Google Groups no longer supports new Usenet posts or subscriptions. Historical content remains viewable.
Dismiss

Hours split in Project Pro 2007 when updating Project from PWA 200

3 views
Skip to first unread message

Marcus

unread,
Oct 30, 2007, 6:52:00 PM10/30/07
to
We have a situation where the actual hours for several resources have
reverted to fractional hours in Project Professional and we are not sure why.
As just one example, a resource imports a timesheet containing whole (not
fractional) hours to update his tasks, and then submits the tasks update to
the project manager.

The project manager approves the task updates and then sees that the updated
hours are not sucked into the project as they were entered into the time
sheet.

M T W T F
5h 9h 6h 8h 5h

in PWA becomes...

M T W T F
2.5h 2.5h 9h 6h 8h

in Project Professional - the 5 hours on Monday was split in two between
Monday and Tuesday and then the rest of the hours were all offset a day going
forward.

Can anyone offer an explanation? Thank you.

Rod Gill

unread,
Oct 30, 2007, 8:12:43 PM10/30/07
to
Which version of Project Server and this is with Project Server Timesheet
rather than a 3rd party timesheet?

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx


----------------------------------------------------------------------------------------------------


"Marcus" <Mar...@discussions.microsoft.com> wrote in message
news:4E54012D-32F2-4B69...@microsoft.com...

Marcus

unread,
Oct 30, 2007, 8:31:00 PM10/30/07
to
We are using Project Server 2007 and the timesheet functionality provided by
Project Web Access.

/pd

unread,
Nov 1, 2007, 4:56:06 PM11/1/07
to
are the users updating the field "Work Remaining" on the task updates ?

e.g Task1 = A


M T W T F
> 5h 9h 6h 8h 5h

but users updates 2.5 hrs work on M, so therefore the remaining works gets
pushed down the timelines which reflects ;

> M T W T F
> 2.5h 2.5h 9h 6h 8h

MSP will automatically do this for the task /resource ..when updates are
pushed thru at the PWA level..

/pd

Vadim Gerya, PMP

unread,
Nov 1, 2007, 7:11:02 PM11/1/07
to
Hi Rod ! I have recently discovered the same problem ! It is for MSEPM2007

Now I am trying to understand why timescaled actuals splited unpredictedly
between days. Timesheet does not matter, you may see such spliting in
Project 2007 Pro in timescaled assignment views (Task Usage for eaxmple)

I was totally sure that actuals could not be changed after approving ones by
PM. But ...
I think it may depends on administrative time entered by user.
If I find something new I post ..

--
Vadim Gerya, PMP

aaronmiller

unread,
Dec 22, 2009, 12:19:29 PM12/22/09
to
Folks, we are on PS2007 SP2 with April CU. We are also using MS Project Pro 2007 with same SP levels.

We have just started migrating our projects from 2003 to 2007 and have discovered some of our tasks are showing "bizarre" actual hours splits.

I haven't seen this resolved anywhere else.

What was the cause or resolution here?

thanks,
Aaron Miller, PMP
Jack Henry & Associates

VadimGeryaPM wrote:

Hi Rod ! I have recently discovered the same problem !

01-Nov-07

Hi Rod ! I have recently discovered the same problem ! It is for MSEPM2007

Now I am trying to understand why timescaled actuals splited unpredictedly
between days. Timesheet does not matter, you may see such spliting in
Project 2007 Pro in timescaled assignment views (Task Usage for eaxmple)

I was totally sure that actuals could not be changed after approving ones by
PM. But ...
I think it may depends on administrative time entered by user.
If I find something new I post ..

--
Vadim Gerya, PMP


"Rod Gill" wrote:

Previous Posts In This Thread:

On Tuesday, October 30, 2007 6:52 PM
Marcu wrote:

Hours split in Project Pro 2007 when updating Project from PWA 200


We have a situation where the actual hours for several resources have
reverted to fractional hours in Project Professional and we are not sure why.
As just one example, a resource imports a timesheet containing whole (not
fractional) hours to update his tasks, and then submits the tasks update to
the project manager.

The project manager approves the task updates and then sees that the updated
hours are not sucked into the project as they were entered into the time
sheet.

M T W T F
5h 9h 6h 8h 5h

in PWA becomes...

M T W T F
2.5h 2.5h 9h 6h 8h

in Project Professional - the 5 hours on Monday was split in two between
Monday and Tuesday and then the rest of the hours were all offset a day going
forward.

Can anyone offer an explanation? Thank you.

On Tuesday, October 30, 2007 8:12 PM
Rod Gill wrote:

Which version of Project Server and this is with Project Server Timesheet
Which version of Project Server and this is with Project Server Timesheet
rather than a 3rd party timesheet?

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx


----------------------------------------------------------------------------------------------------


"Marcus" <Mar...@discussions.microsoft.com> wrote in message
news:4E54012D-32F2-4B69...@microsoft.com...

On Tuesday, October 30, 2007 8:31 PM
Marcu wrote:

We are using Project Server 2007 and the timesheet functionality provided by
We are using Project Server 2007 and the timesheet functionality provided by
Project Web Access.

"Rod Gill" wrote:

On Thursday, November 01, 2007 4:56 PM
p wrote:

are the users updating the field "Work Remaining" on the task updates ?
are the users updating the field "Work Remaining" on the task updates ?

e.g Task1 = A


M T W T F

but users updates 2.5 hrs work on M, so therefore the remaining works gets

pushed down the timelines which reflects ;

MSP will automatically do this for the task /resource ..when updates are
pushed thru at the PWA level..

/pd

"Marcus" wrote:

On Thursday, November 01, 2007 7:11 PM
VadimGeryaPM wrote:

Hi Rod ! I have recently discovered the same problem !
Hi Rod ! I have recently discovered the same problem ! It is for MSEPM2007

Now I am trying to understand why timescaled actuals splited unpredictedly
between days. Timesheet does not matter, you may see such spliting in
Project 2007 Pro in timescaled assignment views (Task Usage for eaxmple)

I was totally sure that actuals could not be changed after approving ones by
PM. But ...
I think it may depends on administrative time entered by user.
If I find something new I post ..

--
Vadim Gerya, PMP


"Rod Gill" wrote:


Submitted via EggHeadCafe - Software Developer Portal of Choice
Visual Basic And FTP Project Sample
http://www.eggheadcafe.com/tutorials/aspnet/72ea3972-d36c-4c8a-98bb-cfe42b6ff731/visual-basic-and-ftp-proj.aspx

Gary Chefetz

unread,
Dec 23, 2009, 8:20:58 AM12/23/09
to
Aaron:

I would strongly recommend that you upgrade your system to the December CU,
which contains all of the latest fixes for actual work issues. Eliminate
this source of potential problems and then post if you have continue to see
issues so that we can help you understand or work around them.

--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com

"Aaron Miller" wrote in message news:20091222121...@jackhenry.com...

0 new messages