I have not recieved any request. I have booked a flat in Tower 2.
Since I am going for a bank loan and the application is reviewed by bank at this stage. I have informed them that the payments after the 20% intial payments will be done by bank.
regards, Praveen On Fri, Oct 14, 2011 at 4:37 AM, davuluri laxman rao <dlax...@gmail.com>wrote:
Dear all, I have paid 5% cellar 2 completion stage for flat 404,tower 2. I had visited the site 3 days back. tower 2 cellar 2 is completed, 1st floor work is going on. tower 1 is getting delayed as they have changed the plan to construct 4 bedroom to 2 bedroom due to lack of demand for 4 bed rooms, I was told. Regarding payment intimation for cellar 2 completion, those who are going for bank loan for this amt, has to get a NOC from Union Bank of India, Newdelhi, where from Emami has taken loan for the project. UBI will issue the NOC to individual flats based on the sanction letter for loan for individual loans of buyers. So those who are going for bank loan, may submit copy of sanction letter to emami, who in turn will submit to UBI for issue of NOC. Others, may pay 5% for tower 2 if intimation is received for payment. regrds Antony hyderabad Mobile 8008400465
On Fri, Oct 14, 2011 at 9:09 AM, Kaustav Sinha Ray <k.sinha....@gmail.com>wrote:
cdantonyn...@gmail.com> wrote: > Dear all, > I have paid 5% cellar 2 completion stage for flat 404,tower 2. I had > visited the site 3 days back. tower 2 cellar 2 is completed, 1st floor work > is going on. tower 1 is getting delayed as they have changed the plan to > construct 4 bedroom to 2 bedroom due to lack of demand for 4 bed rooms, I > was told. Regarding payment intimation for cellar 2 completion, those who > are going for bank loan for this amt, has to get a NOC from Union Bank of > India, Newdelhi, where from Emami has taken loan for the project. UBI will > issue the NOC to individual flats based on the sanction letter for loan > for individual loans of buyers. So those who are going for bank loan, may > submit copy of sanction letter to emami, who in turn will submit to UBI for > issue of NOC. Others, may pay 5% for tower 2 if intimation is received for > payment. > regrds > Antony > hyderabad > Mobile 8008400465
> On Fri, Oct 14, 2011 at 9:09 AM, Kaustav Sinha Ray <k.sinha....@gmail.com>wrote:
>> tower2
>> On Fri, Oct 14, 2011 at 2:07 AM, davuluri laxman rao <dlax...@gmail.com>wrote:
>>> Hi,
>>> Is that for tower 1 or 2
>>> Regards >>> Laxman
>>> On Thu, Oct 13, 2011 at 11:11 AM, Kaustav Sinha Ray < >>> k.sinha....@gmail.com> wrote:
>>>> Hi,
>>>> Anyone notified by Emami for the 5% part payment on account of Cellar 2 >>>> completion? I received the same today.
> wrote: > Dear all, > I have paid 5% cellar 2 completion stage for flat 404,tower 2. I had > visited the site 3 days back. tower 2 cellar 2 is completed, 1st floor work > is going on. tower 1 is getting delayed as they have changed the plan to > construct 4 bedroom to 2 bedroom due to lack of demand for 4 bed rooms, I > was told. Regarding payment intimation for cellar 2 completion, those who > are going for bank loan for this amt, has to get a NOC from Union Bank of > India, Newdelhi, where from Emami has taken loan for the project. UBI will > issue the NOC to individual flats based on the sanction letter for loan > for individual loans of buyers. So those who are going for bank loan, may > submit copy of sanction letter to emami, who in turn will submit to UBI for > issue of NOC. Others, may pay 5% for tower 2 if intimation is received for > payment. > regrds > Antony > hyderabad > Mobile 8008400465
> On Fri, Oct 14, 2011 at 9:09 AM, Kaustav Sinha Ray < > k.sinha....@gmail.com> wrote:
>> tower2
>> On Fri, Oct 14, 2011 at 2:07 AM, davuluri laxman rao <dlax...@gmail.com>wrote:
>>> Hi,
>>> Is that for tower 1 or 2
>>> Regards >>> Laxman
>>> On Thu, Oct 13, 2011 at 11:11 AM, Kaustav Sinha Ray < >>> k.sinha....@gmail.com> wrote:
>>>> Hi,
>>>> Anyone notified by Emami for the 5% part payment on account of Cellar 2 >>>> completion? I received the same today.
