> Thanks Vicky. I tried that yet it didn't work. I enter the new start date and then my very first row turns red though the date does not change to what I entered. None of the other dates change.
Yes I see.
So click the top most row,
Edit > Clear Actual Values
Check planned start dates on row 1, they are set with earliest and latest start on Jan 31st 2011. So you can plan your project to start on other dates, but the works on this group will always start on Jan 31st 2011
Remove both date constrains, or just the latest start date by a click onto it (x)
Define a new project start, for example today
See your project starting today and your tasks scheduled accordingly.
Check also the icons in the "info" column. You maybe want to remove a start dates pointing to 2007.
Best regards, Vicky