In case you try to do this in Merlin views, what about using utilization view,
expand all assignments of your resources,
do an advanced search for expected start within the specific range
and if require the report by resource, add a criterion for "title" contains the name of your resource.
Now you can print the utilization view showing only the filtered tasks.
Best regards, Vicky
in the utilization view you see resources and their assignments.
Just create an empty project with one task and one resource.
Being in the 'Activities' view notice that your project has 2 rows, top most row, row 0 with the project info
second row, row 1 with the task.
Now assign the task to a resource, expand the activity and see your project has 3 rows:
Row 3 is the assignment of this resource to that task.
If you now switch to the utilization view and enable the column "#" you will see the assignment rows are transferred not the tasks. That's how this is defined to work.
So, additional titles, or notes entered on the task's row won't be viewed in the utilization, if they are not entered on the assignment rows.
>Is there a way to configure this type of utilisation view to show the fields associated with the activity rather than the person / activity pairing? So the Additional Title >/ Notes entry showing against each user in this report are the same (and the same as that which shows in the Activities view)
This is not possible. Sorry.
You would need to report this in a separate window.
For example in the "information" report, which reports all informations in a project.
If you want to modify the "information" report further, for example to output not all tasks but only those with notes, feel free to use the attached template "information report (plus)"
Best regards, Vicky
I would suggest you check this report screenshot and tell me which columns are you missing.
Maybe I could implement a new version of this report to show the desired columns.
Best regards, Vicky
> --
> You received this message because you are subscribed to the Google Groups "Merlin2Users" group.
> To view this discussion on the web visit https://groups.google.com/d/msg/merlin2users/-/q5-tJzXzPTwJ.
> To post to this group, send email to merlin...@googlegroups.com.
> To unsubscribe from this group, send email to merlin2users...@googlegroups.com.
> For more options, visit this group at http://groups.google.com/group/merlin2users?hl=en.
Here a screenshot of an output sample
and a screenshot of the report options.
To install:
• Extract the zip first
• place the contained mrept package under the following path of your mac: ~/Library/Application Support/Merlin/Reports
• (in case you have no “Reports” folder please create it first and pay attention to name it exactly as “Reports”)
• restart your Merlin and
• call File > New Report… to find the new report called “Assignment report”.
Options:
• output either expected work or actual work / remaining work
• select a duration for the report to show only uncompleted assignments on that period
• output project names (if in a master project)
• output notes
• output additional titles
Please let me know if it helps you further.
Best regards, Vicky