PM5/18/12
to Enterprise-Pro...@googlegroups.com, Gabl...@googlegroups.com, International-Pr...@googlegroups.com, pmi...@googlegroups.com, PMI-...@googlegroups.com, PMI-PCC-Ref...@googlegroups.com, PMI...@googlegroups.com, PMI...@googlegroups.com, PMP-...@googlegroups.com, PMP-Pre...@googlegroups.com, PMP_...@googlegroups.com, PMP...@googlegroups.com, PMPI...@googlegroups.com, PMPL...@googlegroups.com, pm...@googlegroups.com, Project-M...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Manageme...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Management-Practices-T...@googlegroups.com, Project-Manage...@googlegroups.com, project-...@googlegroups.com, ProjectM...@googlegroups.com, Proje...@googlegroups.com, proj...@googlegroups.com, rochelle...@osp-international.com, Software-Proj...@googlegroups.com, TeamPM...@googlegroups.com, vn...@googlegroups.com
Hi All,

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

You are developing your IT development project team. Some of the team members need training on the latest software that you are using in your project. Which of the following documents is most useful to find out the information regarding the scheduled training for the team members?

A.) Project Staff Assignments
B.) Training Management Plan
C.) Staffing Management Plan
D.) Human Resource Plan

------------------------------
Hint: Training needs are developed during the early stages of planning.

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: The Human Resource Plan is used to document details about training and training schedules.
Reference: PMBOK Guide 4th Edition, pages 218, 232

Reply all
Reply to author
Forward
0 new messages