cdantonyn...@gmail.com> wrote: > Dear all, > I have paid 5% cellar 2 completion stage for flat 404,tower 2. I had > visited the site 3 days back. tower 2 cellar 2 is completed, 1st floor work > is going on. tower 1 is getting delayed as they have changed the plan to > construct 4 bedroom to 2 bedroom due to lack of demand for 4 bed rooms, I > was told. Regarding payment intimation for cellar 2 completion, those who > are going for bank loan for this amt, has to get a NOC from Union Bank of > India, Newdelhi, where from Emami has taken loan for the project. UBI will > issue the NOC to individual flats based on the sanction letter for loan > for individual loans of buyers. So those who are going for bank loan, may > submit copy of sanction letter to emami, who in turn will submit to UBI for > issue of NOC. Others, may pay 5% for tower 2 if intimation is received for > payment. > regrds > Antony > hyderabad > Mobile 8008400465
> On Fri, Oct 14, 2011 at 9:09 AM, Kaustav Sinha Ray < > k.sinha....@gmail.com> wrote:
>> tower2
>> On Fri, Oct 14, 2011 at 2:07 AM, davuluri laxman rao <dlax...@gmail.com>wrote:
>>> Hi,
>>> Is that for tower 1 or 2
>>> Regards >>> Laxman
>>> On Thu, Oct 13, 2011 at 11:11 AM, Kaustav Sinha Ray < >>> k.sinha....@gmail.com> wrote:
>>>> Hi,
>>>> Anyone notified by Emami for the 5% part payment on account of Cellar 2 >>>> completion? I received the same today.
> On Fri, Oct 14, 2011 at 12:03 AM, Anthony Chakkalakal < > cdantonyn...@gmail.com> wrote:
>> Dear all, >> I have paid 5% cellar 2 completion stage for flat 404,tower 2. I had >> visited the site 3 days back. tower 2 cellar 2 is completed, 1st floor work >> is going on. tower 1 is getting delayed as they have changed the plan to >> construct 4 bedroom to 2 bedroom due to lack of demand for 4 bed rooms, I >> was told. Regarding payment intimation for cellar 2 completion, those who >> are going for bank loan for this amt, has to get a NOC from Union Bank of >> India, Newdelhi, where from Emami has taken loan for the project. UBI will >> issue the NOC to individual flats based on the sanction letter for loan >> for individual loans of buyers. So those who are going for bank loan, may >> submit copy of sanction letter to emami, who in turn will submit to UBI for >> issue of NOC. Others, may pay 5% for tower 2 if intimation is received for >> payment. >> regrds >> Antony >> hyderabad >> Mobile 8008400465
>> On Fri, Oct 14, 2011 at 9:09 AM, Kaustav Sinha Ray < >> k.sinha....@gmail.com> wrote:
>>> tower2
>>> On Fri, Oct 14, 2011 at 2:07 AM, davuluri laxman rao <dlax...@gmail.com>wrote:
>>>> Hi,
>>>> Is that for tower 1 or 2
>>>> Regards >>>> Laxman
>>>> On Thu, Oct 13, 2011 at 11:11 AM, Kaustav Sinha Ray < >>>> k.sinha....@gmail.com> wrote:
>>>>> Hi,
>>>>> Anyone notified by Emami for the 5% part payment on account of Cellar 2 >>>>> completion? I received the same today.
I am planning to book 2 BHK and paying 5% today evening. While
searching, I found this group with lot of useful information.
I am buying for the rate of 2850 per sft.(please let me know is it
reasonable? As Manjeera is quoting very high). They are telling the
possession is on March 2013.. are you all aware of this date?? what
happened to Dec2012 delivery??
I guess it is the practice of builder to postpone the date.
Please let me know if you have any suggestion for me.
Sandesh
9000 777 961
On Oct 13, 9:11 pm, Kaustav Sinha Ray <k.sinha....@gmail.com> wrote:
I visited the site on Saturday , and observed in Tower 2 ,Celler 2 and 1 ceiling is completed, currently level zero/ground floor wall is 20-25% complete. The Club house missed my notice- I mean if anything was started it would have caught my observation. Yes, as u rightly pointed out the club house is the pain of majority of the projects. On the notification for payment, it is unwarranted that they asked for 2 payments of 5 pc each. If they delayed the notification for cellar 2, they should give some interval in asking for Cellar 1 and not ask a chunk. Infact on my inquiry did I come to know about cellar 2 payment notification, which I paid on Saturday.
Another note for Tower 1 flat owners, Emami is changing few or all 4 bed room flats to 3.5 bedroom flats and the cellar 2 for the same has started.
I have a feeling that the construction rate is fine, but we never know if it is good enough for mar 2013 delivery at this point.
Request updates from other group members, whenever applicable.
Thanks all.
Regards, Kaustav
On Tue, Oct 18, 2011 at 5:21 PM, Naseer Mohammed <naseer...@gmail.com>wrote: