施工阶段时间荷载是一个什么概念
0 views
Skip to first unread message
路桥人生
unread,
Sep 1, 2006, 3:09:34 AM
9/1/06
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to 阳光软件.midas-civil
江老师请问,施工阶段时间荷载是一个什么概念?它的取值,对徐变有什么影响?在定义施工阶段的时候不是有龄期与持续时间的定义吗,为什么还要定义施工阶段时间荷载呢?这两者中有联系吗?
谢谢指导。
江安
unread,
Sep 1, 2006, 3:15:28 AM
9/1/06
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to midas...@googlegroups.com
如三跨连续刚构,二个墩子在施工时间有差异,1号墩比2号墩晚60天,为了建模方便,将二个墩按同一步骤安装。可是,徐变与损失不一样啊!这个时间荷载就是在计算徐变时,人为在材龄上增加的天数。
施工阶段中的材龄是迟续的,而时间荷载则是额外的。