I have tried using Start, Finish (week 5), Start1, and Finish1 (week 9),
with separate durations for each, but the program only recognizes the first
Start and Finish. If the past, I have just used one set of Start and Finish
dates, then calculated out the rest manually, but I'm wondering if there is
an easier way to do this.
The program will call a task an undertaking with just one finish I'm afraid.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"ehimrod" <ehi...@discussions.microsoft.com> wrote in message
news:741B542B-6151-4946...@microsoft.com...
Now you can link the subtasks together with additional detail including what
happens on Week 5 and Week 9.
Two important milestones you may want to include underneath the summary task
are (A) Shipment Authorized to Commence Work, and, (B) Shipment Complete
Once you are done with "Shipment #1" you essentially have a template for the
other 9 shipments. Collapse the summary task, copy it, and then paste it 9
times.
If you want to cascade (waterfall) the shipments you can link "B" from
Shipment #1 to "A" in "Shipment #2" (etc.) then the who thing will waterfall
nicely after you do this for every shipment.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
"Jan De Messemaeker" wrote:
> .
>
For discussion, lets say those two actions each take one hour to perform.
How about modeling it this way ....
1 Shipment 1
1.1 Shipment Arrives, Duration 0 (milestone)
1.2 Action 1, Duration 1h, Predecessor 1.1FS+5w
1.3 Action 2, Duration 1h, Predecessor 1.2FS+4w
1.4 Shipment Leaves, Duration 0 (milestone), Predecessor 1.3 FS+1w
2 Shipment 2 ....
--
Steve House
MS Project Trainer & Consultant
"ehimrod" <ehi...@discussions.microsoft.com> wrote in message
news:741B542B-6151-4946...@microsoft.com...