I plan on running conduit at the beginning of next week. I'll need some help moving the two benches away from the wall, removing ceiling tiles and other fun stuff. Brett has graciously donated the wire and conduit that will needed to run the sub panel. The overall goal is to install a 60 amp sub panel, 4-6 110v outlets, and two 30A 220v twist lock outlets for the welder and the compressor. This will more than likely take all week to complete.
Dru: If you are able to get a load center, I will need it by Monday. If not Lowe's has an Eaton 125-amp 6 breaker for 22 bucks and the ground bar is another 6 bucks.