I would like to know whether it is possible to delete a calender that has
been entered incorrectly.

Gérard Ducouret

unread,
Nov 27, 2007, 4:27:06 AM11/27/07
to
Evan,

Tools / Organizer / Calendars : select the calendar and Click Delete

Gérard Ducouret

"Evan" <Ev...@discussions.microsoft.com> a écrit dans le message de news:
CB111D5C-C1CB-4C04...@microsoft.com...

Evan

unread,
Nov 27, 2007, 5:22:00 AM11/27/07
to
Thanks a lot realy appreciate it

Gérard Ducouret

unread,
Nov 27, 2007, 7:35:24 AM11/27/07
to
You are welcome Evan,

Gérard Ducouret

"Evan" <Ev...@discussions.microsoft.com> a écrit dans le message de news:

5757ABBA-7D38-40C8...@microsoft.com...

need to delete a calendar. I went to @discussions.microsoft.com I need to delete a calendar. I went to

unread,
Feb 22, 2009, 1:03:01 PM2/22/09
to

I need to delete a calendar. I went to

unread,
Feb 22, 2009, 1:07:01 PM2/22/09
to
Gerard

HELP! I went to tools then selected calendar but could not click delete.
It was not highlighted.

JulieS

unread,
Feb 22, 2009, 2:31:36 PM2/22/09
to
Hi,

Check again -- It's Tools > Organizer. Click the calendar tab.
Select the individual calendar and then click the delete button.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"I need to delete a calendar. I went to"
<Ineedtodeletea...@discussions.microsoft.com> wrote in
message news:1A804E63-5C91-4969...@microsoft.com...

jldrake

unread,
Feb 8, 2010, 1:17:03 PM2/8/10
to
I went into the Calendar folder and followed the instructions listed above
several times and can't seem to make it disappear. There are still entries
in the old calendar that I transferred to my new 2007 one and don't need them
any more. do I need to clear all those entries before I can clear the one I
want to? That did not seem to be the case for the other one that I got rid
of.

JulieS

unread,
Feb 8, 2010, 2:08:49 PM2/8/10
to
Hi JLDrake,

Unfortunately, your post did not carry over the instructions that you've
followed, so it's tough to tell what is going on here.

So, a few assumptions: you are using Project 2007. When you view Tools
> Change Working Time, you are seeing calendars appear that you do not
wish to show any longer?

You should be able to delete base calendars that are not in use in the
Project file through Tools > Organizer and click on the calendar tab.
Select the calendar on the right side and click the delete button.

Is that working?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project