to Enterprise-Pro...@googlegroups.com, Gabl...@googlegroups.com, International-Pr...@googlegroups.com, pmi...@googlegroups.com, PMI-...@googlegroups.com, PMI-PCC-Ref...@googlegroups.com, PMI...@googlegroups.com, PMI...@googlegroups.com, PMP-...@googlegroups.com, PMP-Pre...@googlegroups.com, PMP_...@googlegroups.com, PMP...@googlegroups.com, PMPI...@googlegroups.com, PMPL...@googlegroups.com, pm...@googlegroups.com, Project-M...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Manageme...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Management-Practices-T...@googlegroups.com, Project-Manage...@googlegroups.com, project-...@googlegroups.com, ProjectM...@googlegroups.com, Proje...@googlegroups.com, proj...@googlegroups.com, rochelle...@osp-international.com, Software-Proj...@googlegroups.com, TeamPM...@googlegroups.com, vn...@googlegroups.com
Hi All,

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

Project Integration Management consists of all of the following activities except?

A.) Develop Project Charter
B.) Develop Project Management Plan
C.) Perform Integrated Change Control
D.) Collect Requirements

------------------------------
Hint: Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate various processes and activities.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com

ANSWER AND EXPLANATION:
The correct answer is D
Explanation: Collect Requirements is not a process in Project Integration Management. This process is contained in Project Scope Management.
Reference: PMBOK Guide 4th Edition, page 71