It has been a while, does anyone has any news at all ? construction status, payments, legal case etc

140 views
Skip to first unread message

mayank sinha

unread,
Apr 7, 2015, 4:35:50 AM4/7/15
to koltepatilr...@googlegroups.com
It has been a while, does anyone has any news at all ? construction status, payments, legal case etc

Shobit Srivastava

unread,
Apr 7, 2015, 4:58:12 AM4/7/15
to mayank sinha, koltepatilr...@googlegroups.com
Hi Mayank,
True, they have been unusually quiet, last i got a mail from their CRM Team asking for the due payment because there would be revision in service tax from April onwards.
I also spoke with john about 2-3 weeks back, what he told me was the same as what they had been telling us that the litigation in nearing its closure and since they have a strong case, they will not likely go for a settlement.
About the construction status, I was told that it was getting delayed because people are not paying up in time and we can expect completion by December. 

If anyone has any other update, please do tell us.
Regards
Shobit K

On Tue, Apr 7, 2015 at 2:05 PM, mayank sinha <mayanks...@gmail.com> wrote:
It has been a while, does anyone has any news at all ? construction status, payments, legal case etc

--
You received this message because you are subscribed to the Google Groups "KoltePatilRaagaFamilies" group.
To unsubscribe from this group and stop receiving emails from it, send an email to koltepatilraagafa...@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

mail2subhashjha

unread,
Apr 7, 2015, 2:05:10 PM4/7/15
to Shobit Srivastava, mayank sinha, koltepatilr...@googlegroups.com
In last 4 month construction work has slowed down or its on hold. From my information Koltepatil has not done payments to their vendors which will result into furthet delay.  they have started their 2nd project and that has shifted their focus and resource.

So I am doubtful about December 2015 date. 


Sent via the Samsung GALAXY S® 5, an AT&T 4G LTE smartphone

Asis Mohanty

unread,
Apr 7, 2015, 10:11:45 PM4/7/15
to Subhash Jha, koltepatilr...@googlegroups.com, mayank sinha, Shobit Srivastava

I believe 80% folks have already paid all the due. Can we meet up and discuss with KP.

Regards
Asis Mohanty

kapoor...@gmail.com

unread,
May 2, 2015, 2:47:03 AM5/2/15
to koltepatilr...@googlegroups.com

Went to the site on 1 May , Uploading latest pics .. With current status , it looks to be delayed . Also the Nearby property from Supertech ( 100 mtr away ) construction is @ 2nd floor .  I asked About the Quary & was told that they  don't hear blasts happening any more .

Rajan
On Tuesday, April 7, 2015 at 2:05:50 PM UTC+5:30, mayank sinha wrote:
WP_000097.jpg
WP_000085.jpg
WP_000087.jpg
WP_000086.jpg
WP_000096.jpg

kapoor...@gmail.com

unread,
May 2, 2015, 2:54:54 AM5/2/15
to koltepatilr...@googlegroups.com

Here is the link to track case status , There is a hearing today 2 May 2015 where evidence would  be presented ..


On Tuesday, April 7, 2015 at 2:05:50 PM UTC+5:30, mayank sinha wrote:

SanT

unread,
May 6, 2015, 4:52:19 AM5/6/15
to koltepatilr...@googlegroups.com
We have it in agreement that, post September, they will pay some compensation monthly, if their construction is still not completed. 

mayank sinha

unread,
May 6, 2015, 7:19:28 AM5/6/15
to koltepatilr...@googlegroups.com
Hi San T, 

Thanks for this info on "post September payment". Can you please let us know for our awareness and knowledge,which part of the contract specifies this and how theat compensation will be calculated ?

SanT

unread,
May 6, 2015, 7:46:49 AM5/6/15
to koltepatilr...@googlegroups.com
Check the point no 15.


On Tuesday, 7 April 2015 14:05:50 UTC+5:30, mayank sinha wrote: