Andrea Tomasini wrote:
> Hi Dennis & Vela,
> do you mean that hiding milestones and sprints together, when a milestone is completed is not enough? The idea was to keep a full milestone (release) open till all the sprint have been completed, and the milestone itself completed, not to loose the overview while in the Roadmap. The risk would be that one would not see how many sprints have been planned for a milestone.
>
> So you close milestones setting them completed?
>
>
Hi, Andrea.
We have very short sprints and have a dozen of completed sprints now for
the milestone. We will have another dozen by the time we complete the
milestone. Yeah, this milestone is rather stretched in time, but we work
that way.
Adding a checkbox "Show already completed sprints" under "Show already
completed milestones" would be the solution for me. "Show already
completed sprints" should be checked by default to mimic the old behavior.
--
Dennis