Perform Integrated Change Control question

157 views
Skip to first unread message

Sherif

unread,
Feb 29, 2012, 8:57:32 AM2/29/12
to PMP Cert Online Study Group
Which of the following is NOT an output of Perform Integrated Change
Control?
a. Approved change requests
b. Rejected change requests
c. Validated defect repair
d. Recommended change requests

My answer : B but the right is : D , i doubt the D answer , am i
right ?

Thanks
Sherif

Sri

unread,
Feb 29, 2012, 1:58:18 PM2/29/12
to pmp-cert-onli...@googlegroups.com
D is the correct Answer. 

Varun Paliwal

unread,
Feb 29, 2012, 12:48:59 PM2/29/12
to pmp-cert-onli...@googlegroups.com
Hi,
 
As far as my understanding goes, the answer should be 'd', i.e. 'Recommended change requests' because 'Perform Integrated Change Control' process should tell about both approved as well as rejected change requests and 'Recommended change requests' doesn't seems to be a status (e.g.: approved/rejected) to be updated in 'change request log'.
 
Regards,
Varun
 
Sherif

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.


Imran Khan

unread,
Feb 29, 2012, 12:23:11 PM2/29/12
to pmp-cert-onli...@googlegroups.com

ANSWER D

Mira Kaul

unread,
Feb 29, 2012, 11:18:09 AM2/29/12
to pmp-cert-onli...@googlegroups.com
Hello,

The right answer is D and can't be B.

As part of the the Change control process, the change request could either be approved, rejected,expedited and validated for the requested change . Change Control Board ( CAB) will not recommend the change requests but approve / reject / validate it. Hence its D.

Thanks


--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.




--
~Mira

Jayabharath Rajadurai

unread,
Feb 29, 2012, 10:50:02 PM2/29/12
to pmp-cert-onli...@googlegroups.com

approving, rejecting and recommending are part of integrated change control. Validating the defect repair would be part of the quality control.

Jb

Sagar

unread,
Feb 29, 2012, 11:18:09 PM2/29/12
to pmp-cert-onli...@googlegroups.com
The correct Answer is 
C. Validated Defect Repair

Validated defect repair is a part of Quality Control process.

-Sagar,PMP

Varun Paliwal

unread,
Mar 1, 2012, 2:53:20 AM3/1/12
to pmp-cert-onli...@googlegroups.com
I guess, Perform Integrated Change Control provides:

Approved preventive action
Approved corrective action
Approved defect repair
Validated defect repair
Non-approved change requests
Updates of Project Management Plan
 
 
 
"Integrated Change Control – It is performed from project inception thru completion. Here all recommendations for changes, CA, PA and defect repairs are evaluated and either approved or rejected. It includes:
  1. Identifying that a change needs to occur or has occurred
  2. Make sure only approved changes are implemented
  3. Reviewing and approving requested changes
  4. Managing approved changes as and when they occur and regulating them
  5. Maintain integrity of baseline
  6. Review and approve all recommended corrective and preventive actions
  7. Controlling and updating scope, cost, budget, schedule and quality
  8. Documenting impact of requested changes
  9. Validating defect repair"
Regards,
Varun
 
 

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.

Ramesh Kasthuri Rangan, PMP

unread,
Mar 1, 2012, 3:21:58 AM3/1/12
to pmp-cert-onli...@googlegroups.com
Varun

The key word here is "validated" which means quality control. Check output of Perform quality control PMBOK "Validated Changes" 
where the change can be a defect repair. So, there is no validation of defect repair under integrated change control.
The correct answer is C. 

Integrated change control only approves/rejects change requests or may itself result in change request.
--
Regards
Ramesh PMP®

Ramesh Kasthuri Rangan, PMP

unread,
Mar 1, 2012, 3:29:46 AM3/1/12
to pmp-cert-onli...@googlegroups.com
Only approved requests are validated but input to ICC process are only recommended changes. Its not meaningful to have a validated changes as output.
Whereas all approved requests need to be implemented (project execution) but before such an implementation it should be validated and that happens in QC. Whose output goes for implementation. Only proper understanding of entire process flow will help in tricky questions.

Always think if its validation it most likely talking about QC.

On Thu, Mar 1, 2012 at 1:23 PM, Varun Paliwal <paliwa...@gmail.com> wrote:



--
Regards
Ramesh PMP®

Arash Zaree

unread,
Mar 1, 2012, 9:18:50 AM3/1/12
to pmp-cert-onli...@googlegroups.com
Correct Answer is D. Cause we don't have an expersion like Recommended Change Request. we Have recommended change that can be corrective or preventive action. 

Varun Paliwal

unread,
Mar 1, 2012, 8:06:00 AM3/1/12
to pmp-cert-onli...@googlegroups.com
I second you Ramesh, thanks for clearing the doubt.
 
Regards,
Varun

330.gif

Imran Khan

unread,
Mar 1, 2012, 7:57:04 PM3/1/12
to pmp-cert-onli...@googlegroups.com

Please post the correct answer sherif !!!

Ramesh Kasthuri Rangan, PMP

unread,
Mar 1, 2012, 10:40:31 PM3/1/12
to pmp-cert-onli...@googlegroups.com
Arash,

Change request mean Recommended Change Request (output). Do not look for exact word "recommended" change request you will not find it.
Read Rita's book, you will better understanding. If you simply memorize the words as in PMBOK it wont help. You need to understand.
Do not look for exact words as in PMBOK (for ITTO), you may not get it. Unless you understand each term, you will get the question wrong.
Memorizing entire PMBOK wont even help.

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.

To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.



--
Regards
Ramesh PMP®

Pranav Sheth

unread,
Mar 1, 2012, 10:51:16 PM3/1/12
to pmp-cert-onli...@googlegroups.com
Answer is "D". Because "validated" is trick word. It indicates to QC. Because in Perform Integrated Change Control, change request never be recommended.
Varun has explained in good way.
100% sure answer is "D".

Regards,
Pranav, PMP.
Thanks and Best Regards,
Pranav Sheth.

Satish Singh

unread,
Mar 1, 2012, 11:46:12 PM3/1/12
to pmp-cert-onli...@googlegroups.com
CORRECT ANSWER IS : d. Recommended change requests 

- a,b and c are the output of  Perform Integrated Change 


Sherif

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.




--
"Excellence is not a skill. it is an attitude"


Regards,
Satish.


Sherif

unread,
Mar 3, 2012, 3:33:16 AM3/3/12
to pmp-cert-onli...@googlegroups.com
Thanks ,For clearing my doubts  