Q- You have been assigned as a project manager to a software project. While you and your team are working on a WBS (work breakdown structure), estimations for activity durations based on the activity list vary significantly. Which additional documents may help you clarify this situation?
Milestone list and scope baseline. Project schedule network diagrams and human resource plan. Activity cost estimates and scope baseline. Activity attributes and project scope statement.
My Answer - D (define scope o/p - scope statement which will be use here)__._,_.___