I assume you mean auditing function for the Schedule? If so the answer is
no. You can see when and who has last modified the schedule but not what.
That is different when you want to track timesheet data or workspace related
data. The timesheet has an audit that you can switch on under server
settings and you can create reports of this log. that will take care of the
timesheet data. Risks, Issues and any other list within your workspace can
be switched on with Version history. that will give you a detail breakdown
what has changed by whom when.
I hope that helps
--