Hello Ben, 

this is not easy. Because the lead can be entered
- in the Dependency inspector by a selected dependency line, 
- in der Dependencies inspector by  a selected activity row
-or in the #Successor column.

All above do not work in a selection of more than one items.

Please see attached screenshots.
Best regards, Vicky
On 7 May 2013, at 23:11, Ben Sutherland <b...@presentcreative.com> wrote:

is it possible to set the lead lag time for multiple entries at once?  I have a lot of tasks that are linked FS and I want to make it so they all have a lead/lag of 1 day.  is it possible to set multiple entries at once?  or do I have to click on each entry individually and set it?

thanks


--
You received this message because you are subscribed to the Google Groups "Merlin2Users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to merlin2users...@googlegroups.com.
To post to this group, send email to merlin...@googlegroups.com.
Visit this group at http://groups.google.com/group/merlin2users?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

Reply all
Reply to author
Forward
0 new messages