How do I set the start date to DEFAULT to a more current date ????
-- Joe
The page responds to the data it receives. I suspect that if you look at the
projects, you have a project with a bad date in it.
--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com
"Joe Morton" <J...@discussions.ms.com> wrote in message
news:106FBAAD-A515-4011...@microsoft.com...
If an enterprise project contains a very long-Duration task, spanning
months, quarters, or even years, the Task Updates page will always default
to the Start date of that long-Duration task. This is the default behavior
of the tool, by the way. Does this explain your issue? Let us know.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"Joe Morton" <J...@discussions.ms.com> wrote in message
news:106FBAAD-A515-4011...@microsoft.com...