Nicolas vautrin

unread,
Apr 26, 2013, 9:51:50 AM4/26/13
to or-tools...@googlegroups.com

Hello,

Your library is excellent very good job ....

I'm not fluent in english as I'm not a good writer in my natural language (Francais) so I copy/paste my need ;)

Is there a way in or-tools to take into account or modeling calendar resources ?
Are tasks breakables ?

House building with resource calendars

This is a problem of building five houses in different locations; the masonry, roofing, painting, and so forth. Some tasks must necessarily take place before others and these requirements are expressed through precedencesubject to.
There are two workers and each task requires a specific worker. The worker has a calendar of days off that must be taken into account. The objective is to minimize the overall completion date.
To access this example, go to: examples/opl/sched_calendar.
See also the Adding Calendars to the House Building Problem section of the Language User's Manual, where this problem is discussed in more detail.

PS : this example come from ILOG IBM, they introduce a intensity notion