We made a couple of important decisions at the last Gecko 1.9 meeting
about the Alpha scheduling:
* We will do date driven alpha releases on a one-month cadence
* Any very high risk changes must be landed on the trunk two weeks
before code freeze to ensure proper baking
I've updated the main FF3 schedule page to reflect the major change
freeze date, code freeze date, and release date for the next two
Alphas and a draft for beta 1 (*draft*). If you click through the
Alpha5 you'll also see a check list I've cribbed from our maintenance
releases to help make the Alpha release more straightforward.