How do I delete an Enterprise Resource.

0 views
Skip to first unread message

Khurshid

unread,
Nov 18, 2003, 2:49:37 PM11/18/03
to
Hello,

Can some one tell me how I can delete a enterprise from
project server?
Thanks
Khurshid

Josh

unread,
Nov 18, 2003, 4:26:30 PM11/18/03
to
I too would like to know how to do this. I have tried to
merge the resources that I do not want and I get the
following: "Project cannot merge an enterprise resource
account into another account." Help...
Thanks,Josh
>.
>

Lon Swain

unread,
Nov 18, 2003, 5:09:49 PM11/18/03
to

to the best of my knowledge, you can only make an
Enterprise Resource "inactive". If you want to delete an
ER completely, the only way I know is to do it manually in
SQL which requires that you have a very good idea what
you're doing. Not recommended unless you understand the
underlying schema.

>.
>

Kevin Flanagan

unread,
Nov 19, 2003, 8:40:20 AM11/19/03
to
You really do not want to delete a resource. Any
assignments made to that resource will be lost for
historical purpose. The better option is to merge the
account you want to delete into a similar resource.

Kevin

>.
>

Josh

unread,
Nov 19, 2003, 11:29:03 AM11/19/03
to
Is this possible in Proj Server 2002?
>.
>

martha....@lafarge.com

unread,
Nov 20, 2003, 4:57:56 AM11/20/03
to
I agree, don't delete it. You can adjust it, if the problem is a
spelling error, but to delete it would be deleting all historical
information. Instead, make in inactive as suggested.

Have fun!