Re: Answers for these

224 views
Skip to first unread message

Sukhdev Singh

unread,
May 19, 2013, 11:05:25 PM5/19/13
to pmp-cert-onli...@googlegroups.com
apply PERT(EAD)------(P+4xM+O)/6   comes upto 12days


On Sun, May 19, 2013 at 4:02 PM, Shanti <bsha...@gmail.com> wrote:
found these questions. guess the answers..
 
 

James has been managing a hotel construction project in a busy street. He is in the process of estimating

activity durations for building walls and calculates the Expected activity duration as 14 days. If pre-fabricated

material is used, it would take no more than 12 days to finish the work. However, the work may be delayed

and could take up to 18 days if less experienced construction workers are used to build the walls. But, the

engineer in-charge of the work estimates the duration as 8 days when pre-fabricated material is used. What

is the most likely estimate, if the engineer's estimation is

assumed correct?

a. 12 days

b. 11 days

c. 15 days

d. 14 days

 

whats the answer.

 

Rodney is in the process of preparing the project performance report for the team meeting. He is expecting

many questions from his stakeholders on the budget and schedule. He calculates the following values;

Budget at Completion (BAC) = $22,000, Earned Value (EV) = $13000, Planned Value (PV) = $ 14000, Actual

cost (AC) = $15000. What is the Estimate at Completion (EAC) for the project if the work is performed at the

budgeted rate?

a. $24000

b. $36000

c. $22500

d. $37000

 

Whats the answer for this too..

 

 

 

 

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to pmp-cert-online-stu...@googlegroups.com.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
Visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

Sukhdev Singh

unread,
May 19, 2013, 11:10:08 PM5/19/13
to pmp-cert-onli...@googlegroups.com
For EAC budgeted Rate Apply EAC=AC+BAC-EV comes upto $24000

Shanti Narayanan

unread,
May 21, 2013, 12:56:40 PM5/21/13
to pmp-cert-onli...@googlegroups.com
Hi,
 
Thanks manickavel.
 
Question 2 answer is $24000
 
Question 1 answer is 15 days
 
Te 14 days To 8 days Tp 18 days
4Tm =(6Te-To-Tp) = (84-8-18)=58
Tm=15 days.(14.5 days)

On Tue, May 21, 2013 at 8:30 AM, Manickavel A, PMP <manic...@gmail.com> wrote:
For Question No. 2, the answer is: EAC=AC+BAC-EV = $24000.

For a detailed explanation on EAC calculations, you can refer to http://www.justgetpmp.com/2013/04/doubt-in-estimate-at-completion-eac.html



--
Thanks,
Shanti

Shelly C

unread,
May 24, 2013, 12:21:45 PM5/24/13
to pmp-cert-onli...@googlegroups.com
hello, answer anyone?


On Wed, May 22, 2013 at 10:50 AM, Shelly C <shel...@gmail.com> wrote:
Hello All,
What do you think is the answer to this question?

Start dates in the following network logic diagram are defined as early morning, finish dates are evening.

If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d.

Activity B has a total float of 10 d.

Activity A has a free float of 10 d.

Activity A has a total float of 10 d.

Inline image 1

image.png

Shelly C

unread,
May 22, 2013, 1:50:15 PM5/22/13
to pmp-cert-onli...@googlegroups.com
Hello All,
What do you think is the answer to this question?

Start dates in the following network logic diagram are defined as early morning, finish dates are evening.

If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d.

Activity B has a total float of 10 d.

Activity A has a free float of 10 d.

Activity A has a total float of 10 d.

Inline image 1

On Tue, May 21, 2013 at 9:56 AM, Shanti Narayanan <bsha...@gmail.com> wrote:
image.png

Sivakumar Perumalla

unread,
May 25, 2013, 8:58:58 AM5/25/13
to pmp-cert-onli...@googlegroups.com
the answer is: "

Activity B has a free float of 10 d.

"

As the network diagram, seems to be continuing to next tasks, we can't measure of "TOTAL FLOAT" . ACD is critical path, only B is left with 10d FLOAT.
image.png

Sameer Wakude

unread,
May 25, 2013, 3:04:03 AM5/25/13
to pmp-cert-onli...@googlegroups.com
Activity B has total float of 10d.
Total float = LS - ES = 26 - 16 = 10
Free float = ES of next activity - LS of current activity=31-31=0


On Fri, May 24, 2013 at 9:51 PM, Shelly C <shel...@gmail.com> wrote:
image.png

Shanti Narayanan

unread,
Jun 10, 2013, 9:24:57 PM6/10/13
to pmp-cert-onli...@googlegroups.com
Hi,
 
I got it from christopher scordo 1000QA. Pls note that either they are asking Expected duration or  any one P,M,O.

I have altered the question slightly to get Most likely. Answer is 15 days for M. but if we do that way we get in decimal points(14.33) instead of 15 days. anyways correct answer is 15 days.

33.

James has been managing a hotel construction project in a busy street. He is in the process of estimating

activity durations for building walls and calculates the most likely estimate as 15 days. If pre-fabricated

material is used, it would take no more than 12 days to finish the work. However, the work may be delayed

and could take up to 18 days if less experienced construction workers are used to build the walls. But, the

engineer in-charge of the work estimates the duration as 8 days when pre-fabricated material is used. What

is the expected duration of building walls using the three-point estimate, if the engineer's estimation is

assumed correct?

A.

12 days

B.

11 days

C.

15 days

D.

14 days

 

33.

D - If the engineer is correct, the optimistic estimate can be taken as 8 days. The pessimistic estimate is still 18 days

and the most likely estimate is 15 days. Using the PERT or the three-point technique, the expected activity duration is

calculated using the formula Te = (To + 4Tm + Tp)/6, where Te is the estimated duration, To is optimistic duration,

Tm is the most likely duration and Tp is the pessimistic duration. Hence, Te = (8 +60 +18)/6 = 14 days

(approximately.) Therefore, 14 days is the correct answer. [PMBOK 4th edition, Page 150] [Project Time Management]

On Mon, Jun 10, 2013 at 9:30 PM, Rajeev Polepalli <rajeev.p...@gmail.com> wrote:
Hi Kishore, where did you got 15?

P=18, M= 12 , O= 8

(18 + 4*12+8)/6 = 12.33, so A is correct answer


On Tuesday, June 4, 2013 8:55:12 PM UTC-5, Kishore Vaishnav wrote:
Hi Shanti,

I think the question 1 which you have taken has something wrong. Can you please recheck the question again. I feel the question should be something like this...

James has been managing a hotel construction project in a busy street. He is in the process of estimating activity durations for building walls and calculates the most likely estimate as 15 days. However, the work may be delayed and could take up to 18 days if less experienced construction workers are used to build the walls. But, the engineer in- charge of the work estimates the duration as 8 days when prefabricated material is used. What is the expected duration of building walls using the three-point estimate, if the engineer's estimation is assumed correct?

A) 12 days

B) 11days

C) 15 days

D) 14 days


Answer should be D.  (P+4M+0)/6=(18+4*15+8)/6 = 86/6=14.33. 

If not, do you have the answer for the same with explanation, it would be great if you can share it.

regards,
KKV



--
Thanks,
Shanti

Bibi Razia

unread,
Jun 10, 2013, 10:47:01 PM6/10/13
to pmp-cert-onli...@googlegroups.com
Hi Shanti,

Go through the following link, you may be able to find many answers to your numerical problems. 


Best Regards
Razia, PMP.
Reply all
Reply to author
Forward
0 new messages