As we discussed a bit at today's development call, we're going to be moving the code freeze for Beta 1 to *Sept 30*. This schedule adjustment will better allow us to incorporate feedback from the Alpha on exciting features like worker threads before Beta, and adjusts for some of the impact of MU on build and release resources.
Beta 2 will be after Beta 1, unsurprisingly, likely returning to the 4 week cadence and freezing on Oct 28th.
Alpha 2 builds will be produced using the code from Aug 19, as before, and we should have a schedule for the build availability and release pretty shortly. (Likely around Sept 2, if you made me guess. Don't make me guess.)
Seem that I need to start dialing into wed meetings again.
Does that make a string freeze for Beta 1 (not the final product string freeze) to be on the 25th 23:59 PST? Fri-Mon for localization, Tuesday for shipped-locales?
Axel
Mike Shaver wrote: > As we discussed a bit at today's development call, we're going to be > moving the code freeze for Beta 1 to *Sept 30*. This schedule > adjustment will better allow us to incorporate feedback from the Alpha > on exciting features like worker threads before Beta, and adjusts for > some of the impact of MU on build and release resources.
> Beta 2 will be after Beta 1, unsurprisingly, likely returning to the 4 > week cadence and freezing on Oct 28th.
> Alpha 2 builds will be produced using the code from Aug 19, as before, > and we should have a schedule for the build availability and release > pretty shortly. (Likely around Sept 2, if you made me guess. Don't > make me guess.)
On Thu, Aug 28, 2008 at 2:24 AM, Axel Hecht <l...@mozilla.com> wrote: > Seem that I need to start dialing into wed meetings again.
Maybe, but not for this case -- the discussion was "we propose this, there will be a dev.planning thread today, if it causes major problems then please call them out in the thread".
> Does that make a string freeze for Beta 1 (not the final product string > freeze) to be on the 25th 23:59 PST? Fri-Mon for localization, Tuesday > for shipped-locales?
I would expect string freeze to shift by 3 weeks as well, unless, again, that causes problems for some reason. If you're suggesting that time, then yes, I support your suggestion, but I think l10n makes that call, so I guess you're informing us! :)
Mike Shaver wrote: > On Thu, Aug 28, 2008 at 2:24 AM, Axel Hecht <l...@mozilla.com> wrote: >> Seem that I need to start dialing into wed meetings again.
> Maybe, but not for this case -- the discussion was "we propose this, > there will be a dev.planning thread today, if it causes major problems > then please call them out in the thread".
>> Does that make a string freeze for Beta 1 (not the final product string >> freeze) to be on the 25th 23:59 PST? Fri-Mon for localization, Tuesday >> for shipped-locales?
> I would expect string freeze to shift by 3 weeks as well, unless, > again, that causes problems for some reason. If you're suggesting > that time, then yes, I support your suggestion, but I think l10n makes > that call, so I guess you're informing us! :)