In the future, please post your Project Server 2007 questions to the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
the most likely causes for the problem are:
1. The PM did not publish the project using File - Publish. Tasks do not
show up on the team members' My Tasks page until the PM publishes the
project.
2. If the PM did publish the project, then he may have set the Booking type
value to Proposed in the Build Team dialog (click Tools - Build Team from
Enterprise and set the Booking value to Committed, and then publish again).
3. The My Tasks page shows only Current Tasks by default and the tasks in
question are too far in the future to qualify as Current Tasks (normally 10
days in the future). The user can click the Settings pick list menu and
select the View Options item on the list, and then deselect the Show only
current tasks item and click the Apply button.
Hope this helps.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"